HomeMy WebLinkAbout2001-02-22 Council Packet - Work SessionKenai City Council
Work Se~ion
February 22, 2001
Hockey Rink Refrigeration
CITY OF KENAi ~'~ '/
210 FIDALGO AVE., SUITE 200 KENAI, ALASKA 99611-7794
TELEPHONE 907-2811-7535
FAX 907-283-3014 ~
M emoranClum
Date:
To:
From.'
February 15, 2001
Mayor and City Council
Richard A. Ross, City Manager
Refrigeration Alternative
Attached is a memorandum submitted by Mr. Frates and Mr. La Shot. This will be
placed on the March 1 st Parks and Recreation Commission agenda as a discussion item.
As you will note, the alternatives proposed represent a major investment in the facility.
The most costly alternative is also the one that provides the greatest flexibility in usage.
Attachment
CITY OF KENA!
KENAI PARKS & RECREATION
227 CAVIAR ST. KENAI, ALASKA 99611-7794
TELEPHONE 907-283-3855 / 907-283-7926
FAX 907-283-4675
KENAi
MEMORANDUM
TO-
FROM:
Richard A. Ross, City Manager
Robert J. Frates, Parks & Recreation Dir. ecto~
Jack LaShot, Public Works Manager
DATE:
January 18, 2001
Refrigeration Alternatives and Considerations
The most critical aspect of a project such as this is the conceptual planning stage. This
type of planning is imperative in order to achieve the most cost effective and long-term
facility possible, while at the same time serving ,the broad recreation needs of the
community. The ultimate question that begs to be answered involves knowing what the
long term function of the facility is projected to be.
This report will outline some basic refrigeration options along with relative cost
estimates. Also included are some important considerations that should be taken, into
account while different alternatives are examined. The following areas were researched:
Ae
Refrigeration systems.
Rink floor- asphalt, sand-base, concrete surfaces, and dasherboards.
Operating costs.
A. REFRIGERATION SYSTEMS
There are two types of systems used to extract heat from ice: industrial and commercial.
Industrial systems include high-grade equipment (pump, chiller, compressor,
condenser), and are typically installed for permanency, have much higher construction
costs and include both direct and indirect refrigeration systems. Industrial systems have a
lifespan of approximately 30 or more years and are typically installed in conjunction with
a concrete-floor, thus, achieving a multi-purpose rink floor that can be exploited during
the off season.
Commercial systems on the other hand, include refrigeration equipment (chiller,
compressor, brine pump, and condenser) that is less expensive and usually incorporatea a
portable matt system to extract heat from ice. The portable matt is temporary in nature
and is typically installed in a sand-based surface or can rest on a concrete slab. Thi~
system has an estimated lifespan of 10-15 years and is less efficient'to operate. Storage
for the matting is a major consideration and it is labor intensive to set-up and take-down
each season (3 days work for staff of 10).
Direct vs Indirect: Direct refrigeration employs one (1) primary liquid refrigerant
called R-22 (dichlorodifluouromethane) which is a type of fi'eon that absorbs heat from
the ice by directly traversing approximately 10 miles of pipe. Indirect refrigeration
uses two (2) types of refrigerants, including a primary liquid (R-22 or R717 ammonia)
and a secondary liquid (calcium chloride, glycol, or other), called a brine. In this system,
the secondary brine is cooled by the primary in a heat exchanger and circulated back
through pipes evenly spaced below the ice.
Indirect systems have become the most preferred choice today due to the fact that the
hazardous refdgerants (R-22 or R717) are contained in a mechanical room and not
flowing through 10 miles of pipe. Direct systems, on the other hand, employ R-22
through nearly ten miles of pipe beneath the ice, thu~, making leak potential greater,
detection more difficult and repairs costly. For these reasons, a direct system is not
included in this report.
The Central Peninsula Sports Center convened over to an indirect system approximately
eleven years ago. Furthermore, the following facilities throughout Alaska also employ
indirect systems' Ft. Wainwright, McGlinchie, Dempsey 2, BenBOeke, O'malley Ice
Rink, Bonnie Cusack.
B. RINK FOOR AND DASHERBOARDS
Two options are available: concrete and sand-base. Asphalt is not a recommended
surface due to it's low heat transfer qualities. An industrial refrigeration system typically
involves a concrete ~urface, whereas, the tubing throughout the rink is protected beneath
a slab of concrete. Concrete offers the advantage of a flat surface, thus, making it easy to
install and maintain ice. Due to the consistent end-to-end ice thickness of approximately
an inch and a quarter over a concrete slab, it becomes possible to operate much more
efficiently. A concrete slab also protects the nearly 10 miles of pipe. Lastly, concrete
provides a multi-use floor for other activities needing a hard surface, i.e., basketball,
skateboarding/bike riding, in-line hockey, etc.
A sand-base medium is often chosen in order to reduce the initial construction cost. A
permanent piping system may be installed and buffed beneath the sand, or a portable matt
system can be placed on top of the sand. In either case, the sand surface may not be
consistent from end-to-end, and thus, the ice surface has to be built to accommodate the
highest poim, making installation and maimenance more difficult. Permanent piping
would exclude other uses since protection for the pipes would not exist. A portable matt
system, on the other hand, may be rolled up and Stored out of the way thus allowing other
uses during the off-season. In this scenario, off-season use of the facility would Only be
restricted, rather than excluded.
Moreover, if concrete is a consideration, this would be an appropriate time to discuss
dasherboards. The existing dasherboards would mostly likely have to be replaced at-this
stage. New installation could include base plates and removable boards and posts, thus
allowing the option to remove panels for special activities.
C. OPERATING COSTS:
Currently, the 12 month high for heating and electricity at the multi-purpose facility is
$213.93 and $1,546.40 respectfully. Water costs are currently $40.00 per month. One
would reason that if a mechanical room was added heat costs would go up accordingly.
Furthermore, a dependable refrigeration system coupled with a marketable program
would contribute to a longer season and increased use, and thus account for higher
electrical and maintenance cost. However, user fees could offset the additional expense.
Furthermore, the refrigeration unit would only be used during ice installation and
throughout warming spells, otherwise the natural temperature would be used to maintain
ice. The Central Peninsula Sports Center spends approximately $9,000 to $10,000 per
month for utilities; however, much of this cost is directly related t° heating a large facility
and continuous operation of the refrigeration unit.
MULTI-PURPOSE FACILITY
REFRIGERATION SYSTEM
COST ESTIMATE
Commercial System (labor included)
Indirect Refrigeration Equipment
Porta-matt
Mechanical Room - Temporary
Electrical
NE Fees & Contingency
Total (Sand-Based)
Concrete Slab- 4" entire building
Total (Concrete)
$180,000
65,000
50,000
30,000
$325,000
80,000
$100,000
$405,000
$505,000
Industrial System (labor included)
Indirect Refrigeration System
Mechanical
Electrical
6"Concrete Slab with Piping, Insulation, Vapor
Bamer, etc.
A/E Fees & Contingency
Total
$25O,OOO
100,000
40,000
250,00O
640,000
$ 6o,ooo
$800.000
Additional Elements - either system
New Dasher Boards
Additional Storage Building
Restmoms
A.C. Parking - (see estimate)
$ 80,000
50,000
70,00O
90,000
$290,000
MEMORANDUM
.
CITY OF KENAI
210 FIDALGO AVE.. SUITE 200 KENAI, ALASKA 99611-7794
TELEPHONE 907-283-7535
FAX 90T-283-3014 ~
TO:
FROM:
DATE'
SUBJECT:
Rick Ross, City Manager
Jack La Shot, Public Works Manager/~,/~-
Apdi 26, 2000
Paving Costs- Challenger & Multi-Purpose Facilities
,, it ,
I had Wince, Cortheli, Bryson prepare a rough estimate to do the paving at the
reforenced facilities. The attached drawing shows the area divided into possible
areas to pave based on which entity would pay the costs and best use of the
paving. The actual costs will vary, especially if we choose to do less than the
entire project. I based the percentages on the entire project.
Area 1
Area 5
Challenger Parking
Service Entrance
24% $30,627
7% 8,933
Total Challenger $39,560
Area 2 MPF Parking 28% $ 35,731
Area 3 MPF Parking 31% 39,559
Area 4 Access Road 10% ! 2,761
Total City $ 88,051
Grand Total
$127,611
Possible future additions to both facilities will affect Areas No. 3 and No. 5.
Areas No. 1,2, & 4 would seem to benefit both parties the most with the least
loss when future additions are done.
JL/jet
Attachment
COST ESTIMATE
For
CHALLENGER & MULTIPURPOSE FACILITY
SITE PAVING
ITEM QUANTITY UNIT COST
A--'~'alt Pavement 8645 S Y- -
Leveling Course 8813 SY $10.00/SY-
2.00/SY
Excavation 528 CY 10.00/CY
Adjust Manhole 1 Ea 250.00/Ea
Adjust Valve Box 2 Ea 250.00/Ea
Construction Total
Contingency (5%)
Design
Inspection
Total
COST
$8 oo
7,626.00
5,280.00
250.00
500.00
$110,106.00
5,505.00
2,000.00
10,000.00
$127,611.00.
'1'.
3.. ~ 1~.<~0~3S . t g
-- ]
- --'~' ..... --I
\ I
\I
\I
\~
\I
\ !
\ I
MULTI-PURPOSE FACILITY
REFRIGERATION SYSTEM
COST ESTIMATE
Commercial System (labor included)
Indirect Refrigeration Equipment
Porta-matt
Mechanical Room - Temporary
Electrical
NE Fees & Contingency
Total (Sand-Based)
Concrete Slab- 4" entire building
Total (Concrete)
$180,000
65,000
50,000
30,000
$325,OOO
80,000
$100,000
$405,000
$505,000
Industrial System (labor included)
Indirect Refrigeration System
Mechanical
Electrical
6"Concrete Slab with Piping, Insulation, Vapor
Bamer, etc.
NE Fees & Contingency
Total
$25O,OOO
100,000
40,000
250,000
640,000
$ 6o,ooo
$800,000
Additional Elements - either system
New Dasher Boards
Additional Storage Building
Restmoms
A.C. Parking - (see estimate)
$ 8O,OOO
50,000
70,000
9o,ooo
$290,000
MEMORANDUM
CITY OF KENAI
210 FIDALGO AVE.. SUITE 200 KENAI, ALASKA 99611-7794
TELEPHONE g07-283-753S
FAX 907-283-3014
TO:
FROM:
DATE.
SUBJECT:
Rick Ross, City Manager
Jack La Shot, Public Works Uanager~~
'Apdi 26, 2000
Paving Costs - Challenger & Multi-Purpose Facilities
I had Wince, Corthell, Bryson prepare a rough estimate to do the paving at the
reforenced facilities. The attached drawing shows the area divided into possible
areas to pave based on which entity would pay the costs and best use of the
paving. The actual costs will varg, especially if we choose to do less than the
entire project. I based the percentages on the entire project.
Area 1
Area 5
Challenger Parking
Service Entrance
24% $30,627
7% 8,933
Total Challenger $39,560
Area 2 MPF Parking 28% $ 35,731
Ama 3 MPF Parking 31% 39,559
Ama 4 Access Roacl 10% 12,761
Total City $ 88,051
Grand Total $127,611
Possible future additions to both facilities will affect Areas No. 3 and No. 5.
Areas NO. 1,2, & 4 would seem to benefit both parties the most with the least
loss when future additions are done.
JL/jet
Attachment
F ..... ~ ..... -3
I
I
/
I
I
I
Z
COST ESTIMATE
For
CHALLENGER & MULTIPURPOSE FACILITY
SITE PAVING
ITEM QUANTITY UNIT COST
Asphalt Pavement 8645 SY $10.00/Sy
Leveling Course 8813 SY 2.00/SY
Excavation 528 CY 10.00ICY
Adjust Manhole 1 Ea 250.00lEa
Adjust Valve Box 2 Ea 250.00lEa
Construction Total
Contingency (5%)
Design
Inspection
Total
COST
$86,450.00
.17,626.00
5,280.00
250.00
500.00
$110,106.00
5,505.OO
2,000.00
10.000.00
$127,611.00 ·
Ph
Enclose Facility
Indoor Modification
Buyout Phase I L LC
Stable ice
$1,012,000 TO DAY
Possible
i