HomeMy WebLinkAboutResolution No. 2015-55CITY OF KENAI Suggested by: Administration
� °uhf
KE ,A KA
RESOLUTION NO. 2015 -55
A RESOLUTION OF THE COUNCIL OF THE CITY OF KENAI, ALASKA, AWARDING AN
AGREEMENT FOR CONSTRUCTION OF KENAI RECREATION CENTER
IMPROVEMENTS 2015 - HALLWAY ADDITION
WHEREAS, the following bids were received on September 15, 2015;
Bidder
Hallway
Addition
Extend Substantial
Completion Date to 2016
Architect's Estimate
$50,000
- $1500
Blazy Construction
$93,500
- $3,000
Orion Construction
$148,000
- $1,400
Treeline Construction
$122,886
$0
and,
WHEREAS, Blazy Construction, Inc. is the lowest responsive bid; and,
WHEREAS, award to Blazy Construction, Inc. would be in the best interest of the City;
and,
WHEREAS, the recommendation from City Administration is to award the agreement to
Blazy Construction, Inc. for the total approximate cost of $93,500.00; and,
WHEREAS, sufficient monies are appropriated.
NOW, THEREFORE, BE IT RESOLVED BY THE COUNCIL OF THE CITY OF KENAI,
ALASKA, that the agreement for the project entitled "KENAI RECREATION CENTER
IMPROVEMENTS 2015 - HALLWAY ADDITION" be awarded to Blazy Construction, Inc.
for the total approximate cost of $93,500.00.
PASSED BY THE COUNCIL OF THE CITY OF K A AS thi 7��d!ay OCTOBER,
2015.
PAT PORTER, MAYOR
gkr, City
Finance:
t
,o.
�� the C#01//r
KEN AL SKA
210 Fidalgo Avenue, Kenai, Alaska 99611 -7794
Telephone: (907) 283 -7535, Ext. 236 / FAX: (907) 283 -3014
"Villaye with a Past. C# with a Future"
MEMORANDUM
Ir PTO:
Rick Koch, City Manager
1 FROM:
Sean Wedemeyer, Public Works Director s/Kk/
DATE:
September 29, 2015
SUBJECT:
Award of an agreement for the construction of Kenai Recreation Center
- $3,000
Improvements 2015 — Hallway Addition
Rick,
This memo is in support of a resolution awarding an agreement for the construction of
the Kenai Recreation Center Improvements 2015 — Hallway Addition. The following bids
were opened on September 15'", 2015.
Bidder
Hallway
Addition
Alternate - Extend Substantial
Completion Date to 2016
Architect's Estimate
$50,000
- $2,500
Blazy Construction
$93,500
- $3,000
Orion Construction
$148,000
- $1,400
Treeline Construction
$122,886
$0
The scope of work includes constructing a hallway between the weight room and cardio
room (handball court 3) and modifying the emergency exit stairs. I also requested a
proposed bid reduction if the date of substantial completion was changed from 90 days
after Notice to Proceed to June 15 2016. 1 do not recommend accepting the $3,000
deduction offered by Blazy to postpone construction.
As a matter of course Architects do not typically provide estimates to construct.
Therefore they are not very experienced with estimating. For an additional fee we could
have procured a professional estimating company's estimate. We usually pay for this
service for multi - million dollar vertical construction projects only. Despite the seemingly
large difference between the estimate and the low bid, the low bid is very reasonable as
evidenced by the other contractor's proposals. I have discussed possible changes to the
design with the contractor, architect, and structural engineer, and we did not determine
any value engineering proposals.
This project includes multiple disciplines, including roofing, specialty flooring, electrical,
interior finishes, exterior finishes, civil site work, rough and finish carpentry, concrete,
metal flashing, insulation, etc. The fact that the construction is an addition to an existing
facility and must match old existing materials also adds a significant level of complexity.
Thank you for your attention to this matter.