HomeMy WebLinkAboutResolution No. 2022-18New Text Underlined; [DELETED TEXT BRACKETED]
Sponsored by: Administration
CITY OF KENAI
RESOLUTION NO. 2022 - 18
A RESOLUTION OF THE CITY OF KENAI, ALASKA, ADOPTING THE CITY’S CAPITAL
IMPROVEMENT PLAN FOR FISCAL YEARS 2023-2027.
WHEREAS, the City adopts a five-year capital plan annually as a part of the budget preparation
process; and,
WHEREAS, the Capital Improvement Plan included with this Resolution represents the capital
needs of the City for the years 2023-2027; and,
WHEREAS, at their meeting on February 7, 2022, the Harbor Commission recommended
approval of the Plan with a request that dredging of the Kenai River be considered for inclusion
for fiscal year 2025; and,
WHEREAS, at their meeting on February 9, 2022, the Planning and Zoning Commission
recommended approval of the Plan with a recommendation that the Softball Field Shelters /
Dugouts Replacement be prioritized over the Kenai Nordic Trail Lighting Project; and,
WHEREAS, at their meeting on February 10, 2022, the Council on Aging recommended approval
of the Plan with no additional recommendations; and,
WHEREAS, at their meeting on February 10, 2022, the Airport Commission recommended
approval of the Plan with no additional recommendations; and,
WHEREAS, at their meeting on February 15, 2022, the Beautification Commission recommended
approval of the Plan with no additional recommendations; and,
WHEREAS, at their meeting on February 17, 2022, the Parks and Recreation Commission
recommended approval of the Plan with a recommendation that the Softball Field Shelters /
Dugouts Replacement project be moved to fiscal year 2023, and splitting the Kenai Nordic Trail
Lighting project with design in fiscal year 2023 and implementation in fiscal year 2025; and,
WHEREAS, based on the recommendation from the Planning and Zoning Commission, Parks
and Recreation Commission, and an inspection of the softball field shelters by Parks and
Recreation Department personnel, the Capital Improvement Plan included with this Resolution
places the Softball Field Shelters / Dugouts Replacement project into fiscal year 2023; and,
WHEREAS, Administration is in support of and recommends adoption of the Plan; and,
WHEREAS, adoption of this Plan is in the best interest of the City; and,
WHEREAS, the Capital Improvement Plan is intended to be a living document that will be adjusted
periodically to meet the ongoing needs of the City.
NOW, THEREFORE, BE IT RESOLVED BY THE COUNCIL OF THE CITY OF KENAI, ALASKA:
1
FISCAL YEARS 2023 – 2027
CITY OF KENAI
CITY HALL 210 FIDALGO AVENUE KENAI, AK 99611
PAUL OSTRANDER
CITY MANAGER POSTRANDER@KENAI.CITY 907.283.8222
SCOTT CURTIN
PUBLIC WORKS DIRECTOR SCURTIN@KENAI.CITY 907.283.8236
2
TABLE OF CONTENTS Page 3 INTRODUCTION
Page 5 AIRPORT FUND
Page 15 GENERAL FUND
Page 33 WATER & SEWER FUND
Page 43 SENIOR CITIZENS FUND
Page 47 CONGREGATE HOUSING FUND
Page 51 PERSONAL USE FISHERY FUND
3
INTRODUCTION The City of Kenai's five-year Capital Improvement Plan (CIP) is developed by the Public Works Department in coordination with City departments, Administration, Boards and Commissions, and the City Council for the purpose of long-range capital improvement planning and budgeting. A capital improvement project is typically a one-time expenditure, usually, in excess of $35,000, that has a useful life exceeding one year or is a major project such as a comprehensive or master plan. Capital projects on existing assets are included in the CIP, provided they meet the definition of a capital project. Projects can focus on immediate needs or anticipate future needs before critical failures and are developed based on an internal process that determines funding availability and infrastructure needs. The CIP is divided into six parts based on the City Fund in which the project would be accounted for. These include the Airport Fund, General Fund, Water & Sewer Fund, Senior Citizens Fund, Congregate Housing Enterprise Fund, and Personal Use Fishery Fund. Projects are not necessarily listed in priority order for each Fund by fiscal year. Active projects that have been funded in prior years are not included in the Plan. Projects that are identified in the CIP are included for planning purposes and to recognize a need. Not all projects receive the necessary funding to accomplish them in a projected year, which is why the list is updated annually. Many projects are dependent on non-City funding sources, which the City can expect to seek, but are not guaranteed. The availability of outside funds can vary with local, state, and federal economies, and the City's needs can, and do, change frequently.
4
Blank
5
AIRPORT FUND FY2023
Project Name
Project
No.
Total Project
Cost
Airport
Funding
Grant
Funding Description
Runway
Rehabilitation
Project Design
1 $1,550,000 $96,875 $1,453,125
Design Project to
Rehabilitate Runway
2L/20R and Taxiways A,
C, K, L to Current
Standards
ENA Broom
Replacement 2 $1,000,000 $62,500 $937,500 Runway Snow Removal
Equipment
Terminal
Landscaping 3 $100,000 $100,000 Exterior Improvements
to Terminal
Terminal
Surveillance
Camera/Ops
Access Control
4 $150,000 $150,000 Airport Security
Apron Crack Seal
and Seal Coating 5 $300,000 $18,750 $281,250
Within Areas not
planned for upcoming
rehabilitation
Totals $3,100,000 $428,125 $2,671,875
FY2024
Project Name
Project
No.
Total Project
Cost
Airport
Funding
Grant
Funding Description
Runway
Rehabilitation
Project
Construction
6 $22,790,000 $1,424,375 $21,365,625
Project to Rehabilitate
Runway 2L/20R to
Current Standards
Terminal Elevator
Major
Maintenance
7 $50,000 $3,125 $46,875
Major Maintenance on
Existing Elevator at the
Airport Terminal
ARFT Elevator
Major
Maintenance
8 $50,000 $3,125 $46,875
Major Maintenance on
Existing Elevator at the
ARFT Facility
Totals $22,890,000 $1,430,625 $21,459,375
6
FY2025
Project Name
Project
No.
Total Project
Cost
Airport
Funding
Grant
Funding Description
Rehabilitate
Taxiways A,C, K
& L
9 $12,867,000 $804,188 $12,062,812
Design and Construct
Project to Rehabilitate
Taxiways A, C, K, L to
Current Standards
Airfield
Firefighting
Vehicle
Replacement
10 $1,000,000 $62,500 $937,500 Replace Airfield
Firefighting Vehicle
Totals $13,867,000 $866,688 $13,000,312 FY2026
Project Name
Project
No.
Total Project
Cost
Airport
Funding
Grant
Funding Description
Apron and
Willow Street
Extension
11 $2,350,000 $146,875 $2,203,125
Extend Apron Taxiway
for Lease Lots and Road
and Utilities on Willow
Street
Terminal Road
& Parking
Improvements
12 $1,750,000 $875,000 $875,000
Concrete curb, asphalt,
and marking
improvements to road
and parking areas
Totals $4,100,000 $1,021,875 $3,078,125 FY2027
Project Name
Project
No.
Total Project
Cost
Airport
Funding
Grant
Funding Description
ENA Broom
Replacement 13 $1,000,000 $62,500 $937,500 Runway Snow Removal
Equipment
ARFT Fire
Training
Apparatus
Repairs
14 $100,000 $100,000 $0
The planned
replacement of Fire
Trainer apparatus parts
Totals $1,100,000 $162,500 $937,500
7
AIRPORT FUND PROJECTS RUNWAY REHABILITATION PROJECT DESIGN Department: Airport Total Project Cost: $1,550,000 Project Phased: Yes Project Type: Infrastructure Funding Source(s): Grant Dependent Potential Grant Identified: Federal Aviation Admin Operating Budget Impact: Slight Decrease
YEAR: 2023 2024 2025 2026 2027
COST: $1,550,000 Details: This project consists of design services to provide bid-ready construction documents to rehabilitate Runway 2L/20R and taxiways A, C, K, and L to current standards. The project will reduce crack sealing maintenance costs and bring the oldest pavement on the Airport up to the recommended Pavement Condition Index.
ENA BROOM REPLACEMENT Department: Airport Total Project Cost: $1,000,000 Project Phased: No Project Type: Equipment Funding Source(s): Grant Dependent Potential Grant Identified: Federal Aviation Admin Operating Budget Impact: Slight Decrease
YEAR: 2023 2024 2025 2026 2027
COST: $1,000,000 $1,000,000 Details: This purchase will replace existing equipment as it reaches the end of useful life. The 2023 purchase will replace an existing 2000 model year piece of equipment. The 2027 purchase will replace an existing 2012 model year piece of equipment. Modernization of the Airport’s Fleet allows for continued efficient airfield operations.
8
AIRPORT FUND PROJECTS TERMINAL LANDSCAPING Department: Airport Total Project Cost: $100,000 Project Phased: No Project Type: Building Improvement Funding Source(s): Airport Fund Potential Grant Identified: None Operating Budget Impact: Slight Decrease
YEAR: 2023 2024 2025 2026 2027
COST: $100,000 Details: This project will finalize exterior improvements to the Terminal Rehabilitation Project. Work will include plantings and sprinklers that were not grant eligible.
TERMINAL SURVEILLANCE CAMERA/OPS ACCESS CONTROL Department: Airport Total Project Cost: $150,000 Project Phased: Yes Project Type: Technology Funding Source(s): Airport Fund Potential Grant Identified: None Operating Budget Impact: Slight Increase
YEAR: 2023 2024 2025 2026 2027
COST: $150,000 Details: This project will provide for security improvements at the terminal that were not grant eligible during the Terminal Rehab project. Work includes upgrades and replacements related to various access controls and security cameras.
9
AIRPORT FUND PROJECTS APRON CRACK SEAL AND SEAL COATING Department: Airport Total Project Cost: $300,000 Project Phased: No Project Type: Infrastructure Funding Source(s): Grant Dependent Potential Grant Identified: Federal Aviation Admin Operating Budget Impact: None
YEAR: 2023 2024 2025 2026 2027
COST: $300,000 Details: This project will provide for major maintenance on apron areas, to extend the life of the existing asphalt. Work areas proposed are outside of the Runway and Taxiway Rehab areas included in this plan for replacement.
RUNWAY REHABILITATION PROJECT CONSTRUCTION Department: Airport Total Project Cost: $22,790,000 Project Phased: Yes Project Type: Infrastructure Funding Source(s): Grant Dependent Potential Grant Identified: Federal Aviation Administration Operating Budget Impact: Slight Decrease
YEAR: 2023 2024 2025 2026 2027
COST: $22,790,000 Details: This project will rehabilitate Runway 2L/20R to current standards. The project will reduce crack sealing maintenance costs and bring the oldest pavement on the Airport up to the recommended Pavement Condition Index.
10
AIRPORT FUND PROJECTS TERMINAL ELEVATOR MAJOR MAINTENANCE Department: Airport Total Project Cost: $50,000 Project Phased: No Project Type: Building Improvement Funding Source(s): Grant Dependent Potential Grant Identified: Federal Aviation Admin Operating Budget Impact: Minimal or No Impact
YEAR: 2023 2024 2025 2026 2027
COST: $50,000 Details: Provide major maintenance on the existing Airport Terminal Elevator. This maintenance will replace 30-plus-year-old components for safety reasons while providing minor cosmetic improvements.
ARFT ELEVATOR MAJOR MAINTENANCE Department: Airport Total Project Cost: $50,000 Project Phased: No Project Type: Building Improvement Funding Source(s): Airport Fund Potential Grant Identified: None Operating Budget Impact: Minimal or No Impact
YEAR: 2023 2024 2025 2026 2027
COST: $50,000 Details: Provide major maintenance on the existing Alaska Regional Fire Training Facility's elevator. The facility is currently primarily occupied by Beacon. The facility was constructed in 1997, and while the elevator sees relatively minimal use, this project will provide for the continued safe operation of the unit.
11
AIRPORT FUND PROJECTS REHABILITATE TAXIWAYS A,C,K, & L Department: Airport Total Project Cost: $3,500,000 Project Phased: Yes Project Type: Infrastructure Funding Source(s): Grant Dependent Potential Grant Identified: Federal Aviation Admin Operating Budget Impact: Slight Decrease
YEAR: 2023 2024 2025 2026 2027
COST: $12,867,000 Details: This project will rehabilitate Runway taxiways A, C, K, and L to current standards. The project will reduce crack sealing maintenance costs and bring the oldest pavement on the Airport up to the recommended Pavement Condition Index.
AIRFIELD FIREFIGHTING VEHICLE
REPLACEMENT Department: Airport Total Project Cost: $1,000,000 Project Phased: No Project Type: Equipment Funding Source(s): Grant Dependent Potential Grant Identified: Federal Aviation Admin Operating Budget Impact: Minimal or No Impact
YEAR: 2023 2024 2025 2026 2027
COST: $1,000,000 Details: This project will replace an existing 1992 model year Oshkosh TA1500 unit to allow for continued efficient airfield operations and safety standards.
12
AIRPORT FUND PROJECTS APRON AND WILLOW STREET EXTENSION Department: Airport Total Project Cost: $2,350,000 Project Phased: No Project Type: Land Improvement/ Infrastructure Funding Source(s): Grant Dependent Potential Grant Identified: Federal Aviation Administration Operating Budget Impact: Slight Increase
YEAR: 2023 2024 2025 2026 2027
COST: $2,350,000 Details: This project would extend the apron taxiway 600 feet for lease lots and Willow Street Extension (road and utilities) as well as provide for lease lot development (five acres). Lease lot development is assumed to be 100% City-funded. The City General Fund portion of the project is reflected in the General Fund section.
TERMINAL ROAD AND PARKING LOT IMPROVEMENTS Department: Airport Total Project Cost: $1,750,000 Project Phased: No Project Type: Infrastructure Funding Source(s): Grant Dependent Potential Grant Identified: Federal Aviation Admin Operating Budget Impact: Slight Increase
YEAR: 2023 2024 2025 2026 2027
COST: $1,750,000 Details: This project rehabilitates the access road, provides for parking lot expansion to the south, and installs new lighting poles at the Kenai Municipal Airport Terminal parking lot.
13
AIRPORT FUND PROJECTS ARFT FIRE TRAINING APPARATUS REPAIRS Department: Airport Total Project Cost: $100,000 Project Phased: No Project Type: Technology Funding Source(s): Airport Fund Potential Grant Identified: None Operating Budget Impact: Minimal
YEAR: 2023 2024 2025 2026 2027
COST: $100,000 Details: Planned maintenance to provide for the continued operation of the trainers. This equipment resides in very volatile conditions, with exposures to extreme cold and heat. As a result, many components require preventive maintenance to provide for reliable use.
14
Blank
15
GENERAL FUND FY2023
Project Name
Project
No.
Total
Project
Cost
City
Funding
Grant
Funding Description
Kenai Bluff
Stabilization
*Multi-year
Project
1 $17,500,000 $0 $17,500,000
Stabilize a one-mile area
on the northern bank of
the Kenai River
Repair of Inground
Water Tank 2 $60,000 $60,000 $0
Repairs to storage tank
used in functional testing
of apparatus
Phase II Willow
Street
Rehabilitation
3 $420,000 $420,000 $0
Milling & resurfacing of
roadway from Kenai Spur
to Airport Way
Rec Center RTU
HVAC
Replacements
Supplemental
Funding
4 $280,000 $280,000 $0
Replacement of
mechanical units beyond
their useful life
Fire Department
Apparatus Bay
Painting
5 $45,000 $45,000 $0 Strip and paint apparatus
bays at Fire Department
Kenai Nordic Trail
Lighting 6 $200,000 $0 $200,000
Design and construct
lighted Nordic trail at the
golf course
Facility
Assessments
Phase 2
7 $80,000 $80,000 $0
Engineering & Contracting
services to identify and
prioritize facility
maintenance projects
Lilac Street Repairs 8 $393,000 $393,000 $0
Replace failed concrete
curb and provide new
asphalt surface
Softball Field
Shelters/Dugouts
Replacement
9 $120,000 $120,000 $0 Replacement of existing
structures with new
Total $19,098,000 $1,398,000 $17,700,000
16
FY2024
Project Name
Project
No.
Total
Project
Cost
City
Funding
Grant
Funding Description
Kenai Bluff
Stabilization
*Multi-year
Project
10 $17,500,000 $2,550,000 $14,950,000
Stabilize a one-mile area
on the northern bank of
the Kenai River
Police/Fire Mobile
Radios 11 $100,000 $100,000 $0
Replacement of outdated
equipment with new
Motorola radios
City Hall Elevator
Major
Maintenance
12 $50,000 $50,000 $0
Replace 30-plus year-old
components in the
elevator
Softball Green
Strip Play
Equipment
Replacement
13 $85,000 $85,000 $0 Replace children’s
playground equipment
Aliak Storm Water
and Paving Repair 14 $400,000 $400,000 $0
Replacement of failed
storm line causing
roadway damages
Trail Development
at Municipal Park 15 $75,000 $75,000 $0 Trail Improvements
Police In-Car
Cameras 16 $100,000 $100,000 $0 Safety & Security
Improvements
Facility
Improvements to
be Identified
17 $500,000 $500,000 $0
Projects based on priority
need to be identified
through condition
assessments
Outdoor Event
Park Design and
Feasibility
18 $35,000 $35,000 $0
Provide engineered
drawings to construct an
event park
Total $18,845,000 $3,895,000 $14,950,000
17
FY2025
Project Name
Project
No.
Total
Project Cost
City
Funding
Grant
Funding Description
Storm Water CCTV
Inspections 19 $80,000 $80,000 $0
Maintenance repairs to the
stormwater conveyance
system
Future Stormwater
Improvements 20 $120,000 $120,000 $0
Maintenance repairs to the
stormwater conveyance
system
Kenai Multi-
Purpose Facility
Perm. Locker-
Rooms
21 $1,250,000 $0 $1,250,000 Construction of 5,000
square-foot locker room
Flight Services RTU
Replacements 22 $350,000 $350,000 $0 Replace roof-top unit at the
Flight Service Station
Old Town
Playground
Equipment
Replacement
23 $100,000 $100,000 $0 Replacement of aging
equipment with new
Future Road
Repairs 24 $450,000 $450,000 $0
Roadway Improvements
based on condition
assessments
Total $2,350,000 $1,100,000 $1,250,000 FY2026
Project Name
Project
No.
Total
Project
Cost
City
Funding
Grant
Funding Description
Future Stormwater
Improvements 25 $120,000 $120,000 $0
Maintenance repairs to the
stormwater conveyance
system
Emergency Service
Facility
Improvement
26 $750,000 $0 $750,000
Asbestos Removal and
various improvements to
facility layout
Street Lighting
Improvements –
Design
27 $80,000 $80,000 $0 Assessment of existing
systems
18
FY2026 Continued
Project Name
Project
No.
Total
Project
Cost
City
Funding
Grant
Funding Description
Future Road
Repairs 28 $450,000 $450,000 $0
Roadway Improvements
based on condition
assessments
Facility
Improvements to
be Identified
29 $500,000 $500,000 $0
Projects based on priority
need to be identified
through condition
assessments
Total $1,900,000 $1,150,000 $750,000 FY2027
Project Name
Project
No.
Total
Project
Cost
City
Funding
Grant
Funding Description
Future
Stormwater
Improvements
30 $120,000 $120,000 $0
Maintenance repairs to the
stormwater conveyance
system
Future Road
Repairs 31 $450,000 $450,000 $0
Roadway Improvements
based on condition
assessments
Street Lighting
Improvements –
Construction
32 $400,000 $400,000 $0
Implementation of
Improvements through
previous years’
assessments
Facility
Improvements to
be Identified
33 $500,000 $500,000 $0
Projects based on priority
need to be identified
through condition
assessments
Total $1,470,000 $1,470,000 $0
19
GENERAL FUND PROJECTS BLUFF STABILIZATION Department: Administration | Public Works Total Project Cost: $35,000,000 Project Phased: Yes Project Type: Infrastructure Funding Source(s): Grant Dependent | Bonding Potential Grant Identified: State Capital Project Submission and Federal Grants To Be Identified Operating Budget Impact: Slight Increase
YEAR: 2023 2024 2025 2026 2027
COST: $17,500,000 $17,500,000 Details: The City of Kenai in coordination with the Army Corp of Engineers Bluff Erosion Control Project is intended to stabilize an area on the northern bank of the Kenai River from near the river's mouth below Historic Old Town extending upriver approximately one mile toward the first cannery just below Bluff Overlook Park at the end of Spur View Drive.
REPAIR OF INGROUND WATER TANK Department: Fire Total Project Cost: $60,000 Project Phased: No Project Type: Building Improvement Funding Source(s): General Fund Potential Grant Identified: None Operating Budget Impact: Minimal
YEAR: 2023 2024 2025 2026 2027
COST: $60,000 Details: The Fire Department conducts its NFPA required Fire Engine Pump testing using the in-ground water tank located in the back parking lot of the Fire Department. Upon examination of the tank, it was discovered parts of the tank had rusted through exposing gravel and soil material that could be drafted into an engine's fire pump, causing major damage. This project will provide repairs to the existing tank.
20
GENERAL FUND PROJECTS Phase II WILLOW STREET REHABILITATION Department: Public Works Total Project Cost: $420,000 Project Phased: No Project Type: Infrastructure Funding Source(s): General Fund Potential Grant Identified: None Operating Budget Impact: Slight Decrease
YEAR: 2023 2024 2025 2026 2027
COST: $420,000 Details: This project includes milling and repaving of asphalt roadway approximately 40 feet in width and 1,950 feet in length between the Kenai Spur Highway and Airport Way.
KENAI RECREATION CENTER RTU HVAC REPLACEMENTS Department: Public Works Total Project Cost: $280,000 Project Phased: No Project Type: Building Improvement Funding Source(s): General Fund Potential Grant Identified: None Operating Budget Impact: Minimal or No Impact
YEAR: 2023 2024 2025 2026 2027
COST: $280,000 Details: This project will replace the oldest equipment first, including air handlers, control valves, and thermostats. The Kenai Recreation Center was constructed in 1980 with an addition added in 1982. Many of the mechanical systems are now 40 years old and require extensive maintenance to maintain operation.
21
GENERAL FUND PROJECTS FIRE DEPARTMENT APPARATUS BAY PAINTING Department: Fire Department Total Project Cost: $45,000 Project Phased: No Project Type: Building Improvement Funding Source(s): General Fund Potential Grant Identified: None Operating Budget Impact: Minimal or No Impact
YEAR: 2023 2024 2025 2026 2027
COST: $45,000 Details: This project strips the remaining finish from the floor in the Fire Department apparatus bays and repaints it with a durable paint designed for the fire department apparatus. The Apparatus bays of the Fire Department have not been refinished since the building was built in the early 1970s.
KENAI NORDIC TRAIL LIGHTING - DESIGN & CONSTRUCTION Department: Parks & Recreation Total Project Cost: $200,000 Project Phased: No Project Type: Infrastructure Funding Source(s): Grant Dependent Potential Grant Identified: Land Water Conservation Fund Operating Budget Impact: Slight Increase
YEAR: 2023 2024 2025 2026 2027
COST: $200,000 Details: This project includes the design and construction of a lighted Nordic trail system at the Kenai Municipal Golf Course. The design will dictate future phases and feasibility, but it is anticipated that the first phase of trail lighting would focus on the driving range and central bowl area near the clubhouse.
22
GENERAL FUND PROJECTS FACILITY ASSESSMENTS PHASE 2
Department: Public Works Total Project Cost: $80,000 Project Phased: Project Type: Funding Source(s): Potential Grant Identified: Operating Budget Impact:
YEAR: 2023 2024 2025 2026 2027
COST: $80,000 Details: These funds will assist the Building Maintenance and Public Works Department in identifying priority-related issues within our facilities. Funding will be used to conduct sampling for hazardous materials and hiring of professional services to assist with the development of Scopes of Work for problem areas.
LILAC STREET REPAIRS Department: Public Works Total Project Cost: $393,000 Project Phased: No Project Type: Infrastructure Funding Source(s): General fund Potential Grant Identified: None Operating Budget Impact: Slight Decrease
YEAR: 2023 2024 2025 2026 2027
COST: $393,000 Details: This project replaces the failed concrete curb in affected areas, re-stabilizes settled subbase areas, and provides a new asphalt surface course along approximately 1600 linear feet of 30-foot wide roadway. Lilac Lane is located off the Spur Highway and Cook Inlet View Drive on the north side of Kenai. The roadway and concrete curb and gutter are suffering from severe settlement in multiple areas.
23
GENERAL FUND PROJECTS SOFTBALL FIELD SHELTERS/DUGOUTS REPLACEMENT Department: Parks and Recreation Total Project Cost: $120,000 Project Phased: No Project Type: Facility Improvement Funding Source(s): General Fund Potential Grant Identified: None Operating Budget Impact: Slight Decrease
YEAR: 2023 2024 2025 2026 2027
COST: $120,000 Details: This project will replace existing facilities that are falling into disrepair with new ones. There are four fields in total located between Coral St. and Main St. Loop, and they are widely used by the community throughout the summer months.
POLICE/FIRE MOBILE RADIOS Department: Police Department/Fire Department Total Project Cost: $100,000 Project Phased: Project Type: Technology Funding Source(s): Grant Depen Potential Grant Identified: Operating Budget Impact:
YEAR: 2023 2024 2025 2026 2027
COST: $100,000 Details: Replacement of existing radio equipment with new.
24
GENERAL FUND PROJECTS CITY HALL ELEVATOR MAINTENANCE Department: Public Works Total Project Cost: $50,000 Project Phased: No Project Type: Building Improvement Funding Source(s): General Fund Potential Grant Identified: None Operating Budget Impact: Minimal or No Impact
YEAR: 2023 2024 2025 2026 2027
COST: $50,000 Details: This project provides major maintenance on the existing City Hall Elevator. This will replace 30+-year-old components for safety purposes while providing minor cosmetic improvements.
SOFTBALL GREEN STRIP PLAY EQUIPMENT REPLACEMENT Department: Parks & Recreation Total Project Cost: $85,000 Project Phased: No Project Type: Equipment Funding Source(s): General Fund Potential Grant Identified: None Operating Budget Impact: Minimal or No Impact
YEAR: 2023 2024 2025 2026 2027
COST: $85,000 Details: This project replaces an aging and obsolete children's playground located at one of the most heavily used outdoor locations. This area is near the adult softball fields and adjacent to a large green strip with a shelter and restrooms.
25
GENERAL FUND PROJECTS ALIAK STORMWATER AND PAVING REPAIR Department: Public Works Total Project Cost: $400,000 Project Phased: Project Type: Infrastructure Funding Source(s): General Fund Potential Grant Identified: None Operating Budget Impact: Moderate Decrease
YEAR: 2023 2024 2025 2026 2027
COST: $400,000 Details: This project will begin to address a failed stormwater line on Aliak Dr. between Candlelight Dr. and Highbush Ln. The galvanized piping has collapsed in several locations which causes the occasional sinkhole to surface after significant runoff. The photo above is from April 2021 shortly after the breakup. The staff has been filling these in with gravel and then patching the asphalt as short-term solutions. This project will require the removal of sections of roadway and the replacement of existing stormwater piping with new and then resurfacing of the roadway.
TRAIL DEVELOPMENT AT MUNICIPAL PARK Department: Parks and Recreation Total Project Cost: $75,000 Project Phased: Project Type: Funding Source(s): Potential Grant Identified: Operating Budget Impact:
YEAR: 2023 2024 2025 2026 2027
COST: $75,000 Details: This project is intended to enhance the widely used trails located at Municipal Park. The Trail system goes from the park down to the beach, and this work will make the area more accessible to all users.
26
GENERAL FUND PROJECTS
POLICE IN-CAR CAMERAS Department: Police Department Total Project Cost: $100,000 Project Phased: No Project Type: Technology Funding Source(s): Grant Dependent Potential Grant Identified: Department of Homeland Security Operating Budget Impact: Slight Increase
YEAR: 2023 2024 2025 2026 2027
COST: $100,000 Details: This project will expand on the Kenai Police Department’s purchase of In-Car Cameras. Several of the new recently purchased vehicles are being up-fitted with this equipment installed, this project will provide cameras within other vehicles within the Fleet. Currently, there are a total of 18 police vehicles to be equipped
OUTDOOR EVENT PARK DESIGN AND FEASIBILITY Department: Parks & Recreation Total Project Cost: $35,000 Project Phased: Yes Project Type: Infrastructure Funding Source(s): General Fund Potential Grant Identified: None Operating Budget Impact: Slight Increase
YEAR: 2023 2024 2025 2026 2027
COST: $35,000 Details: This project will provide engineered drawings to construct an event park to include a stage, restrooms, parking lot, and utilities. The phased project would construct an elevated stage with future phases of the project to include the construction of a permanent restroom with utilities, spectator area, event area, vendor area, and parking lot.
27
GENERAL FUND PROJECTS STORMWATER CCTV INSPECTIONS Department: Public Works Total Project Cost: $80,000 Project Phased: No Project Type: Infrastructure Funding Source(s): Water Sewer Fund Potential Grant Identified: None Operating Budget Impact: Minimal
YEAR: 2023 2024 2025 2026 2027
COST: $80,000 Details: This project is intended to provide insight into the existing condition of forty-fifty-year-old stormwater conveyance piping. The system is currently poorly mapped and multiple areas within the city have experienced issues with rusting and deteriorating piping and pipe connections which result in sinkholes and pipe failures. Information gathered will be used to direct future repair projects.
FUTURE STORMWATER IMPROVEMENTS Department: Public Works Total Project Cost: $360,000 Project Phased: Yes Project Type: Infrastructure Funding Source(s): General fund Potential Grant Identified: None Operating Budget Impact:
YEAR: 2023 2024 2025 2026 2027
COST: $120,000 $120,000 $120,000 Details: This project will allow Public Works to continue to address stormwater runoff, culvert, and catch basin issues as they continue to deteriorate throughout the City.
28
GENERAL FUND PROJECTS KENAI MULTI-PURPOSE FACILITY PERMANENT LOCKER ROOMS Department: Parks & Recreation Total Project Cost: $1,250,000 Project Phased: No Project Type: Building Improvement Funding Source(s): Grant Dependent Potential Grant Identified: State of Alaska Operating Budget Impact: Slight Decrease
YEAR: 2023 2024 2025 2026 2027
COST: $1,250,000 Details: This project constructs six locker rooms at the Kenai Multi-purpose Facility. This would include utilities, bathrooms, shower rooms, and related appurtenances. Approx. 5,000 SF. The Facility was designed to an ultimate "build-out" which included locker rooms, enhanced seating, building insulation, heating systems, etc. Without locker rooms which include showers and other appurtenances, use of the Facility is limited.
FLIGHT SERVICES RTU REPLACEMENT Department: Public Works Total Project Cost: $350,000 Project Phased: No Project Type: Building Improvement Funding Source(s): General Fund Potential Grant Identified: Operating Budget Impact: Minimal or No Impact
YEAR: 2023 2024 2025 2026 2027
COST: $350,000 Details: This project will replace the HVAC roof-top units that have reached the end of their useful life at the Flight Service Station. The facility owned by the City has a long-term tenant in the Federal Aviation Administration leasing the building. The reliability of these units is integral in supporting their operations.
29
GENERAL FUND PROJECTS OLD TOWN PLAYGROUND EQUIPMENT REPLACEMENT Department: Parks and Recreation Total Project Cost: $100,000 Project Phased: Project Type: Funding Source(s): Potential Grant Identified: Operating Budget Impact:
YEAR: 2023 2024 2025 2026 2027
COST: $100,000 Details: This project will replace aging equipment at the Park on Peninsula Ave adjacent to the Fine Arts Center. The area of Old Town attracts numerous visitors every year. The park is located two blocks from the Visitor’s Center and is in close proximity to several large housing complexes providing plenty of children to utilize the park.
FUTURE ROAD REPAIRS Department: Public Works Total Project Cost: $1,350,000 Project Phased: No Project Type: Infrastructure Funding Source(s): General Fund Potential Grant Identified: TBD Operating Budget Impact: TBD
YEAR: 2023 2024 2025 2026 2027
COST: $450,000 $450,000 $450,000 Details: The Public Works Department continues to monitor roadways. Staff continues to utilize the 2009 Roadway Improvement Survey that reviewed and graded all City Roads at that time. Roadway conditions and traffic demand determine which roads receive priority. Funding may be used for capping of existing gravel roadways, replacement of existing asphalt through milling and paving, as well as point repairs for specific smaller areas experiencing sub-base failures.
30
GENERAL FUND PROJECTS EMERGENCY SERVICES FACILITY IMPROVEMENT Department: Police Department/Fire Department Total Project Cost: $750,000 Project Phased: No Project Type: Facility Improvement Funding Source(s): Potential Grant Identified: Dept. of Homeland Security Operating Budget Impact: Minimal
YEAR: 2023 2024 2025 2026 2027
COST: $750,000 Details: This project will provide much-needed renovations to the facility. The building is known to have asbestos which has limited opportunities for smaller renovations. This project will identify hazards, provide a code assessment of the facility, and make modifications as appropriate.
STREET LIGHTING IMPROVEMENTS -
DESIGN Department: Public Works Total Project Cost: $80,000 Project Phased: Yes Project Type: Infrastructure Funding Source(s): General Fund Potential Grant Identified: None Operating Budget Impact: Slight Decrease
YEAR: 2023 2024 2025 2026 2027
COST: $80,000 Details: This project will identify underserved and problem locations for street lighting to improve safety and security for citizens. New lighting will be LED to reduce energy and maintenance costs. This first project will provide for the design and identification of locations to be served.
31
GENERAL FUND PROJECTS STREET LIGHTING IMPROVEMENTS - CONSTRUCTION Department: Public Works Total Project Cost: $400,000 Project Phased: Yes Project Type: Infrastructure Funding Source(s): General Fund Potential Grant Identified: None Operating Budget Impact: Slight Decrease
YEAR: 2023 2024 2025 2026 2027
COST: $400,000 Details: This project will implement the lighting needs identified in the previous years’ effort. The first phase provided bid-ready construction documents, this phase will provide for construction implementation.
FACILITY IMPROVEMENTS TO BE IDENTIFIED Department: Public Works Total Project Cost: $1,500,000 Project Phased: Yes Project Type: Building Improvements Funding Source(s): General Fund Potential Grant Identified: TBD Operating Budget Impact: TBD
YEAR: 2023 2024 2025 2026 2027
COST: $500,000 $500,000 $500,000 Details: This project provides facility improvements to be identified and based on a facility assessment for City buildings that looks at each part of a building's infrastructure and reports system conditions, code deficiencies, and functional effectiveness.
32
WATER & SEWER FUND FY2023
Project Name
Project
No.
Total
Project
Cost
City
Funding
Grant
Funding Description
WTP Pump House
Construction 1 $1,500,000 $1,500,000 $0 Construct water
treatment pump house.
Lift Station
Renovations – Phase
II
2 $400,000 $0 $400,000
Continuing with
replacement of Lift
Station Pumps &
Controls
WWTP - Digestor
Blowers
Construction
3 $2,800,000 $0 $2,800,000
Replacement of 40-
year-old equipment,
piping, and controls
WWTP, W&S
Electronic Access
Gate & Controls
4 $100,000 $100,000 $0
Provide restricted
electronic access for
security
Total $4,800,000 $1,600,000 $3,200,000
FY2024
Project Name
Project
No.
Total
Project
Cost
City
Funding
Grant
Funding Description
Major lift Station
Renovations – Broad
Station
5 $600,000 $600,000 $0
Complete Renovation of
the Broad Street Lift
Station – new wet well,
pumps, controls, and
backup generator
Airport Reservoir
Pump House
Improvements
6 $1,500,000 $150,000 $1,350,000
Replacement of pumps,
controls, and valves
including pressure
monitoring
WWTP Ops Building
Renovations 7 $2,580,000 $250,000 $2,230,000
Facility improvements
include exterior finishes
and roofing, insulation,
floorplan modifications
to modernize the facility
Total $4,680,000 $1,000,000 $3,580,000
33
WATER & SEWER FUND FY2025
Project Name
Project
No.
Total
Project
Cost
City
Funding
Grant
Funding Description
Lift Station
Renovations – Phase
III
8 $400,000 $0 $400,000
Continuing with
replacement of Lift
Station Pumps &
Controls
Standby Power
Upgrades 9 $200,000 $200,000 $0
Lift Station Backup
Power Generators at
select locations
WWTP Rotary
Screen Replacement
with Combination
Screens
10 $1,750,000 $0 $1,750,000
Replace 40-year-old
equipment and controls
with more modern
technology
Total $2,350,000 $200,000 $2,150,000
FY2026
Project Name
Project
No.
Total
Project
Cost
City
Funding
Grant
Funding Description
Water, Sewer,
WWTP, Facility
Fencing
Improvements
11 $200,000 $200,000 $0 Security Improvements
SCADA Integration
Waste Water 12 $500,000 $500,000 $0
Major Controls project
for the Wastewater
Plant to provide remote
monitoring of newly
installed equipment
WWTP Effluent Flow
Monitoring/Automa
ted Dosing
13 $225,000 $0 $225,000
Environmental
upgrades to remain in
compliance with
Discharge Permitting
requirements
Total $925,000 $700,000 $225,000
34
WATER & SEWER FUND FY2027
Project Name
Project
No.
Total
Project
Cost
City
Funding
Grant
Funding Description
WWTP Influent
Pump Station 14 $1,000,000 $0 $1,000,000
Infrastructure / Process
improvements to
provide influent surge
protection as well as
grease and grit control
Total $1,000,000 $0 $1,000,000
35
WATER & SEWER PROJECTS WTP PUMP HOUSE - CONSTRUCTION Department: Public Works – Water & Sewer Total Project Cost: $1,500,000 Project Phased: Project Type: Funding Source(s): Potential Grant Identified: Operating Budget Impact:
YEAR: 2023 2024 2025 2026 2027
COST: $1,500,000
Details: This Project is the next step in the development of the City’s Water System. In 2011 the Water Treatment Facility located at the intersection of Shotgun Drive and the Kenai Spur Highway was developed. In 2015/2016 Well Field Improvements were completed. This project will update the distribution pumps that transport water from the water plant to all end users. Completion of this work will improve system reliability while increasing our ability to meet system demand.
LIFT STATION RENOVATIONS – Phase II Department: Public Works - Water & Sewer Total Project Cost: $400,000 Project Phased: Yes Project Type: Infrastructure Funding Source(s): Water & Sewer Fund Potential Grant Identified: None Operating Budget Impact: Moderate Savings
YEAR: 2023 2024 2025 2026 2027
COST: $400,000
Details: This project provides for major maintenance on existing lift stations to include access, structural, security, and safety upgrades.
36
WATER & SEWER PROJECTS WWTP - DIGESTER BLOWERS CONSTRUCTION Department: Public Works - Water & Sewer Total Project Cost: $2,800,000 Project Phased: No Project Type: New Building & Equipment Funding Source(s): Grant Dependent Potential Grant Identified: None Operating Budget Impact: Significant Decrease
YEAR: 2023 2024 2025 2026 2027
COST: $2,800,000 Details: This project will replace two 40-year-old blowers with new and installation of the new blowers in a new approximately 24 x 24 square foot prefab metal building located adjacent to the existing digester tank. This project is anticipated to provide significant operational and energy savings for the department.
WWTP ELECTRONIC ACCESS GATE & CONTROLS Department: Public Works - Water & Sewer Total Project Cost: $100,000 Project Phased: No Project Type: Technology Funding Source(s): Water & Sewer Fund Potential Grant Identified: None Operating Budget Impact: Minimal or No Impact
YEAR: 2023 2024 2025 2026 2027
COST: $100,000
Details: This project will provide restricted electronic access control to the Wastewater Treatment Plant entrance for safety and security.
37
WATER & SEWER PROJECTS MAJOR LIFT STATION RENOVATIONS – BROAD STREET Department: Public Works – Water & Sewer Total Project Cost: $600,000 Project Phased: No Project Type: Infrastructure Funding Source(s): Water & Sewer Fund Potential Grant Identified: None Operating Budget Impact: Significant Decrease
YEAR: 2023 2024 2025 2026 2027
COST:
$600,000
Details: This project will provide much-needed major improvements to the Broad Street Lift Station. This is a major collection site with all connections east of Broad St. running through this site before proceeding to the Waste Water Plant. This project will increase the capacity of the existing site, provide emergency backup power generation, and replacement of pumps and controls with new ones.
AIRPORT RESERVOIR PUMP HOUSE IMPROVEMENTS Department: Public Works – Water & Sewer Total Project Cost: $1,500,000 Project Phased: No Project Type: Infrastructure Funding Source(s): Water & Sewer Fund / Grant Potential Grant Identified: Federal & State Options Operating Budget Impact: Moderate Decrease
YEAR: 2023 2024 2025 2026 2027
COST:
$1,500,000
Details: This project will provide for equipment replacements at the Airport Reservoir Pump House. This site has a three million gallon storage tank which provides the majority of water for the City during daytime hours. This work will utilize the existing building, but modify pumps and controls to provide a more robust and reliable system.
38
WATER & SEWER PROJECTS WWTP OPS BUILDING RENOVATIONS Department: Public Works - WWTP Total Project Cost: $2,580,000 Project Phased: No Project Type: Building Improvement Funding Source(s): Water Sewer Fund / Grant Potential Grant Identified: Federal & State Options Operating Budget Impact: Significant Decrease
YEAR: 2023 2024 2025 2026 2027
COST:
$2,580,000
Details: This project will provide much-needed improvements to the main operations building at the Waste Water Plant which was originally constructed in 1974 with improvements completed in 1982. The Facility is on the shore of Cook Inlet and subject to the constant presence of salt air. As a result, much of the facility doors, windows, siding, hardware, etc. have rusted beyond repair. This project will provide a much-needed facelift with improvements anticipated to help with improved energy savings.
LIFT STATION RENOVATIONS – PHASE III Department: Public Works - Water & Sewer Total Project Cost: $400,000 Project Phased: Yes Project Type: Infrastructure Funding Source(s): Water & Sewer Fund Potential Grant Identified: None Operating Budget Impact: Minimal or No Impact YEAR: 2023 2024 2025 2026 2027
COST:
$400,000
Details: This project provides for major maintenance on existing lift stations to include access, structural, security, and safety upgrades.
39
WATER & SEWER PROJECTS STANDBY POWER UPGRADES Department: Public Works – Water & Sewer Total Project Cost: $200,000 Project Phased: No Project Type: Technology / Infrastructure Funding Source(s): Water & Sewer Fund Potential Grant Identified: None Operating Budget Impact: Slight Increase
YEAR: 2023 2024 2025 2026 2027
COST:
$200,000
Details: This project will provide emergency backup power generation for several lift station sites.
WWTP ROTARY SCREEN REPLACEMENT Department: Public Works - Water & Sewer Total Project Cost: $1,750,000 Project Phased: Yes Project Type: Equipment Funding Source(s): Grant Dependent Potential Grant Identified: None Operating Budget Impact: Moderate Decrease
YEAR: 2023 2024 2025 2026 2027
COST:
$1,750,000
Details: This project will replace 40-year old equipment with new technology and controls. This is an integral part of the treatment process. Effectively screening the influent safeguards pumps and controls downstream, allowing operators the ability to manage the treatment process.
40
WATER & SEWER PROJECTS FACILITY FENCING IMPROVEMENTS Department: Public Works – Water & Sewer/WWTP Total Project Cost: $200,000 Project Phased: Yes Project Type: Infrastructure Funding Source(s): Water & Sewer Fund Potential Grant Identified: None Operating Budget Impact: Minimal
YEAR: 2023 2024 2025 2026 2027
COST:
$200,000
Details: This project will replace 40-year-old fencing and improve site security at several locations.
SCADA INTEGRATION WASTEWATER Department: Public Works - WWTP Total Project Cost: $500,000 Project Phased: No Project Type: Technology Funding Source(s): Water & Sewer Fund Potential Grant Identified: None Operating Budget Impact: Minimal
YEAR: 2023 2024 2025 2026 2027
COST:
$500,000
Details: This project will provide major components to get all of the new equipment installed over the last several years tied back to one SCADA system to improve operator response time and troubleshooting abilities.
41
WATER & SEWER PROJECTS WWTP EFFLUENT FLOW MONITORING/AUTOMATED DOSING Department: Public Works - WWTP Total Project Cost: $225,000 Project Phased: No Project Type: Technology Funding Source(s): Grant Potential Grant Identified: Federal & State Options Operating Budget Impact: Moderate Decrease
YEAR: 2023 2024 2025 2026 2027
COST:
$225,000
Details: This project will provide equipment to provide more accurate dosing of chemicals in the treatment of wastewater effluent which will result in savings on Sodium Hypochlorite and Sodium Bisulfate. Chemical feed will vary based on the flow of effluent leaving the plant.
WWTP INFLUENT PUMP STATION Department: Public Works - Water & Sewer Total Project Cost: $1,000,000 Project Phased: Yes Project Type: Infrastructure Funding Source(s): Grant Dependent Potential Grant Identified: None Operating Budget Impact: Moderate Increase
YEAR: 2023 2024 2025 2026 2027
COST:
$1,000,000 Details: This project will replace the existing influent station and install a new pump station to provide surge protection storage and grit capture. This will allow for more balanced incoming flows into the plant and reduce staff time on recovering from surges.
42
SENIOR CITIZENS FUND FY2023
Project Name
Project
No.
Total
Project
Cost
City
Funding
Grant
Funding Description
No Data
Total FY2024
Project Name
Project
No.
Total
Project
Cost
City
Funding
Grant
Funding Description
Emergency Backup
Power Generation 1 $125,000 $0 $125,000
Total $125,000 $0 $125,000 FY2025
Project Name
Project
No.
Total
Project
Cost
City
Funding
Grant
Funding Description
Senior Center
Landscaping
Project Phase I
2 $40,000 $0 $40,000
Landscape the south lawn of
the Senior Center to a level
area
Total $40,000 $0 $40,000
43
SENIOR CITIZENS FUND FY2026
Project Name
Project
No.
Total
Project
Cost
City
Funding
Grant
Funding Description
Senior Center
Landscaping
Project Phase II
3 $35,000 $0 $35,000 Create a community fire pit
area with memorial benches
Total $35,000 $0 $35,000
FY2027
Project Name
Project
No.
Total
Project
Cost
City
Funding
Grant
Funding Description
No Data
Total
44
SENIOR CITIZENS FUND PROJECTS
EMERGENCY BACKUP POWER GENERATION Department: Senior Center Total Project Cost: $125,000 Project Phased: Yes Project Type: Building Improvement Funding Source(s): Grant/ Donation Dependent Potential Grant Identified: State Operating Budget Impact: Slight Increase
2023 2024 2025 2026 2027
COST: $125,000 Details: This project would provide emergency backup power to the Senior Center. The facility is a gathering place for the community and provides needed meal services to the elderly. In the event of a major weather event, earthquake, etc., the ability to provide for the continued operation of the facility is an intricate resource for the City.
SENIOR CENTER LANDSCAPING - PHASE I Department: Senior Center Total Project Cost: $40,000 Project Phased: Yes Project Type: Land Improvement Funding Source(s): Grant/ Donation Dependent Potential Grant Identified: State Operating Budget Impact: Minimal or No Impact
2023 2024 2025 2026 2027
COST: $40,000 Details: This project would landscape the south lawn of the Senior Center to level the area, which now contains sunken areas which prohibit safe access and replant grass and trees as well as construct walkways for easy and safe maneuvering. This would improve lost access to the perimeter of the building, yard, and bluff areas for private rentals and the public, including wheelchair access. The project would be contingent on the construction of the Bluff Stabilization Project.
45
SENIOR CITIZENS FUND PROJECTS
SENIOR CENTER LANDSCAPING - PHASE II Department: Senior Center Total Project Cost: $35,000 Project Phased: Yes Project Type: Land Improvement Funding Source(s): Grant/ Donation Dependent Potential Grant Identified: State Operating Budget Impact: Minimal or No Impact
2023 2024 2025 2026 2027
COST: $35,000 Details: This project would create a community fire pit area with wooden all-weather park benches for easy access for seniors and private rentals. Memorial benches and greenery provide an opportunity to generate revenue and celebrate individuals in the community. The project would be contingent on the construction of the Bluff Stabilization Project.
46
CONGREGATE HOUSING FUND FY2023
Project Name
Project
No.
Total
Project
Cost
City
Funding
Grant
Funding Description
Apartment Kitchen
and Bathroom
Remodel
1 $100,000 $100,000 $0 Remodel the kitchen and
bathrooms in 3-6 apartments
Total $100,000 $100,000 $0 FY2024
Project Name
Project
No.
Total
Project
Cost
City
Funding
Grant
Funding Description
Apartment Kitchen
and Bathroom
Remodel
2 $100,000 $100,000 $0 Remodel the kitchen and
bathrooms in 3-6 apartments
Vintage Pointe
Elevator Major
Maintenance
3 $50,000 $50,000 $0
Major elevator maintenance
to allow for continued safe
operation
Total $150,000 $150,000 $0 FY2025
Project Name
Project
No.
Total
Project
Cost
City
Funding
Grant
Funding Description
Apartment Kitchen
and Bathroom
Remodel
4 $100,000 $100,000 $0 Remodel the kitchen and
bathrooms in 3-6 apartments
Total $100,000 $100,000 $0
47
CONGREGATE HOUSING FUND FY2026
Project Name
Project
No.
Total
Project
Cost
City
Funding
Grant
Funding Description
Apartment Kitchen
and Bathroom
Remodel
5 $100,000 $100,000 $0 Remodel the kitchen and
bathrooms in 3-6 apartments
Total $100,000 $100,000 $0 FY2027
Project Name
Project
No.
Total
Project
Cost
City
Funding
Grant
Funding Description
No Data
Total
48
CONGREGATE HOUSING FUND PROJECTS
APARTMENT KITCHEN AND BATHROOM REMODEL Department: Senior Center Total Project Cost: $500,000 Project Phased: Yes Project Type: Building Improvement Funding Source(s): Congregate Housing Fund Potential Grant Identified: None Operating Budget Impact: Minimal or No Impact
YEAR: 2023 2024 2025 2026 2027
COST: $100,000 $100,000 $100,000 $100,000 Details: This project remodels the kitchen and bathrooms in three to six apartments each year at Vintage Pointe. The project would replace original (1993) tile flooring, cabinetry, countertops, and fixtures in kitchens and bathrooms to bring apartments into compliance with the Americans with Disabilities Act. This project is not eligible for low-income housing grants.
VINTAGE POINTE ELEVATOR MAJOR MAINTENANCE Department: Public Works Total Project Cost: $50,000 Project Phased: Yes Project Type: Building Improvement Funding Source(s): Congregate Housing Fund Potential Grant Identified: None Operating Budget Impact: Minimal or No Impact
YEAR: 2023 2024 2025 2026 2027
COST: $50,000 Details: This project will provide for major maintenance of the Vintage Pointe elevator to allow for the continued safe operation of the City's most used elevator. The Vintage Pointe Senior Housing was constructed in 1993 and is approximately 40,450 square feet.
49
Blank
50
PERSONAL USE FISHERY FUND FY2023
Project Name
Project
No.
Total
Project
Cost
City
Funding
Grant
Funding Description
Personal Use
Fishery Float
Replacements
$50,000 $50,000 $0 Purchase ten new floats at
the City Dock
Total $50,000 $50,000 $0 FY2024
Project Name
Project
No.
Total
Project
Cost
City
Funding
Grant
Funding Description
No Data
FY2025
Project Name
Project
No.
Total
Project
Cost
City
Funding
Grant
Funding Description
Boat Ramp
Concrete Repairs $135,000 $0 $135,000 Replace concrete ramps at
the City Dock
Total $135,000 $0 $135,000
51
PERSONAL USE FISHERY FUND FY2026
Project Name
Project
No.
Total
Project
Cost
City
Funding
Grant
Funding Description
No Data
Total FY2027
Project Name
Project
No.
Total
Project
Cost
City
Funding
Grant
Funding Description
No Data
52
PERSONAL USE FISHERY FUND PROJECTS
PERSONAL USE FISHERY FLOAT REPLACEMENT Department: Public Works Total Project Cost: $50,000 Project Phased: Yes Project Type: Infrastructure Funding Source(s): Personal Use Fishery Fund Potential Grant Identified: None Operating Budget Impact: Minimal or No Impact
YEAR: 2023 2024 2025 2026 2027
COST: $50,000 Details: This project, which began in FY2021 purchases ten new floats at the City Dock and Boat Ramp to replace existing floats. There are currently 22 float sections in total for the ramp and another eight for the front of the trestle.
CITY DOCK BOAT RAMP CONCRETE REPAIRS Department: Public Works Total Project Cost: $135,000 Project Phased: Yes Project Type: Infrastructure Funding Source(s): Personal Use Fishery Fund/ State Grant Potential Grant Identified: State Operating Budget Impact: Minimal or No Impact
YEAR: 2023 2024 2025 2026 2027
COST: $135,000 Details: This project will replace the concrete ramps at the City Dock in FY2022 and FY2025. The FY2022 portion of the project will be funded with the State of Alaska North and South Beach Improvement Grant.
52
PERSONAL USE FISHERY FUND PROJECTS
PERSONAL USE FISHERY FLOAT REPLACEMENT Department: Public Works Total Project Cost: $50,000 Project Phased: Yes Project Type: Infrastructure Funding Source(s): Personal Use Fishery Fund Potential Grant Identified: None Operating Budget Impact: Minimal or No Impact
YEAR: 2023 2024 2025 2026 2027
COST: $50,000 Details: This project, which began in FY2021 purchases ten new floats at the City Dock and Boat Ramp to replace existing floats. There are currently 22 float sections in total for the ramp and another eight for the front of the trestle.
CITY DOCK BOAT RAMP CONCRETE REPAIRS Department: Public Works Total Project Cost: $135,000 Project Phased: Yes Project Type: Infrastructure Funding Source(s): Personal Use Fishery Fund/ State Grant Potential Grant Identified: State Operating Budget Impact: Minimal or No Impact
YEAR: 2023 2024 2025 2026 2027
COST: $135,000 Details: This project will replace the concrete ramps at the City Dock in FY2022 and FY2025. The FY2022 portion of the project will be funded with the State of Alaska North and South Beach Improvement Grant.