A RESOLUTION OF THE COUNCIL OF THE CITY OF KENAI, ALASKA, ADOPTING THE
CITY OF KENAI CAPITAL IMPROVEMENTS PLAN PRIORITY LISTS FOR STATE
FUNDING REQUESTS FOR THE FISCAL YEAR 2017
WHEREAS, the Capital Improvements Plan (CIP) is a guide for capital expenditures;
and,
WHEREAS, the City of Kenai CIP process has involved consideration of existing plans,
programmatic needs and public input; and,
WHEREAS, the CIP compliments the legislative priorities, City Budget and
Comprehensive Plan; and,
WHEREAS, the Kenai City Council held a public hearing on the Capital Improvements
Program adoption on September 16, 2015; and,
WHEREAS, if unforeseen circumstances occur, the City Council authorizes the City
Manager to modify as necessary the City of Kenai's Capital Improvements Plan Priority
Lists for State and Federal Funding Requests for the Fiscal Year 2017, and that any
modification will be brought before Council for approval at the next regularly
scheduled Council meeting.
NOW, THEREFORE, BE IT RESOLVED BY THE COUNCIL OF THE CITY OF KENAI,
ALASKA, adopts the attached City of Kenai Capital Improvements Plan Priority List for
State Funding Requests for the Fiscal Year 2017.
PASSED BY THE COUNCIL OF THE CITY OF KENAI, ALASKA, this 7th day of October,
2015.
PAT PORTER, MAYOR
CITY OF KENAI
CAPITAL IMPROVEMENTS PROGRAM (CIP) PRIORITES
FOR STATE FUNDING REQUESTS GREATER THAN $100,000 FOR
SFY 2017
PRIORITY
PROJECT TITLE
DESCRIPTION
STATE
LOCAL
NOTES /COMMENTS
NUMBER
FUNDING
CONTRIBUTION
REQUEST
Construction of Wastewater Treatment
Plant Upgrades -Phase II
This project is the second phase of a four -phase project.
$ 980,084.00
$ 420,036.00
The City Council passed Resolution No. 2015 -45
Phase II will address improvements to the treatment process
identifying this project as the number one Alaska
to lower ammonia effluent discharge levels in advance of
Department of Environmental Conservation (ADEC)
ammonia limitations which will be included in the next
Municipal Matching Grant ( MMG) priority. A grant
APDES permit renewal. Phase II improvements will also
application for this project was submitted under the ADEC
include replacement of aging, failing, equipment and install
MMG Program.
1
additional equipment to provide redundancy in critical
operating systems. Upgrades to electric - motor -driven
compressor systems will lower operational costs by at least
$60,000 per year. The design is presently being completed
under a separate contract and is presently at the 65%
(Design Development) Phase. The design and construction
documents will be complete by February 2015.
Paving & Improvements to City Streets
The City of Kenai maintains approximately 20 miles of gravel
$ 1,000,000.00
$ 250,000.00
This ongoing infrastructure improvement project has
surfaced roadways within its municipal boundaries. The cost
of maintenance of gravel roadways is high, dust from gravel
improved the safety and operational efficiency of the City's
roadways is a health issue for the elderly & young. The City
roadways. The projects have been designed and
constructed by local consultants and contractors providing
2
maintains an ongoing Local Improvement District (LID)
further economic benefits to the area.
program to pave local streets and roads with the City
providing a 50% cost share for the improvements for some
projects.
Public Safety Building, Boiler Replacement
and HVAC Improvements and installation
This project would install a new HVAC System to replace the
30+ year old system in the Public Safety Building
$ 360,000.00
$ 50,000.00
The HVAC system at the Public Safety Building is old,
of bullet- resistant windows.
which
houses the Kenai Fire Department and Kenai Police
inefficient and in constant need of repairs. The existing
Department. The new energy efficient HVAC system would
sytem is inefficient and energy costs are significantly
greater than what is expected from modem mechanical
3
decrease operational costs. The design and bid documents
sytems.
are complete. With an HVAC system capable of supporting
the building non - opening bullet resistant windows can be
installed. This improvement is consistent with security
improvements undertaken in Police buildings.
Improvements/Renovation of the Kenai
Senior Center,Phase I
This project includes, but is not limited to the demolition and
$ 250,000.00
$ 50,000.00
The building is approximately 25 years old and the glass
replacement of a failing atrium area and expansion of service
atrium in the dining room is leaking and the windows have
areas.
lost their thermal seals. Each year water damage occurs
during the winter and portions of the dining room are
4
unavailable for use by the Senior Clientele. Annually, in
excess of 50,000 meals are served to Senior Citizens in
the Kenai area by the Kenai Senior Center through the
Congregate meal program or the home meal delivery
program. This is an essential facility for the local Senior
population.
Page 1 of 5 Prepared by: R. Koch
CITY OF KENAI
CAPITAL IMPROVEMENTS PROGRAM (CIP) PRIORITES
FOR STATE FUNDING REQUESTS GREATER THAN $100,000 FOR
SFY 2017
PRIORITY
PROJECT TITLE
DESCRIPTION
STATE
LOCAL
NOTESICOMMENTS
NUMBER
FUNDING
CONTRIBUTION
REQUEST
Radio Frequency Identification (RFID)
The project would tag every item in the collection with a
$ 125,000.00
$ 25,000.00
The project has the advantage of eliminating human error
Tagging of Library Collection and Self-
machine readable tag. All checkout stations would
in the processing of library materials. Inventory and control
Sorting Machine
automatically check out everything in a stack of books as
would also be much simpler and more accurate.
well as check them in. Currently this is done manually one
Customers would have virtually no wait time. With atintion,
5
item at a time. A self - sorting machine would be installed so
staffing and overall operating costs could be reduced.
that items could be checked in, sorted and routed to the
correct location. This is also currently very labor intensive in
the staff area.
City Emergency & Operational Fueling
This project would construct a new fueling facility located at
$ 280,000.00
$ 35,000.00
During a recent power outage there was a situation
Facility
the City's new Heavy Equiupment Maintenance Facility and
requiring the re- fueling of emergency and other City
Heavy Equipment Warm Storage Building. The Facility would
vehicles. Private - Sector commercial fuel stations were not
be capable of providing fuel for all City operations,
operational during that period and City emergency vehicles
5
specifically Public Safety and Public Works, through a two -
were unable to re -fuel. In a prolonged disaster event such
week emergency when other sources of fuel may be
as an eartquake or other natural disaster the City Police,
unavaialable. The facility would also provide capacity for
Fire, Public Works, and other Departments must have a
fueling other emergency response agencies such as the
reliable fuel source of sufficient volume to sustain basic
State Troopers, FBI, Coast Guard, etc.
and emergency operations.
OTHER PROJECTS CONSIDERED BUT NOT RANKED
Kenai Industrial Park Construction - Phase
This project would construct
$ 500,000.00
$ 50,000.00
This fully develops the Kenai Industrial Park. If the
II
water/ sewer /electhc Ytelecommunications /natural gas
Legislature is seeking economic development projects this
utilities to the second phase of the Kenai Industrial Park (up
year, this would be an attractive project.
to 20 lots, +/- 25 acres)
Public Safety Building,
This project would remove walls and remodel a portion of the
$ 400,000.00
$ 25,000.00
The east wing of the public safety building is comprised of
renovate /reconstruct evidence room /sate
Public Safety Building to construct a larger, secure evidence
small rooms, with limited efficient use, one of which is the
safe to meet the needs of the Kenai Police Department.
present evidence safe. The overall volume of items
requiring storage in an evidence safe is continually
growing. The size of the present evidence safe is
Inadequate to the Departments' needs
Sewage Lift Stations Upgrade
This project would construct a telemetry system meeting
$ 225,000.00
$ 25,000.00 IThe
existing telemetry system is operationally problematic
both operational requirements and the regulatory
as well as violating the most recent regulatory changes
requirements of the FCC.
re ardin band -width usage.
New Soccer Fields Irrigation
Project would design and install irrigation system for four
$ 250,000.00
$ 25,000.00
soccer fields
Page 2 of 5 Prepared by: R. Koch
CITY OF KENAI
CAPITAL IMPROVEMENTS PROGRAM (CIP) PRIORITES
FOR STATE FUNDING REQUESTS GREATER THAN $100,000 FOR
SFY 2017
PRIORITY
PROJECT TITLE
DESCRIPTION
STATE
LOCAL
NOTES /COMMENTS
NUMBER
FUNDING
CONTRIBUTION
REQUEST
Inlet Woods Storm Drain System
This project would construct an underground, piped, storm
$250,000-
Inlet Woods Subdivision was originally constructed with
drain system in Inlet Woods Subdivision. Disposal of surface
$1,000,000
curbed and guttered roadways at elevation lower than the
water run-off during rainfall/thawing events would be through
adjacent residential lots. The lots drain to the streets, and
a piped connection to the stone water collection system on
while some streets are graded in a matter that run -off
Forest Drive, to on -site settling ponds, underground drainage
occurs, ultimately water collects to a significant depth at
basins, or a combination of these allematives
sections of roadways at lower elevations.
Storage Facility for Kenai Senior Center
This project would construct a six -bay vehicle storage facility
$ 400,000.00
$ 100,000.00
At present all vehicles are stored outside the center.
Vehicles
at the City maintenance yard. The Kenai Senior Center
During the winter this results in vehicles running to
provides seniors a wide range of services to it's clients,
maintain heat for trips for the senior dients, reduced
including providing over 50,000 meals annually and
vehicle useful -life, and increased operation and
transportation services. This requires buses, meal delivery
maintenance costs.
vans and other vehicles.
Kenai Multi- Purpose Facility Locker Room
This project would construct six locker rooms (4 -team, 1-
$ 1,250,000.00
$ 200,000.00
The Kenai Mullti- Purpose Facility was designed to an
Construction
female, 1- referee) at the Kenai Multi Purpose Facility. This
untimate "build -out" which included locker rooms, enhanced
would include utilities, bathrooms, shower rooms and related
seating building insulation and heating systems, etc.
appurtenances. Approximately 5,000 at
Without locker rooms which include showers and other
appurtenances use of the facility is limited.
City of Kenai Indoor Turf Field Facility
This project would construct a 100'x200' indoor turf field, as
$ 3,500,000.00
$ 1,000,000.00
Indoor turf facilities throughout Alaska are heavily used
an addition to the existing Kenai Multi - Purpose Facility. The
and in high demand for school activities, youth athletics
facility would be used by area schools, pre - schools, soccer
such as soccer and kickball, and adult activities. The Kenai
and other organizations.
Peninsula does not presently have an indoor turf facility
and the construction of one as a component of the Kenai
Mulkti- Purpose facility is a cost effective manner in which
Ito provide these services.
Kenai - Old Town Pedestrian Walkway
This project would construct approximately 2,000 lineal feet
$ 150,000.00
$ 35,000.00
Old Town Kenai is heavily traveled by pedestrian traffic,
System - Phase II
of 4' wide sidewalk @ $150 /lf adjacent to roadways.
consisting of local residents, and during the summer
approximately 50,000 tourists. Because there are no
sidewalks pedestrians share the traveled roadways with
vehicles creating an unsafe condition. During the 2014
construction season the City of Kenai constructed Phase I
of the project by constructing approximately 1,100 lineal
feet of sidewalk along Overland Way.
Design for Expansion of the Kenai Public
This project would design an expansion and renovation of
$ 180,000.00
$ 10,000.00
Both the Kenai Police Deparetmenl and Fire Department
Safety Building
the Kenai Public Safety Building which houses both the
require additional buidling space to safely and effectively
Kenai Police Department and Kenai Fire Department. The
conduct operations. The Police Department evidence room
Public Safety Building has not been remodeled or expanded
is a remodeled kitchen /break room. The evidence locker is
in over two decades.
in a former holding cell entirely inadequate to the needs of
the Department. Storage areas are needed for both Fire
and Police equipment storage. Expanded, dedicated
training areas are also needed for both departments.
Page 3 of 5 Prepared by: R. Koch
CITY OF KENAI
CAPITAL IMPROVEMENTS PROGRAM (CIP) PRIORITES
FOR STATE FUNDING REQUESTS GREATER THAN $100,000 FOR
SFY 2017
PRIORITY
PROJECT TITLE
DESCRIPTION
STATE
LOCAL
NOTES /COMMENTS
NUMBER
FUNDING
CONTRIBUTION
REQUEST
Improvements to the City of Kenai
Recreation Center- Phase II
This is Phase II of a project to repair /replace the major
$ 250,000.00
$ 50,000.00
The Kenai Recreation Center is housed in a building that
operating systems in the facility as well as
relocate /reconstruct the facility entrance. The improvements
has reached a stage in its life cycle that major operation
would include, but not be limited to: HVAC System, Boilers,
systems are wearing out, becoming functionally obsolete,
or both. After 20 -30 years significant renovations are
Air Handling Units, New Facility Entrance replacement,
usually required to maintain an acceptable standard of
replacement of spectator sealing, locker room
service, and to decrease the rising costs of ongoing
reconstruction, tiMure replacements, flooring, and other
operations and maintenance issues in commercial /public
interior remodel /reconstruclion. In SFY 2015 the City of
buildings.
Kenai requested $500,000 for this project and received a
Legislative appropriation in the amount of $250,000 to initiate
Phase I of the project.
City of Kenai - Kenai Peninsula Regional
Convention and Activities Center
Feasibility and Conceptual Design of a Regional Convention
$ 225,000.00
$ 25,000.00
The Kenai Peninsula is in need of a Regional
Center to serve the Kenai Peninsula and to attract
Convention/Activities Center to serve the residents of the
convention and other activities to the Kenai Peninsula
Kenai Peninsula and attract in -state and out -of -state
convention activities. This requested appropriation would
support a comprehensive financial feasibility analysis,
including but limited to funding alternatives, as well as
City of Kenai -New Event Park Facility
This project would design and construct a new event park in
$ 500,000.00
$ 100,000.00
including a conceptual design.
The City is in need of a permanent facility to support
the downtown area of the City.lmprovements would include,
outdoor public events. Currently the area used for public
but not be limited to, a stage capable of supporting musical
events is on airport property and is not designed for
and performance events, designated vendor area(s), parking
facilities for 250 -500 vehicles, sound system(s), lighting
events, nor can the area be expanded to provide for the
system(s), picnic shelers, and other related improvements
communities needs.
Public Safety Radio Replacement
This project would replace the existing outdated base radio
$ 340,000.00
$ 40,000.00
The replacement will allow the City of Kenai to reliably
system with an IP -base radio system for the City's three
sustain the delivery of core public safety dispatching
dispatch positions.
capabilities for a decade or more to Kenai Police
Fire, and Animal Control, as well as providing support
services to other City Departments.The replacement will
also allow the City to reliably sustain its emergency backup
dispatching capabilities for emergency service zones
outside the Ci as the need arises.
Page 4 of 5 Prepared by: R. Koch
CITY OF KENAI
CAPITAL IMPROVEMENTS PROGRAM (CIP) PRIORITES
FOR STATE FUNDING REQUESTS GREATER THAN $100,000 FOR
SFY 2017
PRIORITY
PROJECT TITLE
DESCRIPTION
STATE
LOCAL
NOTES /COMMENTS
NUMBER
FUNDING
CONTRIBUTION
Kenai Fire Department -Self- Contained
This project will replace all Department SCBA's and
REQUEST
$ 250,000.00
Breathing Apparatus (SCBA)
purchase additional packs for reserve and utility vehicles for
$ 25,000.00
The Kenai Fire Department currently has 26 SCBA's in
Preplacement Project
a total of 34 SCBA's. Included with each SCBA will be 2 air
service. Of these packs, 22 are 1997 edition packs and
bottles.
are at the end of their service life. Components of the
SCBA's have been upgraded over time, but the pack frame
and other key components are at the entl of their service
life. In addition 44 of our 52 air cylinders that are in service
with these packs go out of service date in 2017. This
project will also Provide spare SCBA's in reserve to
replace damaged packs or packs in need of service. The
Project will also provide SCBA's in the department's utility
vehicles. At a minimum each of those vehicles should be
equipped with at least one SCBA to provide immediate
respiratory protection to the driver.
Kenai Fire Department - Portable Radio
This project will fund the purchase of replacement of 26
$ 140,000.00
$
Replacement Project
portable radios that have reached the end of their service
20,000.00
The current portable radios in use by the department have
life.
reached the end of their service life. The models of the
radios currently in use by the department are no longer in
Production and are nearing the end of the period where the
Waste Water Treatment Plant (W WTP)
Make improvements to the existing pit to include
manufacture will support and repair these models.
Dump Station Building
a new
heated building enclosure with overhead doom on each end
$ 160,000.00
$ 40,000.00
We use our I: : I truck to clean manholes and lift
and replace the drain line.
stations. It is not prudent place the resulting solids into
W
the W TP. There is a dump station at the W WiP that is
not adequately constructed. The drain line from it to the
basins is undersized and has a belly. The pit is also not
Lift Station Telemetry
try - Ratlio
Replacement
This project will replace radios at lift stations with FCC
approved
$ 220,000.00
$ 40,000.00
nclosed.
The existing radios are not FCC compliant because
alternatives,
they
are not narrow banded. They are also obsolete. It will not
be long before we will have an equipment failure that will
Construct Crew Offices in Equipment
This project would build -out unfinished areas in the
result in the inability to monitor a lift station remotely.
Due to fiscallimitationsche new equipment storage building
Storage Building
Equipment storage building for crew offices, breakroom,
$ 250,000.00
$ 25,000.00
locker room and related improvements
did not include crew support facilities.
Page 5 of 5 Prepared by: R. Koch
I VIlage to h a Past, C# with a Fut-a
210 Fidalgo Avenue, Kenai, Alaska 99611 -7794
Telephone: 907 - 283 -7535 / FAX: 907 - 283 -3014 illly
1992
MEMO:
TO: City Council
FROM: Rick Koch, City Manager
DATE: September 24, 2015
SUBJECT: Resolution 2015 -52, Adopting the City of Kenai Capital
Improvement Plan Priority Lists for State Funding Requests for the
Fiscal Year 2017
The purpose of this correspondence is to recommend Council approval of the above referenced
resolution. Each year it is necessary for the City to submit its capital requests to the Governor's
Office of Management and Budget (OMB) in advance of the Governor establishing the Capital
Budget.
Assuming Council adoption, I will submit our recommendations to the OMB by the end of
October. The OMB begins assembling and considering the Governor's Capital Budget shortly
after the first of November. The Governor's Capital Budget is generally released in mid -
December, and it becomes increasingly difficult after the middle of November to have requests
considered.
Thank you for your attention in this matter. If you have any questions, please contact me at
your convenience.