HomeMy WebLinkAboutResolution No. 2023-31KENAI CITY OF KENAI RESOLUTION NO. 2023-31 Sponsored by: Administration A RESOLUTION AUTHORIZING A REALLOCATION OF FUNDS WITHIN THE MUNICIPAL ROADWAY IMPROVEMENTS CAPITAL PROJECT FUND. WHEREAS, Nelson Engineering is nearing design completion on the North Willow Street Roadway Improvements, First Avenue Roadway Repairs, and Miscellaneous Road Repairs Capital Projects; and, WHEREAS, with completion of these documents and a more refined understanding of the project requirements, it has been determined supplemental funding may be needed to allow these projects to be bid and completed; and, WHEREAS, the Lilac Street Reconstruction project, having yet to begin design, will reprioritize funding to the higher priority projects listed above; and, WHEREAS, the new fiscal year 2024 budget presented to Council as well as the newly approved Capital Improvement Plan, includes $100,000 in new funding to allow the Lilac Street Reconstruction project to begin design work later this summer, slightly shifting the projects timeline for completion. NOW, THEREFORE, BE IT RESOLVED BY THE COUNCIL OF THE CITY OF KENAI, ALASKA: Section 1. That the City Manager is authorized to reallocate the existing capital projects funds as detailed below: Municipal Roadway Improvements Capital Project Fund Decrease Expenditures: Lilac Street Reconstruction - Construction $222= Increase Expenditures: N. Willow Street Roadway Improvements - Construction $160,000 First Avenue Roadway Repairs - Construction 100,000 Miscellaneous Road Repairs - Construction 133.000 $ 93 0 Section 2. That this Resolution takes effect immediately upon passage. PASSED BY THE COUNCIL OF THE CITY OF KENAI, ALASKA, THIS 3RD DAY OF MAY, 2023. Brian Gabriel Sr., Mayor T: Michelle Saner , C, City Clerk Approved by Finance: New Text Underlined; [DELETED TEXT BRACKETED] City of Kenai 1210 Fidalgo Ave, Kenai, AK 99611-7794 1907.283.75351 www.kenaixity MEMORANDUM TO: Mayor Gabriel and Council Members THROUGH: Terry Eubank, City Manager FROM: Scott Curtin, Public Works Director DATE: April 25, 2023 SUBJECT: Resolution 2023-31 — Municipal Roadway Improvements The purpose of this memo is to request Council's approval to reallocate funding within the Municipal Roadway Improvements Capital Project Fund to allow several projects to bid and ultimately be completed this year. The Public Works Department is requesting to reallocate previously appropriated funds from the Lilac Street Reconstruction project and supplement the funding for the North Willow Street Roadway Improvements, First Avenue Roadway Repairs, and Miscellaneous Road Repairs Capital Projects. Nelson Engineering has been developing the construction documents for these projects and they are nearing completion. The North Willow project extends from the intersection with Granite Pointe St. to just beyond the Forestry Service lot adjacent to Airport Operations. The First Avenue project repairs are taking place between the intersections of North Spruce and Birch St. The Miscellaneous Road Repairs project sites include the intersections of Haller and Fourth Avenue, Watergate and Pirate Lane, Watergate and Schooner Circle, Watergate and Set Net Drive, VIP Drive and Set Net Drive, VIP Drive and Dollar Drive, Eagle Rock Drive and Tern Place, Eagle Rock Drive and Sandpiper Lane, and Silver Salmon and King Salmon Drive. The Lilac Street project will continue to move forward with new funding being provided with the adoption of the FY2024 budget, which will provide $100,000 to allow design and survey efforts to begin later this summer. The existing funding within the project will be reallocated with $160,000 towards the North Willow St. project, $100,000 towards First Avenue, and $133,000 toward the Miscellaneous Repairs. Completion of these projects is in the best interest of the City. Council's support is respectfully requested.