CITY OF KENAI
RESOLUTION N0, 82-109
A RESOLUTION OF THE COUNCIL OF THE CITY OF KENAI, ALASKA, AWARDING A
CONTRACT FOR THE DESIGN AND CONSTRUCTION OF THE KENAI RECREATION CENTER --
GYMNASIUM ADDITION TO BLAZY CONSTRUCTION FOR A TOTAL COST OF $699,200
INCLUDING ADD AI.T 1,3,4, 4 5 PLUS SOME NEGOTIATED CHANGES, ADDITIONS,
AND/OR ALTERATIONS.
PROPOSER BASIC ADD 1 ADD 2 ADD 3 ADD 4 ADD 5
Blazy Constr. $625,000 $57,000 $7,500 $77,500 $3,100 $3,500
(raise roof)
14,800
(equipment)
Air Tek, Inc. $592,217 $15,000 $3,000 $309600 $3,000 $3,300
Timberline Ind. $621,739 $ 8,469 $29,800 $69,314 $4,986 $3,582
(equipment)
6,430
(striping)
WHEREAS, Additive Alternate No. 1 is Additional Game Equipment, and
WHEREAS, Additive Alternate No. 2 is Landscaping and Seeding, and
WHEREAS, Additive Alternate No. 3 is Asphalt Paving, and
WHEREAS, Additive Alternate No. 4 is Installation of Metal Fireplace, and
WHEREAS, Additive Alternate No. 5 is Electronic Scoreboard, and
WHEREAS, the following changes, additions, and/or alterations were
negotiated with Blazy Construction and are recommended to be included
by the Public Works Department and the Parks and Recreation Department:
BID TOTAL
BASIC
$625,000
AA 1
$14,800
AA 2
$7,500
JAA 3
$77,500
AA 4
$3,100
AA 5
$3,500
1) Increase from R19 to R30 in wails
+ 2,800
2j Change from steel siding to wood
- 9,000
3. Delete landscaping
-7,500
4) Add screen around existing
mechanical
+ 3,500
5) Remove 1st floor west entrance
and add storage area
- 28,200
6) Remove 2nd floor west entrance
(contingent on fire marshall o.k.
- 4,700
I
RESOLUTION NO. 82-109
Page 2
BID TOTAL
7) Delete some of the PEE WEE
basketball striping
81 Reduce slab from 6" to 4"
9 Eliminate curb & gutter except
for entrances
10) Eliminate sidewalk on west
wall of new construction
11) Add 3/4" plywood behind baskets
and place hanging protection mat;
12) Double instead of single door
for south entrance
13) Construct racquetball court -
shell only --use presently for
storage
14) Raise ceiling from 20' to 24'
FINAL BID
BASIC
AA 1
AA 2
AA 3
AA 4
1 AA 5
-1,200
- 5,700
-23,000
- 3,400
+4,000
+ 500
L,700
000
$17,600
0
$51,100
$3,100
$3,500
$623,900
WHEREAS, the recommendation from the Parks and Recreation Commission is to award the
contract to Blazy Construction for a total project design/construction cost of
$699,200 which would include the Basic Bid and Additive Alternates No. 1, 3, 4, and 5
plus some negotiated changes, additions, and/or alterations, and
WHEREAS, Blazy Construction's total bid of $699,200 including Additive Alternates
No. 1, 3, 4, and 5 plus some negotiated changes, additions, and/or alterations is in
the best interest of the City of Kenai, and
WHEREAS, sufficient funds are appropriated.
NOW, THEREFORE, BE IT RESOLVED BY THE COUNCIL OF THE CITY OF KENAI, ALASKA, that the
contract for the Design and Construction of the Kenai Recreation Center --Gymnasium
Addition be awarded to Blazy Construction, in the amount of $699,200 for the project
design and construction cost which includes the Basic Bid and Additive Alternates
No. 1, 3, 4, and 5 plus some negotiated changes, additions, and/or alterations.
PASSED BY THE COUNCIL OF THE CITY OF KENAI, ALASKA, this 6th day of October, 1982.
ATTEST: BETT LI ICE -MY R
get_
Jajot Whelan, City Clerk
Approved by Finance: