AND VISITOR CENTER IMPROVEMENT CAPITAL PROJECT FUNDS TO PROVIDE SUPPLEMENTAL
FUNDING FOR THE ROOF REPLACEMENT PROJECT.
WHEREAS, the Visitor's Center asphalt roof has reached the end of its intended life, Construction Bid
Documents were developed in the Spring 2022 with a formal Invitation to Bid for Construction released
on June 21, 2022; and,
WHEREAS, two bids were received on July 19, 2022 well in excess of budgeted amounts; and,
WHEREAS, it was determined that due to cost escalation factors and an excessive amount of work in
the area limiting available competition, that the project would be delayed and released under more
favorable time lines; and,
WHEREAS, the Public Works Department intends to release the project for bids in January/February
2023 with construction intended for May/June 2023; and,
WHEREAS, the additional funding requested with this Ordinance is intended to account for inflationary
factors and additional Scope of Work items not included within the original cost estimate; and,
WHEREAS, completion of this Work is necessary to avoid potential interior damages, and is intended to
safeguard the facility for the next 25 years.
NOW, THEREFORE, BE IT ORDAINED BY THE COUNCIL OF THE CITY OF KENAI, ALASKA, AS
FOLLOWS:
Section 1. That the following budget revision is authorized:
Visitor Center Improvement Capital Project Fund:
Increase Estimated Revenues —
General Fund $1QQ�QQ4
Increase Appropriations —
Visitor Center Roof Replacement Project $100,000
Section 2. Severability: That if any part or provision of this ordinance or application thereof to any
person or circumstances is adjudged invalid by any court of competent jurisdiction, such judgment shall
be confined in its operation to the part, provision, or application directly involved in all controversy in
which this judgment shall have been rendered, and shall not affect or impair the validity of the remainder
of this title or application thereof to other persons or circumstances. The City Council hereby declares
that it would have enacted the remainder of this ordinance even without such part, provision, or
application.
Section 3. Effective Date: That pursuant to KMC 1.15.070(f), this ordinance shall take effect
immediately upon enactment.
New Text Underlined; [DELETED TEXT BRACKETED]
Ordinance No. 3329-2022
Page 2 of 2
ENACTED BY THE COUNCIL OF THE CITY OF KENAI, ALASKA, THIS 4T" DAY OF JANUARY, 2023.
ATTEST:
Michelle Sa MC, City Clerk
Approved by Finance:
�6es—Baisden, Vice Mayor
Introduced
Enacted:
Effective:
New Text Underlined; [DELETED TEXT BRACKETED]
December 21, 2022
January 4, 2023
January 4, 2023
K! NAI
City of Kenai 1210 Fidalgo Ave, Kenai, AK 99611-7794 1907.283.7535 ( www.kenai.city
MEMORANDUM
TO:
Mayor Gabriel and Council Members
THROUGH:
Paul Ostrander, City Manager
FROM:
Scott Curtin, Public Works Director
DATE:
December 13, 2022
SUBJECT:
Ordinance No. 3329-2022 — Visitor Center Roof Replacement
The purpose of this Ordinance is to provide supplemental funding to this project to allow the
Department to move forward with bidding. The original project estimate was based on square
foot costs of asphalt shingle removal and replacement. As the construction documents were
developed additional items were identified that are appropriate to be addressed at this time
including various flashings and roof drains, which impacted costs. High oil prices have also
contributed to the cost of asphalt shingles, along with the supply chain issues which continue to
be more common the last few years.
As stated in the Ordinance the project was originally bid in June 2022. Material costs were high
and contractors were busy at that time. Our intentions are to rebid for a construction start earlier
in the season, in a more competitive environment.
This project is essential to protect the facility. Completion of the Work is expected to safeguard
the roof system for another 25 years. Completion of this Work at this time is in the best interest
of the City. Council's support is respectfully requested.