HomeMy WebLinkAboutOrdinance No. 3097-2019Sponsored by: Administration
CITY OF K ENAI
ORDI NANCE NO. 3097-2019
AN ORDINANCE OF THE COUNCIL OF THE CITY OF KENAI, ALASKA, INCREASING
ESTIMATED REVENUES AND APPROPRIATIONS IN THE TERM INAL IMPROVEMENTS
CAPITAL FUND , AND AUTHORIZING AN INCREASE TO THE CONSTRUCTION PURCHASE
ORDER TO BLAZY CONSTRUCTION, INC .
WHEREAS, the City of Kenai executed a Construction Agreement with Blazy Construction, Inc.
on October 1, 2018 for the Terminal Rehabilitation Project in the amount of $10,985,994; and ,
WHEREAS , Council, through enactment of Ordinance 3037-2018 authorized the City Manager to
issue a Purchase Orde r in the amount of $11,485 ,994 for the Contract amount of $10,985,994
including $500 ,000 of contingency funding; and,
WHEREAS, Council , through enact ment of Ordinances 3060-2019 and 3080 -2019 increased
estimated revenues and appropriations by $734,232 .51 to provide for continued project
contingency funds and increased the purchase order amount to $12 ,220,226 .51 ; and,
WHEREAS, to date the City has executed six change orders totaling $980 , 165.39 ; an d,
WHEREAS, the Federal Aviation Administration grant eligible portion of those Change Orders 1-
6 has been determined to be $868, 181.49 with the City of Kenai 's share as $111 ,983 .90; and ,
WHEREAS, Administration is requesting appropriation of the additional eligible federal share and
an increase to the authorized Purchase Order Amount to Blazy Construction , Inc. of the same
amount, $133,948.98 to replenish project contingency and to allow for the continued processing
of future change orders; and,
WHEREAS, once complete, the authorized purchase order amount to Blazy Construction, Inc .
will be $12,354, 175.49, the au t horized contract to Blazy Construction , Inc. will be $11 ,966 , 159 .39 ,
with available contingency to complete the project of $388 ,016 .10 ; and ,
WHEREAS, Council will continue to be informed of Change Orders through Public Works Mid-
Month Report.
NOW , THEREFORE , BE IT ORDAINED BY THE COUNCIL OF THE CITY OF KENAI, ALASKA,
as follows :
Section 1. The City Manager is authorized to accept grant funding from the Federal Aviation
Administration in the amount of $133 ,948.98 for the grant eligible portions of Change Order 6 to
Blazy Construction , Inc.
Ordinance No . 3097-2019
Page 2 of 2
Section 2. The City Manager is authorized to increase Purchase Order No. 116510 to Blazy
Construction, Inc. by $133 ,948 .98.
Section 3. That the estimated revenues and appropriations be increased as follows:
Terminal Improvement Capital Project Fund:
Increase Estimated Revenues -
FAA Grant
Increase Appropriations :
Construction
$133 .948.98
$133.948,98
Section 4. Severability: That if any part or provision of this ordinance or application thereof to
any person or circumstances is adjudged invalid by any court of competent jurisdiction, such
judgment shall be confined in its operation to the part, provision, or application directly involved
in all controversy in which this judgment shall have been rendered, and shall not affect or impair
the validity of the remainder of this title or application thereof to other persons or circumstances.
The City Council hereby declares that it would have enacted the remainder of this ordinance even
without such part, provision, or application .
Section 5. Effective Date: That pursuant to KMC 1.15.0?0{f), this ordinance shall take effect
upon adoption.
ENACTED BY THE COUNCIL OF THE CITY OF KENAI , ALASKA, this 4th day of December,
2019 .
ATTEST:
ffRIAN GABRIEL SR., MAYOR
Introduced : November 6, 2019
Enacted : December 4, 2019
Effective: December 4, 2019
'V/fl~ U1/t~ a PaJ'~ tt'tj U1/t~ a Fu.t~e"
210 F idalgo Ave, Kenai , Alaska 99611 -7794
Telephone: (907) 283-7535 I Fax: (907) 283-3014
www.kenai.city
MEMORANDUM
TO:
THROUGH:
FROM:
DATE:
SUBJECT:
Mayor Brian Gabriel and Kenai City Council
Paul Ostrander, City Manager
Scott Curtin, Public Works Director
October 30, 2019
Ordinance No. 3097-2019 -Authorizing increases to the Terminal
Rehabilitation Project
The Kenai Municipal Airport Terminal Rehabilitation Project has been underway since October 1,
2018. The current completion date has been adjusted slightly to February 20 , 2020 through
execution of Change Order 6 which added 18 Calendar days as the result of labor and material
delays resulting from highway closures from the Swan Lake Fire.
The Project was awarded with $500,000.00 in contingency funds to allow for the prompt
processing of change orders during construction to minimize potential cost impacts related to time
delays . The Public Works Director in coordination with the City Manager have been reviewing
and processing change requests as they are received, and notifying council through Departmental
Mid-month reports throughout the project.
To summarize:
Change Order#1 -$188,955.55 executed on January 31, 2019
Change Order #2 -$272,630.01 executed on March 4, 2019
Ordinance 3060-20 19 appropriating the Federal share of C0#1-2 April 3, 2019-$408 ,849.41
Change Order #3 -$203,602. 75 executed on April 26 , 2019
Change Order #4 -$67,624.42 executed on May 29 , 2 019
Ordinance 3080-20 19 appropriating the Federal share of C0#3-5 August 21, 2019 -$325,383.10
Change Order #5 -$96, 126.03 executed on September 3, 2019
Change Order#6-$151,226.63 executed on October 21, 2019
Ordinance No. 3097-2019
The Original Contract to Blazy Construction, Inc. was $10,985,994.00
Total Change Orders to date C0#1-6 -$980, 165.39
Total Contract to date shall be $11,966 ,159.39
Passage of this Ordinance will replenish the contingency and allow for the continued processing
of future change orders. Council will continue to be informed of change orders through Public
Works Mid-Month reports .
As a reminder to Council, the extent of the Asbestos Abatement, is the largest contributing factor
to the additional costs, accounting for $546,896.40 of all change orders to date.
Council 's approval is respectfully requested .