HomeMy WebLinkAboutResolution No. 2015-46/i Suggested by: Administration
tlec[tyof CITY OF KENAI
KENAI, ALASKA
RESOLUTION NO. 2015 -46
A RESOLUTION OF THE COUNCIL OF THE CITY OF KENAI, ALASKA, AWARDING AN
AGREEMENT FOR CONSTRUCTION OF SWIRES ROAD WATER MAIN EXTENSION AND
BUFFALO RUN WATER MAIN REPLACEMENT 2015 -2016.
WHEREAS, the following bids were received on July 28, 2015;
Bidder
Buffalo Run
Swires Road
Total
Engineer's Estimate
$559,580
$503,410
$1,062,990
Foster Construction
$464,180
$603,338
$1,067,518
Peninsula Construction
$783,640
$830,003
$1,613,643
Chumley's
$449,671.11
$679,676.56
$1,129,347.67
Southcentral
$380,824
1$554,225.80
$ 935,049.80
Coastal Excavation
$653,852 1$1,115,622
1
$1,769,474
and,
WHEREAS, Southcentral Construction, Inc. is the lowest responsive bid; and,
WHEREAS, award to Southcentral Construction, Inc. would be in the best interest of
the City; and,
WHEREAS, the recommendation from City Administration is to award the agreement to
Southcentral Construction, Inc. for the total approximate cost of $935,049.80; and,
WHEREAS, sufficient monies are appropriated.
NOW, THEREFORE, BE IT RESOLVED BY THE COUNCIL OF THE CITY OF KENAI,
ALASKA, that the agreement for the project entitled " SWIRES ROAD WATER MAIN
EXTENSION AND BUFFALO RUN WATER MAIN REPLACEMENT 2015- 2016" be
awarded to Southcentral Construction, Inc. for the total approximate cost of
$935,049.80.
PASSED BY THE COUNCIL OF THE CITY OF KEN KA, is 5th d�3 of AUGUST,
2015.
PAT PORTER, MAY R
ATT
Sandtyo-dAjh, City Clerk
Approved by Finance: ,`
the utyof ZI
KENALALA SKA
�NTO:
FROM:
DATE:
210 Fidalgo Avenue, Kenai, Alaska 99611 -7794
Telephone: (907) 283 -7535, Ext. 236 / FAX: (907) 283 -3014
"Villa9e with a Past, City with a Future"
MEMORANDUM
Rick Koch, City Manager
Sean Wedemeyer, Public Works Director S/w
July 28, 2015
SUBJECT: Award of an agreement for the construction of Swires Road Water
Main Extension and Buffalo Run Water Main Replacement 2015-
2016
Rick,
This memo is in support of a resolution awarding an agreement for the construction of
the Swires Road Water Main Extension and Buffalo Run Water Main Replacement. The
following bids were opened on July 28, 2015.
Bidder
Buffalo Run
Swires Road
Total
Engineer's Estimate
$559,580
$503,410
$1,062,990
Foster Construction
$464,180
$603,338
$1,067,518
Peninsula Construction
$783,640
$830,003
$1,613,643
Chumley's
$449,671.11
$679,676.56
$1,129,347.67
Southcentral
$380,824
$554,225.80
$ 935,049.80
Coastal Excavation
$653,852
$1,115,622
$1,769,474
The scope of work is as follows. Swires Road: Furnish and install approximately 2200
feet of water main. Reconstruct and repave approximately 1870 square yards of paved
street. Water Main Replacement 2015: Furnish & Install approximately 1860' of water
main.
Thank you for your attention to this matter.