HomeMy WebLinkAbout1968-07-10 Council Minutes - Special MeetingF—. T KENAI CITY COUNCIL_ MINUTES - SPECIAL MEETING 10 JULY, 1968 Called for the purpose of reviewing the revised Hudgat for Project 00271 and for Paving. Roll call: Members present - Chas. A. Bailie, Robert Bielefeld, Chester Cone, Billy McCann and Mayor Eugene H. Mnrin. Also prevent: City Manager James W. I arrison; Accountant reorle R. Brown; DPW Director Nets 0. K.ielstad and Project Engineer Harold 11, r,,,lliptt, Jr. Oalliett presented material on the Water, Sewer, Streets and Paving Projprts say.. inq we had done well in holding to the budget: that we had not exro"ded it in construction costs. The Water, sewer and associated streets Project (EDA 00271) was discussed first: Change orders, approved by EDA, 1 to 15 were briefly reviewed; change orders, to be approved, 16 to 24, have been accomplished; change orders 25 to 28, anticipated change orders,were discussed. Streets is the only project to have an over -run in the amount of $2,000.00. Contingency allowances on the over- all projects will take care of this over -run. The revised budget will allow an increase in engineering fees (necessary because of the hours spent on change orders), a decraase in Administrative and Legal costs, deletion of financing costs and an increase V interest costs. The total costs remains the same. Of the Total $60,000.00 allowed for equipment, $30,000 has already been spent for the Cat Grader. Discussion on need for equipment revealed the City needs: water testing equipment; sweeping equipment for the streets; valve and pipe finders; lear,•'cle- tectors; trucks and graders. The CIty has about 7,000 ft. of paved streets. If sub -divisions Kira in- cluded, there are about 10 miles of paved streets. Construction on all projects should be over in about one month; the assess- ment rolls should be done by the end of the month. This will allow the City to get notices mailed out and money coming in to meet the interest payment on the bonds which amounts to about $75,000.00 a .year. It, is hoped there will be money left over to accomplish some of the improv- ments that are badly needed; i.e. water, sewer and streets in some of the resident- ial districts. The original contract on paving was reviewed with change orders already done; Har- rison reviewed in detail the change orders Nos. 3 and 4 - totalling $5,863.34 which have already been accomplished. Change orders 5,6 and 7 are suqqested, and were discussed. The paving to tie in Marine and Main Streets with the Spur Hwy. were adjudged to be necessary; Paving on Willow would be torn up later on, so was dis- carded. McCann moved, Bailie seconded, to approve change orders on paving Nos. 3,4,5 and authorize the periodic pay estimate No. 2 in the amount of $31,393.21. Motion carried -unanimously by roll call vote. Cone moved, Bailie seconded, to instruct the engineer to prepare Change Order No. 6. Main St. Paving, and to approve this change order. Motion carried unanimously by roll call vote. ($3,000.00 approx.) Bielefeld moved. McCann seconded, to accept the budget review as presented by the Engineer on water, sewer, associated streets and paving. Motion passed unani- mously by roll call vote. Harrison, with consent of Council,will block. off Overland between Bookey's Drive - In and the Drug Store for a street dance for Kenai Days. Meeting adjourned at 9:30 p.m. Respectfull uhmitted, Frances rki lsen, i ty C e r'001� 1y eI ................ _ _ . . ... .. ......... -- ,�. ou 2.0,0° 0