ORDINANCE NO. 3330-2022
Sponsored by: Administration
AN ORDINANCE INCREASING ESTIMATED REVENUES AND APPROPRIATIONS IN THE GENERAL
AND RECREATION CENTER IMPROVEMENT CAPITAL PROJECT FUNDS TO PROVIDE
SUPPLEMENTAL FUNDING FOR THE KENAI RECREATION CENTER IMPROVEMENTS PROJECT.
WHEREAS, the Recreation Center Improvements Project has finalized bid ready construction documents
including a cost estimate; and,
WHEREAS, this project is primarily focused on the replacement of the existing roof system along with
various mechanical HVAC unit replacements; and,
WHEREAS, during the design numerous code and performance type issues were .identified, many of
which have been included within the bid documents which is why the additional funding is being
requested; and,
WHEREAS, there remains many code and maintenance type issues within the facility that are not being
undertaken with this project that would likely require an additional $1,000,000 in funding to address; and,
WHEREAS, approval of this Ordinance will allow the facility's roof, which is actively leaking in several
locations, to be replaced extending the life of the facility and the replacement of multiple failed and end
of useful life HVAC units will assist with the long term safeguarding and maintenance of the facility; and,
WHEREAS, completion of this Work is in the best interest of the City.
NOW, THEREFORE, BE IT ORDAINED BY THE COUNCIL OF THE CITY OF KENAI, ALASKA, AS
FOLLOWS:
Section 1. That the following budget revision is authorized:
Recreation Center Improvement Capital Project Fund:
Increase Estimated Revenues —
General Fund $210,000
Increase Appropriations —
Kenai Recreation Center Improvements Project $210.000
Section 2. Severability: That if any part or provision of this ordinance or application thereof to any
person or circumstances is adjudged invalid by any court of competent jurisdiction, such judgment shall
be confined in its operation to the part, provision, or application directly involved in all controversy in
which this judgment shall have been rendered, and shall not affect or impair the validity of the remainder
of this title or application thereof to other persons or circumstances. The City Council hereby declares
that it would have enacted the remainder of this ordinance even without such part, provision, or
application.
Section 3. Effective Date: That pursuant to KMC 1.15.070(f), this ordinance shall take effect
immediately upon enactment.
New Text Underlined; [DELETED TEXT BRACKETED]
Ordinance No. 3330-2022
Page 2 of 2
ENACTED BY THE COUNCIL OF THE CITY OF KENAI, ALASKA, THIS 4T" DAY OF JANUARY, 2023.
?1m '
es Baisden, Vice Mayor
ATTEST:
Miche e . ane , City Clerk
Approved by Finance:
Introduced: December 21, 2022
Enacted: January 4, 2023
Effective: January 4, 2023
New Text Underlined; [DELETED TEXT BRACKETED]
•
K. Im N A I
City of Kenai 1 210 Ficlalgo Ave, Kenai, AK 99611-7794 1 907.283.7535 1 www.kenai.city
MEMORANDUM
TO:
Mayor Gabriel and Council Members
THROUGH:
Paul Ostrander, City Manager
FROM:
Scott Curtin, Public Works Director
DATE:
December 14, 2022
SUBJECT:
Ordinance 3330-2022 — Kenai Recreation Center Improvements
The Public Works Department with K+A Architecture have now completed bid ready construction
documents for this project. We are preparing to release the project for bidding next month. This
Ordinance is intended to appropriate additional funding to cover the cost estimate provided by the
design team.
As the project design has proceeded, numerous issues were identified in need of correction.
Items that were within the specific project area, touching items associated with the primary goals
of roof replacement and mechanical system improvements, were added to the project scope.
Others have been avoided, to be addressed in future projects.
The additional $210,000 being requested with this Ordinance is largely to address significant
issues with a lack of roof drains which has contributed to the roof leaks common over the last few
years. Numerous new drains have been added within the design and extend to a new storm drain
field within the existing parking area. Additionally on the mechanical side six roof top units (RTUs)
and five exhaust fans are included with the design for replacement, along with a complete new
roof system for the facility.
These repairs represent a substantial investment in this facility. I want to be clear to Council that
this work is necessary to protect the facility, however the expenses are adding up. Council should
understand that completion of this project and an estimated $1,000,000 of additional future needs
at the facility will total approximately $2,500,000.
I will be available at the meeting to discuss, thank you for your consideration of this Ordinance.