HomeMy WebLinkAboutOrdinance No. 3013-2018Sponsored by: Administration
C ITY OF KENAI
ORDINANCE NO. 3013-2018
AN ORDINANCE OF THE COUNCIL OF THE CITY OF KENAI, ALASKA, INCREASING
ESTIMATED REVENUES AND APPROPRIATIONS BY $286,288 IN THE AIRPORT SPECIAL
REVENUE AND AIRPORT TERMINAL IMPROVEMENTS CAPITAL PROJECT FUNDS FOR
INCREASED COSTS ASSOCIATED WITH PHASE 11 OF THE PROJECT TO DESIGN THE
AIRPORT TERMINAL REHABILITATION PROJECT AND AUTHORIZING A CONTRACT
AMENDMENT WITH WINCE-CORTHELL-BRYSON FOR COMPLETION OF PHASE II OF THE
PROJECT'S DESIGN.
WHEREAS , the scope of the Airport Terminal Improvement project has expanded based on
Phase 1 analysis to a project estimated at approx imately $9 , 700,000 in design and construction
costs ; and ,
WHEREAS, Ordinance No . 2975-2017 appropriated the original design grant from the Federal
Aviation Administration totaling $521,007; including the City's required local match of $32,563 but
is no longer sufficient to complete the expanded design; and,
WHEREAS , an additional $286,288 is needed to complete the design and bid services and will
initially be provided by the Airport Special Revenue Fund; and ,
WHEREAS , total professional services for design is estimated at $726,500 , approximately 7 .5 %
of the tota l project budget, a nd $80,795 in City Administration for a total design budget of
$807 ,295, approximately 8 .3% of the estimated project costs ; and ,
WHEREAS, the additional $286,288 being provided by the Airport Special Revenue Fund is
eligible for reimb ursement by the project and will be included in the grant to be awarded for
construction ; and,
WHEREAS, Wince-Corthell -Bryson submitted a proposal to provide additional design and bid
services which the Administra t ion has reviewed and found to be fair and reasonable ; and,
NOW , THEREFORE, BE IT ORDAINED BY THE COUNCIL OF THE CITY OF KENAI , ALASKA,
as follows :
Section 1. That estimated revenues and appropriations be increased as follow s :
Airport Special Revenue Fund :
Increase Estimated Revenues:
Appropriation of Fund Balance
Increa se Appropriations:
Transfer to Airport Terminal Improvements
Capital Project Fund
New Text Underlined; [DELETED T EXT BRACKE TE D]
$286.288
$286.288
Ordinance No. 3013-2018
Page 2 of 2
Airport Terminal Improvements Capital Project Fund :
Inc rease Estimated Revenues:
Transfer from Airport Special Revenue Fund
Increase Appropriations:
Design & Engineering
$286.288
$286.288
Section 2. The City Manager is authorized to execute an amendment to the professional
services agreement with Wince-Corthell-Bryson in the amount of $286,288 for completion of the
Phase II Design for the Airport Terminal Rehabili tation Project.
Section 3 . Severability: That if any part or provision of this ordinance or application thereof to
any person or circumstances is adjudged invalid by any court of competent jurisdiction, such
judgment shall be confined in its operation to the part, provision , or application directly involved
in all controversy in which this judgment shall have been rendered , and shall not affect or impair
the validity of the remainder of this title or application thereof to other persons or circumstances .
The City Council hereby declares that it would have enacted the remainder of this ordinance even
without such part, provision, or application.
Section 4. Effective Date: That pursuant to KMC 1.15.0?0(f), this ordin a nce shall take effect
upon adoption.
ENACTED BY THE COUNCIL OF THE CITY OF KENAI , ALASKA, this 18th day of April, 2018.
ATIEST:
BRIAN GABRIEL SR., MAYOR
New Text Unde rl ine d ; [DE LETED TEXT BRACKETED]
Introduced: April 4 , 2018
Enacted : April 18, 2018
Effective: April 18, 2018
'Vtffar «J/t/r, tl PaJ'~ Ct'tf «J/t/r, tl l"ata/"e II
210 F idalgoAve, Kenai , Alaska 99611 -7794
Telephone : (907) 283-7535 I Fax : (907) 283-3 014
www.kenai .city
MEMORANDUM
TO:
THROUGH :
FROM:
DATE:
SUBJECT:
Mayor Brian Gabriel and Kenai City Council
Paul Ostrander, City Manager
Mary Bondurant, Airport Manager
March 23 , 2018
Ordinance No. 3013-2018 -Airport Terminal Rehabilitation
The memo recommends the appropriation of an additional $286,888 for the design of the Airport
Terminal Rehabilitation Project.
A large component of Phase 1 of this design project was defining the needs and establishing the
scope of work to adequately rehabilitate the terminal. After completion of Phase 1, the extent of
needed upgrades and the associated estimated construction costs was significantly greater than
what was originally anticipated. The scope of work as established by the Phase 1 design includes
roof replacement, new fire sprinkler system, relocation of administrative offices, exterior siding ,
interior flooring, wall repairs , painting, new ceiling, interior/exterior lighting upgrades , mechanical
electrical room ex pansion, ADA upgrades, structural upgrades, mechanical, electrical , and
telecom upgrades , tenant counter refurbishment, sewer line upgrade , and other improvements.
The Phase II design cost was based on a preliminary scope of work and the original conceptual
construction estimate for the terminal rehabilitation project of $4 .5 million . With the change of
scope and a revised cost estimate of $9. 7 million for construction, the scope and cost for the
Phase II design has increased . W ince-Corthell-Bryson submitted a proposal of $286 ,288 for
additional design and bid services resulting in total design costs of approximately 7.5% of the
estimated construction cost. Administration found this proposal to be fair and reasonable .
In August 2017, the City received an FAA grant for the Phase 1 and 2 design. It is not uncommon
for design to change during the development of a project and the FAA has confirmed these
additional design costs are grant eligible and can be reimbursed through the construction grant.
Your consideration is appreciated.
Grant Total FAA City
No. Improvement Eligible Cost Share S hare
I Roof System
A. New Roof y $ 903 ,996.00 $ 847,496.25 $ 56,499.75
B. Asbestos Abatement y $ 234,370.00 $ 219,721.88 $ 14,648.13
2 Sprinkler System y $ 125,250.00 $ 117,421.88 $ 7,828.13
3 Exterior Tenninal Siding y $ 638,505.00 $ 598,598.44 $ 39,906.56
4 Interior Flooring, Wall Repairs, Painting and Ceiling 76.5% $ 1,841 ,3 56.00 $ 1,320,597.51 $ 520,758.49
5 Interior /Exterior Lighting Upgrades y $ 585,73 3.00 $ 549,124.69 $ 36,608.31
6 Mechanical and Electrical Room Expansion y $ 98,934.00 $ 92,7 50.63 $ 6, 183.38
7 ADA Upgrades y $ 194,397.00 $ 182,247.19 $ 12 ,149.81
8 Baggage Make-Up Area E xpansion y $ 595,6 61.00 $ 558 ,432.19 $ 37,228.8 1
9 Baggage Breakdown Area Expansion y $ 688,957.00 $ 645,897.19 $ 43,059.81
10 Departure/Gate Area Expansion y $ 492,318.00 $ 461 ,548.13 $ 30,769.88
11 Ai r Carri er Office Area Refurbishment
A. Ticket Counters y $ 74,77 1.00 $ 70,097.81 $ 4 ,673 .19
B. Baggage Conveyors y $ 59 1,948.00 $ 554,951.25 $ 36,996.75
C . Office Remodel N $ 335,478.00 $ $ 335,478.00
D. Water and Sewer Service N $ 26,8 5 1.00 $ $ 26,8 51 .00
12 Rental Car Area Refurbishment
A. Front Counters y $ 28,56 1.00 $ 26,775.94 $ 1,785.06
B. Office Remodel N $ 75 ,627.00 $ $ 75,627.00
13 Airport Administration Area Refurbishment N $ 83,944.00 $ $ 83,944.00
14 Conference Room N $ 56,880.00 $ $ 56,880.00
15 Structural Upgrades to Tenninal y $ 36,43 1.00 $ 34,154.06 $ 2,276.94
16 Sewer Line Upgrade y $ 50,000.00 $ 46,8 75.00 $ 3, 125.00
17 E lectrical , Mechanical and Telecom. Upgrades y $ 1,029,007.00 $ 964,694.06 $ 64,312.94
20 Service Ani mal Relief Area y $ 40,938.00 $ 38 ,3 79.38 $ 2,558.63
21 Visual Infonnation System y $ 150,905.00 $ 141,473.44 $ 9,431 .56
22 Portable Kiosks y $ 46 ,6 11 .00 $ 43 ,697.81 $ 2,913 .19
23 Smoking Shelter N $ 51,436.00 $ $ 51 ,436.00
24 Arrival Entry Rehabilitation y $ 406,921.00 $ 38 1,488.44 $ 25,432 .5 6
25 Second Story Exit Corridor Reconstruction y $ 257,063.00 $ 240,996.56 $ 16,066.44
Total $ 9,742,849.00 $ 8,137,419.69 $ 1,605,429.31