HomeMy WebLinkAbout2024-01-17 Council Packet - Joint Work Session, Capital Improvement PlanKenai City Council - Joint Work Session Page 1 of 1
January 17, 2024
Kenai City Council - Joint Work Session
FY2025-2029 Capital Improvement Plan
January 17, 2024 ꟷ 4:30 PM
Kenai City Council Chambers
210 Fidalgo Avenue, Kenai, Alaska
**Telephonic/Virtual Information Below**
www.kenai.city
Agenda
A. CALL TO ORDER
B. INTRODUCTION - City Manager Eubank
C. DISCUSSION ITEM
1. Fiscal Year 2025 - 2029 Capital Improvement Plan
D. PUBLIC COMMENTS (limited to 3 minutes per individual)
E. ADJOURNMENT
Join Zoom Meeting OR
https://us02web.zoom.us/j/89109732128 Dial In: (253) 215-8782 or (301) 715-8592
Meeting ID: 891 0973 2128 Passcode: 785524 Meeting ID: 891 0973 2128 Passcode: 785524
Page 1
Draft
FISCAL YEARS 2025 – 2029
CITY OF KENAI TERRY EUBANK SCOTT CURTIN
CITY HALL CITY MANAGER PUBLIC WORKS DIRECTOR
210 FIDALGO AVENUE TEUBANK@KENAI.CITY SCURTIN@KENAI.CITY
KENAI, AK 99611 907-283-8222 907-283-8236
Page 2
Draft
TABLE OF CONTENTS
Page 3
INTRODUCTION
Page 5
AIRPORT FUND
Page 13
GENERAL FUND
Page 35
WATER & SEWER FUND
Page 55
SENIOR CITIZENS FUND
Page 59
CONGREGATE HOUSING FUND
Page 63
PERSONAL USE FISHERY FUND
Page 3
Draft
INTRODUCTION
The City of Kenai's five-year Capital Improvement Plan (CIP) is developed by the
Public Works Department in coordination with other City departments,
Administration, Boards and Commissions, and the City Council for the purpose of
long-range capital improvement planning and budgeting. A capital improvement
project is typically a one-time expenditure, usually, in excess of $35,000, that has a
useful life exceeding one year or is a major project such as a comprehensive or
master plan. Capital projects on existing assets are included in the CIP, provided
they meet the definition of a capital project. Projects can focus on immediate needs
or anticipate future needs before critical failures and are developed based on an
internal process that determines funding availability and infrastructure needs.
The CIP is divided into six parts based on the City Fund from which the project
would be funded. These include the Airport Fund, General Fund, Water & Sewer
Fund, Senior Citizens Fund, Congregate Housing Enterprise Fund, and Personal Use
Fishery Fund. Projects are not necessarily listed in priority order for each Fund by
fiscal year. Active projects that have been funded in prior years are not included in
the Plan.
Projects that are identified in the CIP are included for planning purposes and to
recognize a need. Not all projects receive the necessary funding to accomplish
them in a projected year, which is why the list is updated annually. Many projects
are dependent on non-City funding sources, which the City can expect to seek, but
are not guaranteed to receive. The availability of outside funds can vary with local,
state, and federal economies, and the City's needs can, and do, change frequently.
Page 4
Draft
Blank
Page 5
Airport Fund
FY2025
No
Project Name
Total Project Cost
Grant
Funding
City Funding
1* Rehabilitate Runway 2L / 20R – Construction $24,913,286 $23,356,206 $424,194*
2 Perimeter Fence Line Improvements $3,960,000 $3,712,500 $247,500
3 Airport Master Plan - Phase 2 $1,000,000 $62,500 $937,500
4 Acquire ARFF Vehicle $1,000,000 $937,500 $62,500
Totals
$30,873,286
$28,068,706
$1,671,694
FY2026
No
Project Name
Total Project Cost
Grant
Funding
City Funding
5* Rehab. TW A/B/C/D/E/K/L/M - Construction $14,479,600 $13,574,625 $578,661*
6 Terminal Road & Parking Lot Improvements $1,750,000 $1,640,625 $109,375
Totals
$16,229,600
$15,215,250
$688,036
FY2027
No
Project Name
Total Project Cost
Grant
Funding
City Funding
7
Float Basin TW Sierra w/Access Control &
Lighting
$3,100,000
$2,906,250
$193,750
8
EA/Design/Construct Apron & Willow St
Extension
$2,203,125
$2,203,125
$146,875
Totals
$5,403,125
$5,109,375
$340,625
FY2028
No
Project Name
Total Project Cost
Grant
Funding
City Funding
9 EA/Design - ARFF Building Roof Replacement $100,000 $93,750 $6,250
Totals
$100,000
$93,750
$6,250
Page 6
FY2029
No
Project Name
Total Project Cost
Grant
Funding
City Funding
10 Construct - ARFF Building Roof Replacement $900,000 $843,750 $56,250
Totals
$900,000
$843,750
$56,250
Total Project Cost
Grant
Funding
City Funding
Airport FY2025-2029 Grand Totals
$53,506,011
$49,330,831
$2,762,855
** PROJECTS WITH ASTERISK HAVE HAD ADDITIONAL CITY FUNDING PROVIDED IN PREVIOUS FISCAL
YEAR(S). CITY FUNDING INDICATED IS SPECIFIC TO FISCAL YEAR AND MAY NOT INCLUDE ALL CITY
FUNDING TO DATE
Page 7
AIRPORT FUND PROJECTS
RUNWAY 2L/20R REHABILITATION -
CONSTRUCTION
Department: Airport
Total Project Cost: $23,780,400
Project Phased: Yes
Project Type: Infrastructure
Funding Source(s): Grant Dependent
Potential Grant Identified: Federal Aviation
Administration
Operating Budget Impact: Slight Decrease
YEAR: 2025 2026 2027 2028 2029
COST: $24,913,286
Details: This project will rehabilitate Kenai Municipal Airport’s primary Runway 2L/20R to current
standards. The work will involve milling of the existing runway surface and placement of new
asphalt surfaces along the 7,855 lineal feet in length by 150 lineal feet in width runway. HDR
Engineering continues to develop design documents anticipated to be completed late in 2024.
The project has been moving up through our program with the Federal Aviation Administration
and we anticipate grant funds to become available in mid calendar year 2025 to complete the
construction phase. The City has forward funded the design effort to date.
PERIMETER FENCE LINE IMPROVEMENTS
Department: Airport
Total Project Cost: $3,960,000
Project Phased: No
Project Type: Building Improvement
Funding Source(s): Grant Dependent
Potential Grant Identified: Federal Aviation Admin
Operating Budget Impact: Minimal or No Impact
YEAR: 2025 2026 2027 2028 2029
COST: $3,960,000
Details: This project will remove and replace existing chain link fencing around the airport’s
perimeter to prevent wildlife from accessing the airfield. Assessment of current conditions and
design documents will be completed in 2024 in advance of the 2025 grant application season.
Page 8
AIRPORT FUND PROJECTS
AIRPORT MASTER PLAN – PHASE 2
Department: Airport
Total Project Cost: $1,000,000
Project Phased: Yes
Project Type: Planning
Funding Source(s): Airport Fund
Potential Grant Identified: Federal Aviation Admin.
Operating Budget Impact: Minimal or No Impact
YEAR: 2025 2026 2027 2028 2029
COST: $1,000,000
Details: Airport Master Plans are typically updated every 5-7 years, with ENA’s current Master
Plan finalized in 2017. This document is a requirement from the Federal Aviation Administration
(FAA) to support the continued growth and operation of the Airport. It is a planning document
that assists the City and FAA with project development. Phase 1 work is taking place throughout
2024, Phase 2 will complete the project.
ACQUIRE ARFF VEHICLE
Department: Airport
Total Project Cost: $1,000,000
Project Phased: No
Project Type: Equipment
Funding Source(s): Grant Dependent
Potential Grant Identified: Federal Aviation Admin
Operating Budget Impact: Minimal or No Impact
YEAR: 2025 2026 2027 2028 2029
COST: $1,000,000
Details: This project will replace an existing 1992 model year Oshkosh TA1500 unit to allow for
continued efficient airfield operations and safety standards. The unit will be purchased through
the State of Alaska AIP Fleet purchasing contract.
Page 9
AIRPORT FUND PROJECTS
REHAB TW A/B/C/D/E/K/L/M -
CONSTRUCTION
Department: Airport
Total Project Cost: $14,479,600
Project Phased: Yes
Project Type: Infrastructure
Funding Source(s): Grant Dependent
Potential Grant Identified: Federal Aviation Admin
Operating Budget Impact: Slight Decrease
YEAR: 2025 2026 2027 2028 2029
COST: $14,479,600
Details: This project will rehabilitate runway taxiways A, B, C, D, E, K, L, M to current standards.
The work will involve milling of the existing taxiways and placement of new asphalt surfaces,
markings, and lighting. HDR Engineering continues to develop design documents in coordination
with the Runway Rehab work. These documents will be completed in advance of the 2026 grant
season as coordinated with the Federal Aviation Administration. The City has forward funded
the design effort to date.
TERMINAL ROAD AND PARKING LOT IMPROVEMENTS
Department: Airport
Total Project Cost: $1,750,000
Project Phased: No
Project Type: Infrastructure
Funding Source(s): Grant Dependent
Potential Grant Identified: Federal Aviation
Admin
Operating Budget Impact: Slight Increase
YEAR: 2025 2026 2027 2028 2029
COST: $1,750,000
Details: This project will rehabilitate the primary airport terminal access road and provide for
parking lot expansion to the south. Parking lot lighting will be included with this work within the
affected areas.
Page 10
AIRPORT FUND PROJECTS
FLOAT BASIN TW SIERRA W/ACCESS
CONTROL & LIGHTING
Department: Airport
Total Project Cost: $3,100,000
Project Phased: No
Project Type: Technology
Funding Source(s): Grant Dependent
Potential Grant Identified: Federal Aviation
Administration
Operating Budget Impact: Slight Increase
YEAR: 2025 2026 2027 2028 2029
COST: $3,100,000
Details: The development of the Kenai Municipal Airport (ENA) Seaplane Base (SPB) is critical to
the growth of the airport. The SPB is fundamental to de-conflicting General Aviation (GA)
operations and Commercial Aircraft Operations, it allows for the continued growth of GA to the
west and frees up prime commercial aviation property on the east side of the airport and South
Airpark. The project will establish the foundation for the continued growth of the SPB by
appropriately connecting the SPB to the main runway, and making several plots available for
hangar, tie-down, and other GA services development.
EA / DESIGN / CONSTRUCTION APRON
& WILLOW ST. EXTENSION
Department: Airport
Total Project Cost: $2,350,000
Project Phased: No
Project Type: Land Improvement / Infrastruct.
Funding Source(s): Grant Dependent
Potential Grant Identified: Federal Aviation
Administration
Operating Budget Impact: Slight Increase
YEAR: 2025 2026 2027 2028 2029
COST: $2,350,000
Details: This project would extend the apron taxiway 600 feet for lease lots and N. Willow St.
extension (road and utilities) as well as provide for lease lot development (five acres).
Page 11
AIRPORT FUND PROJECTS
EA / DESIGN / CONSTRUCTION ARFF BUILDING ROOF REPLACEMENT
Department: Airport
Total Project Cost: $1,000,000
Project Phased: No
Project Type: Building Improvement
Funding Source(s): Grant Dependent
Potential Grant Identified: Federal Aviation
Administration
Operating Budget Impact: None
YEAR: 2025 2026 2027 2028 2029
COST: $100,000 $900,000
Details: The Kenai Municipal Airport’s Aircraft Rescue Fire Fighting Operations Facility located at
515 N. Willow St. finished construction in 2001. The facility’s EPDM roof system encompassing
approximately 19,637 square feet will be reaching the end of its intended useful life. This project
will provide design documents for a complete roof replacement. Design documents will be
prepared in FY2028 with construction scheduled to take place in FY2029.
Page 12
General Fund
FY2025
No
Project Name
Total Project Cost
Grant
Funding
City Funding
Wildwood Drive Rehabilitation-Construction $1,000,000 $800,000 $0*
Lilac Street Rehabilitation – Construction $700,000 $700,000
Public Main walk Replacements & ADA
Warning - Design
$40,000
$40,000
Youth Corridor Pedestrian & Roadway
Improvements – 35% Design Development
$160,000
$160,000
Emergency Services Facility Improvement –
35% Design Development $225,000 $225,000
Old Town Park Reconstruction $1,635,000 $981,000 $654,000
Street Lighting Improvements - Construction $400,000 $400,000
Tractor Replacement $80,000 $80,000
Parks & Recreation Master Plan $70,000 $70,000
Totals
$4,310,000
$1,941,000
$2,169,000
FY2026
No
Project Name
Total Project Cost
Grant
Funding
City Funding
Aliak Stormwater and Paving Repair –
Construction $420,000 $400,000 $20,000
Public Main walk Replacements & ADA
Warning - Construction $560,000 $480,000 $80,000
Flight Services RTU Replacements $350,000 $350,000
Beaver Creek Replace Pavilion $50,000 $50,000
Tractor Replacement $70,000 $70,000
City Hall Improvements – Construction $800,000 $640,000 $160,000
Totals
$2,250,000
$1,520,000
$730,000
FY2027
No
Project Name
Total Project Cost
Grant
Funding
City Funding
Future Stormwater Improvements $240,000 $200,000 $40,000
Gravel Roadway Improvements – Design $200,000 $200,000
Asphalt Roadway Improvements – Design $200,000 $200,000
Totals
$640,000
$200,000
$440,000
Page 13
FY2028
No
Project Name
Total Project Cost
Grant
Funding
City Funding
Gravel Roadway Improvements –
Construction $1,000,000 $800,000 $200,000
Asphalt Roadway Improvements –
Construction $1,000,000 $800,000 $200,000
Florida Avenue Roadway Development –
Design $120,000 $120,000
Relocation of Parks & Rec to Daubenspeck –
Design $150,000 $150,000
Multipurpose Facility Roof – Design $75,000 $75,000
Totals
$2,345,000
$1,600,000
$745,000
FY2029
No
Project Name
Total Project Cost
Grant
Funding
City Funding
Relocation of Parks & Rec to Daubenspeck –
Construction $3,000,000 $2,400,000 $600,000
Multipurpose Facility Roof – Construction $850,000 $680,000 $170,000
Florida Avenue Roadway Development –
Construction $700,000 $700,000
Totals
$4,550,000
$3,080,000
$1,470,000
Total Project Cost
Grant
Funding
City Funding
General Fund FY2025-2029 Grand Totals
$14,095,000
$8,341,000
$5,554,000
** PROJECTS WITH ASTERISK HAVE HAD ADDITIONAL CITY FUNDING PROVIDED IN PREVIOUS FISCAL
YEAR(S). CITY FUNDING INDICATED IS SPECIFIC TO FISCAL YEAR AND MAY NOT INCLUDE ALL CITY
FUNDING TO DATE
Page 14
GENERAL FUND PROJECTS
WILDWOOD DRIVE REHABILITATION -
CONSTRUCTION
Department: Public Works
Total Project Cost: $1,000,000
Project Phased: No.
Project Type: Infrastructure
Funding Source(s): General Fund / Grant
Potential Grant Identified: State of Alaska
Operating Budget Impact: Moderate Decrease
YEAR: 2025 2026 2027 2028 2029
COST: $1,000,000*
Details: This project will rehabilitate Wildwood Dr. from the Kenai Spur Highway to the
entrance of the Wildwood Correctional Facility, approximately 2300lf. The roadway has
severely deteriorated over its 50+ year life. The State of Alaska Department of Corrections is
the primary user of the roadway with 85% of all traffic accessing the facility. The project has
been delayed for years due to ownership concerns of the right of way with the Kenai Native
Association, and lack of available grant funds from the State.
LILAC STREET REHABILITATION –
CONSTRUCTION
Department: Public Works
Total Project Cost: $700,000
Project Phased: No
Project Type: Infrastructure
Funding Source(s): General Fund
Potential Grant Identified: State Capital Project
Submission and Federal Grants to Be Identified
Operating Budget Impact: Moderate Increase
YEAR: 2025 2026 2027 2028 2029
COST: $700,000 Details: This project replaces the failed concrete curb in affected areas, re-stabilizes settled
subbase areas, and provides a new asphalt surface course along approximately 1600 linear feet
of 30-foot wide roadway. Lilac Lane is located off the Spur Highway and Cook Inlet View Drive
on the north side of Kenai. The roadway and concrete curb and gutter are suffering from the
severe settlement in multiple areas.
Page 15
GENERAL FUND PROJECTS
PUBLIC MAIN WALK REPLACEMENTS & ADA WARNING PADS -
DESIGN
Department: Public Works
Total Project Cost: $40,000
Project Phased: Yes
Project Type: Infrastructure
Funding Source(s): General Fund
Potential Grant Identified: State Capital Project
Submission and Federal Grants to Be Identified
Operating Budget Impact: None
YEAR: 2025 2026 2027 2028 2029
COST: $40,000 Details: This project will begin to address the numerous cracked public main walks in various
locations around the City. Intersections will receive ADA-stamped indicator pads in yellow.
YOUTH CORRIDOR PEDESTRIAN AND ROADWAY IMPROVEMENTS
35% DESIGN DOCUMENTS
Department: Public Works
Total Project Cost: $160,000
Project Phased: Yes
Project Type: Infrastructure
Funding Source(s): Grant Dependent | Bonding
Potential Grant Identified: State Capital Project
Submission and Federal Grants to Be Identified
Operating Budget Impact: Slight Increase
YEAR: 2025 2026 2027 2028 2029
COST: $160,000 Details: This project seeks to improve safety, visibility & security to families accessing the Kenai
Middle School, High School, Challenger Center and Ice Rink. Project extends from the Spur
Highway down Tinker Ln. to Lawton Dr. turning west to Walker Ln. Sidewalks, bike lane,
Roadway and Street Lighting Improvements are all proposed with the project. This is a
significant project that would affect approximately 7000lf of roadway throughout our densely
populated school zone.
Page 16
GENERAL FUND PROJECTS
EMERGENCY SERVICES FACILITY ASSESSMENT / IMPROVEMENT
35% DESIGN DOCUMENTS
Department: Police Department/Fire Department
Total Project Cost: $225,000
Project Phased: Yes
Project Type: Facility Improvement
Funding Source(s): Grant / General Fund
Operating Budget Impact: None
YEAR: 2025 2026 2027 2028 2029
COST: $225,000 Details: This project will evaluate the needs of the emergency services departments and assess
the existing conditions of their current facility to determine whether renovations to the 50+
year old facility or new construction is the most appropriate course of action. The existing
building is known to have asbestos which has limited opportunities for smaller renovations.
This preliminary set of design documents will be used to seek grant opportunities.
OLD TOWN PLAYGROUND RECONSTRUCTION
Department: Parks and Recreation
Total Project Cost: $1,635,000
Project Phased: No
Project Type: Equipment
Funding Source(s): Grant Dependent | Bonding
Potential Grant Identified: State Capital Project
Submission and Federal Grants to Be Identified
Operating Budget Impact: Minimal to No Impact
YEAR: 2025 2026 2027 2028 2029
COST: $1,635,000 Details: This project will replace aging equipment at the Park on Peninsula Ave adjacent to the
Fine Arts Center. The area of Old Town attracts numerous visitors every year. The park is located
two blocks from the Visitor’s Center and is in close proximity to several large housing complexes
providing plenty of children to utilize the park. The project design was completed in the fall of
2023 in coordination with the Kenaitze Indian Tribe and Salamatof Native Association who are
assisting with grant applications.
Page 17
GENERAL FUND PROJECTS
STREET LIGHTING IMPROVEMENTS - CONSTRUCTION
Department: Public Works
Total Project Cost: $400,000
Project Phased: Yes
Project Type: Infrastructure
Funding Source(s): General Fund
Potential Grant Identified: DOT Grant
Operating Budget Impact: Slight Decrease
YEAR: 2025 2026 2027 2028 2029
COST: $400,000 Details: This project will identify underserved and problem locations for street lighting to
improve safety and security for citizens. New lighting will be LED to reduce energy and
maintenance costs. This first project will provide for the design and identification of locations
to be served.
TRACTOR REPLACEMENT
Department: Parks & Recreation
Total Project Cost: $80,000
Project Phased: No
Project Type: Equipment
Funding Source(s): General Fund
Potential Grant Identified: None
Operating Budget Impact: Minimal
YEAR: 2025 2026 2027 2028 2029
COST: $80,000
Details: This project will replace aging existing equipment with new. Tractor and various
attachments including a wide area mower deck and snow removal components are anticipated.
Equipment is planned for year-round use.
Page 18
GENERAL FUND PROJECTS
PARKS & RECREATION MASTER PLAN
Department: Parks & Recreation
Total Project Cost: $70,000
Project Phased: No
Project Type: Park Improvement
Funding Source(s): Grant Dependent | Bonding
Potential Grant Identified: State Capital Project
Submission and Federal Grants to Be Identified
Operating Budget Impact: Slight Increase
YEAR: 2025 2026 2027 2028 2029
COST: $70,000
Details: This project will seek professional services to assist with the development of a Parks
and Recreation Master Plan. All existing park facilities will be evaluated. The Master Plan
document will be used to direct future funding toward the most desired and appropriate uses
first.
ALIAK STORM WATER & PAVING REPAIR –
CONSTRUCTION
Department: Public Works
Total Project Cost: $420,000
Project Phased: Yes
Project Type: Infrastructure
Funding Source(s): State Grant / General Fund
Potential Grant Identified: None
Operating Budget Impact: Slight Decrease
YEAR: 2025 2026 2027 2028 2029
COST: $420,000 Details: This project will begin to address a failed stormwater line on Aliak Dr. between
Candlelight Dr. and Highbush Ln. The galvanized piping has collapsed in several locations which
cause the occasional sinkhole to surface after significant runoff. The photo above is from April
2021 shortly after the breakup. The staff has been filling these in with gravel and then patching
the asphalt as a short-term solution. This project will require the removal of sections of the
roadway and the replacement of existing stormwater piping with new and then resurfacing of
the roadway.
Page 19
GENERAL FUND PROJECTS
PUBLIC MAIN WALK REPLACEMENTS & ADA WARNING PADS -
CONSTRUCTION
Department: Public Works
Total Project Cost: $560,000
Project Phased: Yes
Project Type: Infrastructure
Funding Source(s): Grant Dependent | Bonding
Potential Grant Identified: State Capital Project
Submission and Federal Grants to Be Identified
Operating Budget Impact: Slight Increase
YEAR: 2025 2026 2027 2028 2029
COST: $560,000 Details: This project will begin to address the numerous cracked public main walks in various
locations around the City. Intersections will receive ADA stamped indicator pads in yellow.
Priority will be placed on higher traffic areas including school routes on Forest Ave and Frontage
Rd.
FLIGHT SERVICES RTU REPLACEMENTS
Department: Public Works
Total Project Cost: $350,000
Project Phased: No
Project Type: Building Improvement
Funding Source(s): General Fund
Potential Grant Identified: None
Operating Budget Impact: Moderate Increase
YEAR: 2025 2026 2027 2028 2029
COST: $350,000 Details: This is a planned replacement project for air handling units reaching the end of their
useful life. This work will provide for the efficient and reliable function of HVAC systems at the
facility currently being leased by the Federal Aviation Administration (FAA). This was a planned
replacement for 2025, however units remain in service at this time.
Page 20
GENERAL FUND PROJECTS
BEAVER CREEK PARK REPLACEMENT PAVILION
Department: Parks and Recreation
Total Project Cost: $50,000
Project Phased: No
Project Type: Building
Funding Source(s): General Fund
Potential Grant Identified: None
Operating Budget Impact: Slight Increase
YEAR: 2025 2026 2027 2028 2029
COST: $50,000 Details: Construct a new pavilion at Beaver Creek Park located just off the Spur Highway on
Parkside Dr. This will be a wood frame structure consistent with other similar structures within
the City.
TRACTOR REPLACEMENT
Department: Parks & Recreation
Total Project Cost: $80,000
Project Phased: No
Project Type: Equipment
Funding Source(s): General Fund
Potential Grant Identified: None
Operating Budget Impact: Minimal
YEAR: 2025 2026 2027 2028 2029
COST: $70,000
Details: This project will replace aging existing equipment with new. Tractor and various
attachments including a wide area mower deck and snow removal components are anticipated.
Equipment is planned for year-round use.
Page 21
GENERAL FUND PROJECTS
CITY HALL IMPROVEMENTS -
CONSTRUCTION
Department: Public Works
Total Project Cost: $800,000
Project Phased: No
Project Type: Building Improvement
Funding Source(s): Grant / General Fund
Potential Grant Identified: State Capital Project
Submission and Federal Grants to be Identified
Operating Budget Impact: Slight Decrease
YEAR: 2025 2026 2027 2028 2029
COST: $800,000 Details: This project will replace the 40+ year old exterior doors, windows, exterior siding and
mechanical ventilation systems. The facility has struggled with drafts and air quality issues for
some time. Project is expected to reduce facility heating costs.
FUTURE STORMWATER IMPROVEMENTS
Department: Public Works
Total Project Cost: $240,000
Project Phased: Yes
Project Type: Infrastructure
Funding Source(s): Grant / General Fund
Potential Grant Identified: None
Operating Budget Impact: Slight Increase
YEAR: 2025 2026 2027 2028 2029
COST: $240,000 Details: This project will allow Public Works to continue to address stormwater runoff, culvert,
and catch basin issues as they continue to deteriorate throughout the City.
Page 22
GENERAL FUND PROJECTS
GRAVEL ROADWAY IMPROVEMENTS – DESIGN
Department: Public Works
Total Project Cost: $200,000
Project Phased: No
Project Type: Infrastructure / Roadway Improvement
Funding Source(s): General Fund
Potential Grant Identified: None
Operating Budget Impact: Slight Decrease
YEAR: 2025 2026 2027 2028 2029
COST: $200,000 Details: This project will develop bid ready construction documents to improve several existing
gravel roadways within the City. Work will consist of ditching and drainage improvements,
removal of soft spots, and capping of roadway with new gravel lift. The primary roadway of
current concern is Phillips Ave. which experiences severe drainage issues each spring.
ASPHALT ROADWAY IMPROVEMENTS - DESIGN
Department: Public Works
Total Project Cost: $200,000
Project Phased: No
Project Type: Infrastructure / Roadway Improvement
Funding Source(s): General Fund
Potential Grant Identified: None
Operating Budget Impact: Slight Decrease
YEAR: 2025 2026 2027 2028 2029
COST: $200,000 Details: This project will provide bid ready construction documents to continue with the City’s
pavement replacement plan. A Roadway Improvement Survey was completed in 2009, this
document along with ongoing site assessments is directing maintenance work. Specific project
to be further identified as project draws closer.
Page 23
GENERAL FUND PROJECTS
GRAVEL ROADWAY IMPROVEMENTS – CONSTRUCTION
Department: Public Works
Total Project Cost: $200,000
Project Phased: No
Project Type: Infrastructure / Roadway Improvement
Funding Source(s): Grant / General Fund
Potential Grant Identified: None
Operating Budget Impact: Slight Decrease
YEAR: 2025 2026 2027 2028 2029
COST: $1,000,000 Details: This project will improve several existing gravel roadways within the City. Work will
consist of ditching and drainage improvements, removal of soft spots, and capping of roadway
with new gravel lift. The primary roadway of current concern is Phillips Ave. which experiences
severe drainage issues each spring.
ASPHALT ROADWAY IMPROVEMENTS - CONSTRUCTION
Department: Public Works
Total Project Cost: $1,000,000
Project Phased: No
Project Type: Infrastructure / Roadway Improvement
Funding Source(s): Grant / General Fund
Potential Grant Identified: None
Operating Budget Impact: Slight Decrease
YEAR: 2025 2026 2027 2028 2029
COST: $1,000,000 Details: This project will continue with the City’s pavement replacement plan. A Roadway
Improvement Survey was completed in 2009, this document along with ongoing site
assessments is directing maintenance work. Specific project to be further identified as project
draws closer.
Page 24
GENERAL FUND PROJECTS
FLORIDA AVENUE ROADWAY DEVELOPMENT - DESIGN
Department: Public Works
Total Project Cost: $120,000
Project Phased: No
Project Type: Infrastructure / Roadway Improvement
Funding Source(s): General
Potential Grant Identified: None
Operating Budget Impact: Slight Increase
YEAR: 2025 2026 2027 2028 2029
COST: $120,000 Details: This is a joint project with the Water & Sewer Utility to extend a 12” water main down
Florida Avenue from Fifth Street to First Street. This area of town dates to old military base
days, and the existing water mains serving homes on First and Second Streets is only 4” in size.
The new 12” main will divide the neighborhood so fewer homes are being served from the 4”
line. As this work will destroy the roadway, roadway improvements will be included with
reinstallation of concrete curb and gutter and asphalt roadway surfacing. The Water & Sewer
Fund is providing funding for the water line work including design, general fund is only covering
costs for roadway improvements.
RELOCATION OF PARKS & REC TO DAUBENSPECK – DESIGN
Department: Parks and Recreation
Total Project Cost: $150,000
Project Phased: Yes
Project Type: Building
Funding Source(s): General
Potential Grant Identified: None
Operating Budget Impact: Moderate Increase
YEAR: 2025 2026 2027 2028 2029
COST: $150,000 Details: This project will relocate Park & Rec facilities from their current location at 332 Airport
Way over to 550 Daubenspeck where the Streets, Shop, and Building Maintenance division
currently reside. A new building including garage and office space shall be provided.
Page 25
GENERAL FUND PROJECTS
MULTIPURPOSE FACILITY ROOF - DESIGN
Department: Public Works
Total Project Cost: $75,000
Project Phased: No
Project Type: Building Maintenance
Funding Source(s): General
Potential Grant Identified: None
Operating Budget Impact: None
YEAR: 2025 2026 2027 2028 2029
COST: $75,000 Details: The Multipurpose facility was constructed in 1999. The ice rink facility has had a fair
amount of condensation issues over the years due to maintaining heat during hockey games.
This project is to acknowledge the roof will be 30 years old at this time and may be in need of
replacement.
RELOCATION OF PARKS & REC TO DAUBENSPECK
Department: Parks and Recreation
Total Project Cost: $3,000,000
Project Phased: Yes
Project Type: Department Relocate
Funding Source(s): Grant Dependent | Bonding
Potential Grant Identified: State Capital Project
Submission and Federal Grants to Be Identified
Operating Budget Impact: Moderate Increase
YEAR: 2025 2026 2027 2028 2029
COST: $3,000,000
Details: This project will relocate Park & Rec facilities from their current location at 332 Airport
Way over to 550 Daubenspeck where the Streets, Shop, and Building Maintenance division
currently reside. A new building including garage and office space shall be provided.
Page 26
GENERAL FUND PROJECTS
MULTIPURPOSE FACILITY ROOF -
CONSTRUCTION
Department: Public Works
Total Project Cost: $850,000
Project Phased: No
Project Type: Building Maintenance
Funding Source(s): Grant / General Fund
Potential Grant Identified: None
Operating Budget Impact: None
YEAR: 2025 2026 2027 2028 2029
COST: $850,000
Details: The Multipurpose facility was constructed in 1999. This ice rink facility has had a fair
amount of condensation issues over the years due to maintaining heat during hockey games.
This project is to acknowledge the roof will be 30 years old at this time and may be in need of
replacement.
FLORIDA AVENUE ROADWAY DEVELOPMENT - CONSTRUCTION
Department: Public Works
Total Project Cost: $700,000
Project Phased: No
Project Type: Infrastructure / Roadway & Utility
Funding Source(s): General Fund / Water Sewer Fund
Potential Grant Identified: None
Operating Budget Impact: Moderate Increase
YEAR: 2025 2026 2027 2028 2029
COST: $700,000
Details: This is a joint project with the Water & Sewer Utility to extend a 12” water main down
Florida Avenue from Fifth Street to First Street. This area of town dates to old military base
days, and the existing water mains serving homes on First and Second Streets is only 4” in size.
The new 12” main will divide the neighborhood so fewer homes are being served from the 4”
line. As this work will destroy the roadway, roadway improvements will be included with
reinstallation of concrete curb and gutter and asphalt roadway surfacing. The Water & Sewer
Fund is providing funding for the water line work including design, general fund is only covering
costs for roadway improvements.
Page 27
Water & Sewer Fund
FY2025
No
Project Name
Total Project Cost
Grant
Funding
City Funding
1
Operator Truck 1/2 Ton
(Split between Water &Sewer)
$65,000
$65,000
2
Operator Truck 3/4 Ton
(Split between Water &Sewer)
$80,000
$80,000
2 Lead Service Line Inventory Support Services $100,000 $58,000 $42,000
4 Lift Station Phase 1 Supplement $300,000 $300,000
5 Broad Street Lift Station Renovation –
Design
$220,000
$220,000
6
WWTP Operations Bldg. Replacement –
Design
$500,000
$400,000
$100,000
7 CCTV Equipment $100,000 $100,000
Totals
$1,365,000
$458,000
$907,000
FY2026
No
Project Name
Total Project Cost
Grant
Funding
City Funding
8
Airport Res Pump House Improvements –
Design
$180,000
$180,000
9 Disinfectant Generation Equipment – Design $100,000 $100,000
10 GIS Mapping Improvements $200,000 $200,000
11 WTP Fencing Improvements $100,000 $100,000
12
WWTP Operations Bldg. Replacement –
Construction
$TBD
$TBD
$TBD
13 WWTP Fencing Improvements $100,000 $100,000
14 Broad Street Lift Station Renovation Phase 2 -
Construction
$TBD
$TBD
$TBD
Totals
$680,000
$TBD
$680,000
Page 28
FY2027
No
Project Name
Total Project Cost
Grant
Funding
City Funding
15 Airport Res Pump House Improvements –
Construction
$TBD
$TBD
$TBD
16
Disinfectant Generation Equipment –
Construction
$500,000
$480,000
$20,000
17 Water Main Valve Replacements I $160,000 $160,000
18 Water Main Line Improvements I $250,000 $250,000
19 Water Meter / Software Equipment $100,000 $100,000
20 Airport Reservoir Tank Exterior Assessment $30,000 $30,000
21 Major Wellhead Maintenance I $100,000 $100,000
Totals
$1,140,000
$480,000
$660,000
FY2028
No
Project Name
Total Project Cost
Grant
Funding
City Funding
22 Airport Reservoir Tank Exterior Repair $270,000 $270,000
23 Water Main Valve Replacements II $160,000 $160,000
24 Florida Ave Water Main – Design $50,000 $50,000
25 WWTP Effluent Flow Monitoring/Auto Dosing $225,000 $225,000
26 Vac Truck $500,000 $400,000 $100,000
Totals
$1,205,000
$400,000
$805,000
FY2029
No
Project Name
Total Project Cost
Grant
Funding
City Funding
27 Florida Ave Water Main – Construction $240,000 $240,000
28 WWTP Influent Pump Station $1,000,000 $800,000 $200,000
Totals
$1,240,000
$800,000
$440,000
Total Project Cost
Grant
Funding
City Funding
W & S Fund FY2025-2029 Grand Total
$5,630,000
$2,138,000
$3,492,000
Page 29
WATER & SEWER PROJECTS
OPERATORS TRUCK
Department: Public Works – Water & Sewer
Total Project Cost: $65,000
Project Phased: No
Project Type: Equipment/Vehicle Replacement
Funding Source(s): Water & Sewer Fund
Potential Grant Identified: State Revolving Fund
Operating Budget Impact: Slight Decrease
YEAR: 2025 2026 2027 2028 2029
COST: $65,000
Details: Replacement of an existing operator truck with new half ton to allow for the continued
operation of the Department. Existing vehicle will be surplus auctioned.
OPERATORS TRUCK
Department: Public Works – Water & Sewer
Total Project Cost: $80,000
Project Phased: No
Project Type: Equipment/Vehicle Replacement
Funding Source(s): Water & Sewer Fund
Potential Grant Identified: State Revolving Fund
Operating Budget Impact: Slight Decrease
YEAR: 2025 2026 2027 2028 2029
COST: $80,000
Details: Replacement of an existing operator truck with new three quarter ton to allow for the
continued operation of the Department. Existing vehicle will be surplus auctioned.
Page 30
WATER & SEWER PROJECTS
Lead Service Line Inventory Support Services
Department: Public Works – Water & Sewer
Total Project Cost: $100,000
Project Phased: No
Project Type:
Funding Source(s): Grant / Water Sewer Fund
Potential Grant Identified: EPA
Operating Budget Impact: None
YEAR: 2025 2026 2027 2028 2029
COST: $100,000
Details: The City of Kenai has new water treatment permitting requirements, which require
reporting of all connections tied to the City’s water distribution system. This project will
provide updated maps, indicating connection types and location.
Lift Station Phase 1 Supplement
Department: Public Works – Water & Sewer
Total Project Cost: $300,000
Project Phased: Yes
Project Type: Infrastructure / Utility
Funding Source(s): Water & Sewer Fund
Potential Grant Identified: None
Operating Budget Impact: Moderate Decrease
YEAR: 2025 2026 2027 2028 2029
COST: $300,000
Details: A Lift Station Renovations project has now finished the design phase. The final product
which address sewer lift stations and mileposts 13 & 14 on the Kenai Spur Highway as well as
the Lawton Drive station, will require additional funding to construct. The project will provide
new pumps and controls to replace 30+ year old technology.
Page 31
WATER & SEWER PROJECTS
BROAD STREET LIFT STATION RENOVATION - DESIGN
Department: Public Works – Water & Sewer
Total Project Cost: $220,000
Project Phased: No
Project Type: Infrastructure
Funding Source(s): Water & Sewer Fund
Potential Grant Identified: State Revolving Fund
Operating Budget Impact: Significant Decrease
YEAR: 2025 2026 2027 2028 2029
COST: $220,000
Details: This project will provide much-needed major improvements to the Broad Street Lift
Station. This is a major collection site with all connections east of Broad St. running through
this site before proceeding to the Waste Water Plant. This project will increase the capacity of
the existing site, provide emergency backup power generation, and replacement of pumps and
controls with new ones.
WWTP OPERATIONS BUILDING
REPLACEMENT - DESIGN
Department: Public Works – WWTP
Total Project Cost: $300,000
Project Phased: No
Project Type: Building Improvement
Funding Source(s): Water Sewer Fund/Grant
Potential Grant Identified: Federal & State Options
Operating Budget Impact: Significant Decrease
YEAR: 2025 2026 2027 2028 2029
COST: $500,000
Details: This Project is the next step in the development of the City’s Water System. In 2011
the Water Treatment Facility located at the intersection of Shotgun Drive and the Kenai Spur
Highway was developed. In 2015/2016 Well Field Improvements were completed. This project
will update the distribution pumps that transport water from the water plant to all end users.
Completion of this work will improve system reliability while increasing our ability to meet
system demand.
Page 32
WATER & SEWER PROJECTS
CCTV EQUIPMENT
Department: Public Works – Water & Sewer
Total Project Cost: $75,000
Project Phased: No
Project Type: Equipment/Technology
Funding Source(s): Water & Sewer Fund
Potential Grant Identified: None
Operating Budget Impact: Minimal
YEAR: 2025 2026 2027 2028 2029
COST: $100,000
Details: This project will provide for the replacement of the Departments existing CCTV camera
equipment with newer technology. This equipment allows operators to trouble shoot sewer
main issues with camera technology.
AIRPORT RESERVOIR PUMP HOUSE IMPROVEMENTS - DESIGN
Department: Public Works – Water & Sewer
Total Project Cost: $300,000
Project Phased: No
Project Type: Infrastructure
Funding Source(s): Water & Sewer Fund/Grant
Potential Grant Identified: Federal and State Option
Operating Budget Impact: Moderate Decrease
YEAR: 2025 2026 2027 2028 2029
COST:
$180,000
Details: This project will provide equipment replacements at the Airport Reservoir Pump
House. This site has a three-million-gallon storage tank which provides the majority of water
for the City during daytime hours. This work will utilize the existing building, but modify pumps
and controls to provide a more robust and reliable system.
Page 33
WATER & SEWER PROJECTS
DISINFECTANT GENERATION EQUIPMENT - DESIGN
Department: Public Works – Water & Sewer
Total Project Cost: $100,000
Project Phased: No
Project Type: Equipment Upgrade
Funding Source(s): Water & Sewer Fund / Grant
Potential Grant Identified: State Revolving Fund
Operating Budget Impact: Moderate Decrease
YEAR: 2025 2026 2027 2028 2029
COST: $100,000
Details: This Project will allow the Public Works department to generate our own chlorine
disinfectant for use at the water and wastewater plants. This will remove the potential for
supply chain issues we experienced starting with COVID.
GIS MAPPING IMPROVEMENTS
Department: Public Works – Water & Sewer
Total Project Cost: $200,000
Project Phased: No
Project Type: Equipment Upgrade
Funding Source(s): Water & Sewer Fund
Potential Grant Identified: None
Operating Budget Impact: Moderate Decrease
YEAR: 2025 2026 2027 2028 2029
COST:
$200,000
Details: This project will update the Utility’s mapping, which is widely used by the department,
contractors and the community. Maps will be updated to reflect recent development as well as
to verify existing locations of water, sewer and fire connections.
Page 34
WATER & SEWER PROJECTS
WATER TREATMENT PLANT FENCING IMPROVEMENTS
Department: Public Works – Water & Sewer
Total Project Cost: $100,000
Project Phased: Yes
Project Type: Infrastructure
Funding Source(s): Water & Sewer Fund
Potential Grant Identified: None
Operating Budget Impact: Minimal
YEAR: 2025 2026 2027 2028 2029
COST:
$100,000
Details: This project will replace 40-year-old fencing and improve site security at several
locations.
WWTP OPERATIONS BUILDING
RENOVATIONS - CONSTRUCTION
Department: Public Works – WWTP
Total Project Cost: $2,280,000
Project Phased: No
Project Type: Building Improvement
Funding Source(s): Water Sewer Fund/Grant
Potential Grant Identified: Federal & State Options
Operating Budget Impact: Significant Decrease
YEAR: 2025 2026 2027 2028 2029
COST:
$TBD
Details: This project will replace the main operations building at the Waste Water Plant which
was originally constructed in 1974 with additions in 1982. The facility is on the shore of Cook
Inlet and subject to the constant presence of salt air. As a result, much of the facility doors,
windows, siding, hardware, etc. have rusted beyond repair. Due to the extent of remodel work
and other issues relating to the size of facility, it has been determined a new building is in the
best interest of the City. With the completion of the design expected for FY2025, grants will be
sought to assist with funding the likely $5,000,000 range of improvements.
Page 35
WATER & SEWER PROJECTS
WASTEWATER TREATMENT PLANT FENCING IMPROVEMENTS
Department: Public Works – Water & Sewer
Total Project Cost: $100,000
Project Phased: Yes
Project Type: Infrastructure
Funding Source(s): Water & Sewer Fund
Potential Grant Identified: None
Operating Budget Impact: Minimal
YEAR: 2025 2026 2027 2028 2029
COST:
$100,000
Details: This project will replace 40+-year-old fencing and improve site security at the
wastewater treatment plant.
BROAD STREET LIFT STATION RENOVATION - CONSTRUCTION
Department: Public Works – Water & Sewer
Total Project Cost: $220,000
Project Phased: No
Project Type: Infrastructure
Funding Source(s): Water & Sewer Fund
Potential Grant Identified: State Revolving Fund
Operating Budget Impact: Significant Decrease
YEAR: 2025 2026 2027 2028 2029
COST:
$TBD
Details: This project will provide much-needed major improvements to the Broad Street Lift
Station. This is a major collection site with all connections east of Broad St. running through
this site before proceeding to the Waste Water Plant. This project will increase the capacity of
the existing site, provide emergency backup power generation, and replacement of pumps and
controls with new ones. With the design anticipated for completion in FY2025, documents and
estimate will be used to pursue grant funding opportunities at the State and Federal level.
Page 36
WATER & SEWER PROJECTS
AIRPORT RESERVOIR PUMP HOUSE IMPROVEMENTS - CONSTRUCTION
Department: Public Works – Water & Sewer
Total Project Cost: $1,200,000
Project Phased: No
Project Type: Infrastructure
Funding Source(s): Water & Sewer Fund/Grant
Potential Grant Identified: Federal and State Option
Operating Budget Impact: Moderate Decrease
YEAR: 2025 2026 2027 2028 2029
COST:
$TBD
Details: This project will provide equipment replacements at the Airport Reservoir Pump
House. This site has a three million gallon storage tank which provides the majority of water for
the City during daytime hours. This work will utilize the existing building, but modify pumps
and controls to provide a more robust and reliable system. The design work is anticipated for
completion in FY2026 and will be used to pursue grant funding opportunities at the State and
Federal level.
DISINFECTANT GENERATION EQUIPMENT - CONSTRUCTION
Department: Public Works – Water & Sewer
Total Project Cost: $500,000
Project Phased: No
Project Type: Equipment Upgrade
Funding Source(s): Water & Sewer
Potential Grant Identified: State Revolving Fund
Operating Budget Impact: Moderate Decrease
YEAR: 2025 2026 2027 2028 2029
COST:
$500,000
Details: This Project is the next step in the development of the City’s Water System. In 2011
the Water Treatment Facility located at the intersection of Shotgun Drive and the Kenai Spur
Highway was developed. In 2015/2016 Well Field Improvements were completed. This project
will update the distribution pumps that transport water from the water plant to all end users.
Completion of this work will improve system reliability while increasing our ability to meet
system demand.
Page 37
WATER & SEWER PROJECTS
WATER MAIN VALVE REPLACEMENTS I
Department: Public Works – Water & Sewer
Total Project Cost: $160,000
Project Phased: No
Project Type: Infrastructure
Funding Source(s): Water & Sewer Fund
Potential Grant Identified: State Revolving Fund
Operating Budget Impact: Moderate
YEAR: 2025 2026 2027 2028 2029
COST:
$160,000
Details: Planned replacements of inoperable 50 year old water main valves with new in various
locations around the City.
WATER MAIN LINE IMPROVEMENTS I
Department: Public Works – Water & Sewer
Total Project Cost: $250,000
Project Phased: No
Project Type: Infrastructure
Funding Source(s): Water & Sewer Fund
Potential Grant Identified: State Revolving Fund
Operating Budget Impact: Moderate Decrease
YEAR: 2025 2026 2027 2028 2029
COST:
$250,000
Details: This project will correct known problem areas within the distribution system.
Page 38
WATER & SEWER PROJECTS
WATER METER / SOFTWARE EQUIPMENT
Department: Public Works – Water & Sewer
Total Project Cost: $100,000
Project Phased: No
Project Type: Technology
Funding Source(s): Water & Sewer Fund
Potential Grant Identified: None
Operating Budget Impact: Slight Decrease
YEAR: 2025 2026 2027 2028 2029
COST:
$100,000
Details: This project will standardize for the department a software solution for reading meters
starting with commercial facilities. This will significantly reduce staff time in reading meters.
AIRPORT RESERVOIR TANK EXTERIOR ASSESSMENT
Department: Public Works – Water & Sewer
Total Project Cost: $30,000
Project Phased: Yes
Project Type: Infrastructure
Funding Source(s): Water & Sewer Fund
Potential Grant Identified: State Revolving Fund
Operating Budget Impact: Minimal
YEAR: 2025 2026 2027 2028 2029
COST:
$30,000
Details: This project will address the exterior appearance of the airport reservoir tank. Five
years ago the interior of the tank was coated to extend its life. This project will address the
exterior insulation and coating that is deteriorating.
Page 39
WATER & SEWER PROJECTS
MAJOR WELLHEAD MAINTENANCE I
Department: Public Works – Water & Sewer
Total Project Cost: $100,000
Project Phased: No
Project Type: Infrastructure
Funding Source(s): Water & Sewer Fund
Potential Grant Identified: State Revolving Fund
Operating Budget Impact: Moderate
YEAR: 2025 2026 2027 2028 2029
COST:
$100,000
Details: This is a preventive maintenance project to provide for the continued operation of the
City’s well field. Items may include well pump and VFD replacements.
AIRPORT RESERVOIR TANK EXTERIOR REPAIR
Department: Public Works – Water & Sewer
Total Project Cost: $270,000
Project Phased: Yes
Project Type: Infrastructure
Funding Source(s): Water & Sewer Fund
Potential Grant Identified: State Revolving Fund
Operating Budget Impact: Moderate
YEAR: 2025 2026 2027 2028 2029
COST:
$270,000
Details: This project will address the exterior appearance of the airport reservoir tank. Five
years ago the interior of the tank was coated to extend its life. This project will address the
exterior insulation and coating that is deteriorating.
Page 40
WATER & SEWER PROJECTS
WATER MAIN VALVE REPLACEMENTS II
Department: Public Works – Water & Sewer
Total Project Cost: $160,000
Project Phased: No
Project Type: Infrastructure
Funding Source(s): Water & Sewer Fund
Potential Grant Identified: State Revolving Fund
Operating Budget Impact: Slight Decrease
YEAR: 2025 2026 2027 2028 2029
COST:
$160,000
Details: Planned replacements of inoperable 50-year-old water main valves with new in various
locations around the City.
FLORIDA AVE WATER MAIN - DESIGN
Department: Public Works – Water & Sewer
Total Project Cost: $50,000
Project Phased: No
Project Type: Infrastructure / Utility
Funding Source(s): Water & Sewer Fund
Potential Grant Identified: None
Operating Budget Impact: Slight Increase
YEAR: 2025 2026 2027 2028 2029
COST:
$50,000
Details: This will be a joint project with the Streets division, to extend a new 12” water main
connecting at Fifth St. and Florida Ave and extending to First St. This project is intended to
resolve 4” water mains that were installed 50+ years ago as part of the old military base. With
recent new construction in the area, the 4” main is limited on how many homes can be served.
By extending the 12” line into the area the existing capacity will be doubled. Total line
extension is approximately 1600lf. Roadway will be reconstructed under a general fund
project.
Page 41
WATER & SEWER PROJECTS
WASTEWATER TREATMENT PLANT EFFLUENT FLOW MONITORING / CONTROL
Department: Public Works – WWTP
Total Project Cost: $225,000
Project Phased: No
Project Type: Technology
Funding Source(s): Grant
Potential Grant Identified: Federal & State Options
Operating Budget Impact: Moderate Decrease
YEAR: 2025 2026 2027 2028 2029
COST:
$225,000
Details: This project will provide equipment to provide more accurate dosing of chemicals in the
treatment of wastewater effluent which will result in savings on Sodium Hypochlorite and
Sodium Bisulfate. Chemical feed will vary based on the flow of effluent leaving the plant.
VAC TRUCK
Department: Public Works – Water &
Sewer
Total Project Cost: $500,000
Project Phased: No
Project Type: Equipment
Funding Source(s): Water Sewer Fund
Potential Grant Identified: State
Revolving Fund
Operating Budget Impact: None
YEAR: 2025 2026 2027 2028 2029
COST:
$500,000
Details: This project will provide for the replacement of the City’s existing Vac Truck. This is an
integral piece of equipment used regularly by the City. We have one, with no backup other
than contracting out the services at a significant expense to the utility. The existing unit will be
surplus auctioned with this purchase. The truck is used to clean and maintain wastewater lift
stations, and the overall sewer collection system. The truck is also capable of jetting clogged
lines.
Page 42
WATER & SEWER PROJECTS
FLORIDA AVE WATER MAIN -
CONSTRUCTION
Department: Public Works – Water & Sewer
Total Project Cost: $240,000
Project Phased: No
Project Type: Infrastructure / Utility
Funding Source(s): Water & Sewer Fund
Potential Grant Identified: None
Operating Budget Impact: Slight Increase
YEAR: 2025 2026 2027 2028 2029
COST:
$240,000
Details: This will be a joint project with the Streets division, to extend a new 12” water main
connecting at Fifth St. and Florida Ave and extending to First St. This project is intended to
resolve 4” water mains that were installed 50+ years ago as part of the old military base. With
recent new construction in the area, the 4” main is limited on how many homes can be served.
By extending the 12” line into the area the existing capacity will be doubled. Total line
extension is approximately 1600lf. Roadway will be reconstructed under a general fund
project.
WASTEWATER TREATMENT PLANT INFLUENT PUMP STATION
Department: Public Works - Water & Sewer
Total Project Cost: $1,000,000
Project Phased: Yes
Project Type: Infrastructure
Funding Source(s): Grant Dependent
Potential Grant Identified: State Revolving Fund
Operating Budget Impact: Moderate Increase
YEAR: 2025 2026 2027 2028 2029
COST:
$1,000,000
Details: This project will replace the existing influent station and install a new pump station to
provide surge protection storage and grit capture. This will allow for more balanced incoming
flows into the plant and reduce staff time on recovering from surges.
Page 43
Senior Citizens Fund
FY2025
No
Project Name
Total Project Cost
Grant
Funding
City Funding
1 Senior Center Canopy Roof Repair $50,000 $50,000
2 Senior Center Landscaping Project Phase I $40,000 $40,000
Totals
$90,000
$90,000
FY2026
No
Project Name
Total Project Cost
Grant
Funding
City Funding
3 Senior Center Landscaping Project Phase II $35,000 $35,000
Totals
$35,000
FY2027
No
Project Name
Total Project Cost
Grant
Funding
City Funding
Nothing Currently Planned this fiscal year
Totals
FY2028
No
Project Name
Total Project Cost
Grant
Funding
City Funding
Nothing Currently Planned this fiscal year
Totals
FY2029
No
Project Name
Total Project Cost
Grant
Funding
City Funding
Nothing Currently Planned this fiscal year
Totals
No
Project Name
Total Project Cost
Grant
Funding
City Funding
Senior Center Fund Grand Total
$125,000
$125,000
Page 44
Blank
Page 45
SENIOR CITIZENS FUND PROJECTS
SENIOR CENTER CANOPY ROOF REPAIR
Department: Senior Center
Total Project Cost: $50,000
Project Phased: No
Project Type: Land Improvement
Funding Source(s): City Funding
Potential Grant Identified:
Operating Budget Impact: Minimal or No Impact
YEAR: 2025 2026 2027 2028 2029
COST: $50,000 Details: This project will repair/replace water damaged roof decking with new and then
installation of a new roof membrane system at the entrance canopy to the Senior Center.
SENIOR CENTER LANDSCAPING - PHASE I
Department: Senior Center
Total Project Cost: $40,000
Project Phased: Yes
Project Type: Land Improvement
Funding Source(s): Grant/ Donation Dependent
Potential Grant Identified: State
Operating Budget Impact: Minimal or No Impact
YEAR: 2025 2026 2027 2028 2029
COST: $40,000 Details: This project would landscape the south lawn of the Senior Center to level the area,
which now contains sunken areas which prohibit safe access, and replant grass and trees as
well as construct walkways for easy and safe maneuvering. This would improve lost access to
the perimeter of the building, yard, and bluff areas for private rentals and the public, including
wheelchair access. The project would be contingent on the construction of the Bluff
Stabilization Project.
Page 46
SENIOR CITIZENS FUND PROJECTS
SENIOR CENTER LANDSCAPING - PHASE II
Department: Senior Center
Total Project Cost: $35,000
Project Phased: Yes
Project Type: Land Improvement
Funding Source(s): Grant/ Donation Dependent
Potential Grant Identified: State
Operating Budget Impact: Minimal or No Impact
YEAR: 2025 2026 2027 2028 2029
COST: $35,000 Details: This project would create a community fire pit area with wooden all-weather park
benches for easy access for seniors and private rentals. Memorial benches and greenery
provide an opportunity to generate revenue and celebrate individuals in the community. The
project would be contingent on the construction of the Bluff Stabilization Project.
Blank
Page 47
Congregate Housing Fund
FY2025
No
Project Name
Total Project Cost
Grant
Funding
City Funding
1 Vintage Point Floors 2 & 3 Hallway Carpet
Repl.
$55,000 $55,000
2 Exterior Door Replacements $60,000 $60,000
3 Apartment Kitchen and Bathroom Remodel $100,000 $100,000
Totals
$215,000
$215,000
FY2026
No
Project Name
Total Project Cost
Grant
Funding
City Funding
3 Apartment Kitchen and Bathroom Remodel $100,000 $100,000
Totals
$100,000
$100,000
FY2027
No
Project Name
Total Project Cost
Grant
Funding
City Funding
6 Apartment Kitchen and Bathroom Remodel $100,000 $100,000
Totals
$100,000
$100,000
FY2028
No
Project Name
Total Project Cost
Grant
Funding
City Funding
Nothing Currently Planned this fiscal year
Totals
FY2029
No
Project Name
Total Project Cost
Grant
Funding
City Funding
Nothing Currently Planned this fiscal year
Totals
No
Project Name
Total Project Cost
Grant
Funding
City Funding
Congregate Housing Fund Grand Total
$355,000
$355,000
Page 48
Blank
Page 49
CONGREGATE HOUSING FUND PROJECTS
VINTAGE POINT FLOORS 2 & 3 HALLWAY CARPET
Department: Senior Center
Total Project Cost: $55,000
Project Phased: Yes
Project Type: Building Improvement
Funding Source(s): Congregate Housing Fund
Potential Grant Identified: None
Operating Budget Impact: Minimal or No Impact
YEAR: 2025 2026 2027 2028 2029
COST: $55,000
Details: This project will replace the 15+ year old carpeting in the hallway and commons areas of
floors two and three as well as all three stair wells.
VINTAGE POINT EXTERIOR DOOR REPLACEMENT
Department: Senior Center
Total Project Cost: $60,000
Project Phased: Yes
Project Type: Building Improvement
Funding Source(s): Congregate Housing Fund
Potential Grant Identified: None
Operating Budget Impact: Minimal or No Impact
YEAR: 2025 2026 2027 2028 2029
COST: $60,000
Details: There remain five wooden exterior doors in need of replacement at the Vintage Point
Senior Housing facility. These include the front entry double doors, exterior door on northwest
side, east side door and the solarium exit door. The front entry door has additional electrical
components which are included with this project.
Page 50
APARTMENT KITCHEN AND BATHROOM REMODEL
Department: Senior Center
Total Project Cost: $300,000
Project Phased: Yes
Project Type: Building Improvement
Funding Source(s): Congregate Housing Fund
Potential Grant Identified: None
Operating Budget Impact: Minimal or No Impact
YEAR: 2025 2026 2027 2028 2029
COST: $100,000 $100,000 $100,000
Details: This project remodels the kitchen and bathrooms in three to six apartments each year
at Vintage Pointe. The project would replace original (1993) tile flooring, cabinetry, countertops,
and fixtures in kitchens and bathrooms to bring apartments into compliance with the Americans
with Disabilities Act. This project is not eligible for low-income housing grants.
Page 51
Personal Use Fishery Fund
FY2025
No
Project Name
Total Project Cost
Grant
Funding
City Funding
1 Boat Ramp Concrete Repairs $175,000 $175,000
2 Boat Ramp Float Replacements $175,000 $175,000
Totals
$350,000
$350,000
FY2026
No
Project Name
Total Project Cost
Grant
Funding
City Funding
Nothing Currently Planned this fiscal year
Totals
FY2027
No
Project Name
Total Project Cost
Grant
Funding
City Funding
Nothing Currently Planned this fiscal year
Totals
FY2028
No
Project Name
Total Project Cost
Grant
Funding
City Funding
Nothing Currently Planned this fiscal year
Totals
FY2029
No
Project Name
Total Project Cost
Grant
Funding
City Funding
Nothing Currently Planned this fiscal year
Totals
Total Project Cost
Grant
Funding
City Funding
Personal Use Fishery Fund Grand Total
$350,000
$350,000
Page 52
Blank
Page 53
PERSONAL USE FISHERY FUND PROJECTS
CITY DOCK BOAT RAMP CONCRETE REPAIRS
Department: Public Works
Total Project Cost: $175,000
Project Phased: No
Project Type: Infrastructure / Harbor
Funding Source(s): State Grant
Potential Grant Identified: 15-DC-078
Operating Budget Impact: Minimal or No Impact
YEAR: 2025 2026 2027 2028 2029
COST: $175,000
Details: This project will replace the severely deteriorating concrete ramps primarily in lane 4 at
the City Dock. The ramps experience severe changes in freezing and thawing conditions with the
tidal influences and river ice both taking their toll. The ramps are primarily used by private
commercial vessels accessing the salmon fishery as well as State residents accessing the personal
use dipnet fishery in July. The Department is working to reallocate existing grant funds from
State Grant 15-DC-078 in support of this project.
CITY DOCK FLOAT REPAIRS
Department: Public Works
Total Project Cost: $175,000
Project Phased: No
Project Type: Infrastructure / Harbor
Funding Source(s): State Grant
Potential Grant Identified: 15-DC-078
Operating Budget Impact: Minimal or No Impact
YEAR: 2025 2026 2027 2028 2029
COST: $175,000
Details: This project will replace the severely deteriorating floats serving all boat launch lanes at
the City Dock. The ramps are primarily used by private commercial vessels accessing the salmon
fishery as well as State residents accessing the personal use dipnet fishery in July. The floats will
be reconstructed in similar design to the existing floats.
Page 54
CIP Existing Project Schedule 011024
Project Cycle FY-2024-2025
J-24 F-24 M-24 A-24 M-24 J-24 J-24 A-24 S-24 O-24 N-24 D-24 J-25 F-25 M-25 A-25 M-25 J-25
Projects
Airport Fund
Sand Storage Facility 2021 342 329 Const Const Final
Airport Operations Boiler & Controls Replacement 2021 328 331 ITB
KMA Runway Rehabilitation 2021 342 333
KMA Improved Airfield Drainage 2021 342 334
KMA Airfield Marking, Crack Sealing, Sealcoat 2023 342 337 ITB
KMA SRE Equipment Loader & Sand Truck 2023 332 340
Terminal Landscaping 2023 335 404
Terminal Surveillance Camera/Ops Access 2023 335 338
Elevator Assessments 2023 335 24301
Airport Master Plan Phase 1 & 2 2023 342 24303
Perimeter Fenceline Improvements 2025
Acquire ARFF Vehicle 2025
General Fund
General Government
Bluff Stabilization Project - Mulityear 2015 129 182 ITB
Cemetery Expansion Phase 1 2019 118 228
Cemetery Expansion phase 2 2022 118 228
Public Safety
Repair Underground Water Tank 2023 135 407
Community Wildfire Protection Mitigation Phase 1 2023 135 413
Community Wildfire Protection Mitigation Phase 2 2024 135 413
Fire Department Flooring Replacement 2024 135 24001
Emergency Services Facility Improvement 2025
Public Works
Bridge Access Pedestrian Path 2020 755 265
Wildwood Drive Rehabilitation 2021 755 253
North Willow Rehabilitation 2021 755 273
Lilac Street Repairs 2023 755 410
Kenai Recreation Center Upgrades 2015 119 285
Multi-purpose Facility Ventilation 2021 217 266
Community Library HVAC Controls 2021 218 267
Kenai City Hall HVAC Unit 2021 228 276
Inlet Woods Storm Drain Repairs 2021 755 271 ITB
Facility Assessments Phase 2 2023 800 411
Elevator Assessment 2024 228 24005
Aliak Storm Water & Paving Repair Design 2024 755 24008
Public Mainwalk Replacements & ADA Ramps 2025 Const.
Youth Corridor Pedestrian & Roadway Improvements 2025
Street Lighting Improvements 2025
Parks, Recreation & Cultural
Kenai Community Library Center Plaza 2021 218 242
Municipal Park Trail Construction 2021 751 251
Softball Field Shelters/Dugouts Replacement 2023 116 405
Slash Disposal Site 2023 116 412
Activity CodeFu
n
d
C
o
d
e
Fu
n
d
i
n
g
F
Y
FY -2024 FY-2025
Grant Closeout
ITB Construction
Grant Closeout
Construction
Design
On Hold / will run concurrent with Runway Rehab
Design Construction Grant Closeout
Grant Closeout
ITB Construction
Construction
Closeout
On Hold awaiting DOT Funding
On Hold awaiting State Funding
Construction Closeout
Design ITB Construction
Construction Closeout
Construction Closeout
ITB Construction Closeout
RFP Design Construction Closeout
Ongoing throughout CWPP projects
ITB Construction Closeout
RFP Design
Contract Equipment on Order
Design Construction
Contract
RFP
Design Phase 1 Design Phase 2
Construction
Design ITB Construction Closeout
Closeout
RFP Design Construction Closeout
Apply for Grants
RFP Design Construction
RFP 35% Design Applying for Grants
Completed remaining funds roll to General Fund
RFP Design
Funding moved to City Hall Improvements Design
RFP
RFP
Closeout
Construction Closeout
Design ITB Construction
RFP Design
Construction
Design ITB Construction Closeout
Alan Robillard Page 1 1/11/2024
Page 55
CIP Existing Project Schedule 011024
Project Cycle FY-2024-2025
J-24 F-24 M-24 A-24 M-24 J-24 J-24 A-24 S-24 O-24 N-24 D-24 J-25 F-25 M-25 A-25 M-25 J-25Activity CodeFu
n
d
C
o
d
e
Fu
n
d
i
n
g
F
Y
FY -2024 FY-2025
Park Area Hazardous Tree Removal 2023 116 24009
Municipal Park Shelter #3 Replacement 2023 116 24010
Recreation Center Athletic Floor Refinishing 2023 119 23005 ITB
Tractor Replacement 2025
Parks & Recreation Master Plan 2025
Old Town Park Reconstruction 2025
Water & Sewer Fund
Water & Sewer Renovations 621
Lift Station Upgrades 2021
MP 13 Lift Station 621 295
MP 14 Lift Station 621 299
Lawton Drive Lift Station 621 400
Water & Sewer Utility Master Plan 2021 621 243
SCADA System Integration 2021 621 244
Hydrant Mapping & Installation Phase 1 2021 621 245
Manhole Restoration 2021 621 264
WTP Pump House Construction 2023 621 408
Cemetery Creek Culvert 2024 621 24013
Broad Street Lift Station Renovation 2025
CCTV Equipment 2025
Waste Water Renovations 625
Water & Sewer Utility Master Plan 2021 625 246
SCADA System Integration 2021 625 250
Digester Blower Replacement and Building 2021 625 263
WWTP Chlorine Contact Basin Repair 2022 625 249
Drainage Repair at Clarifiers 2022 625 292
Electronic Gate and Controls 2023 625 409
WWTP Operations Building Replacement 2025
Senior Center Fund
Senior Center Front Door Modifications 2022 120 287
Senior Center HVAC Controls 2022 120 286
Senior Center Canopy Roof Repair 2025
Senior Center Landscaping Project Phase 1 2025
Congregate Housing Fund
Vintage Point Boiler Replacement & Generator 2022 209 239
Vintage Kitchen/Bathroom Remodel 2023 209 281
Elevator Assessment 2024 209 24003
Vintage Point Floors 2 & 3 Hallway Carpet Replacement 2025
Exterior Door Replacements 2025
PU Fishery Fund
Personal Use Fishery Float Replacements 2023 130 280
Boat Ramp Concrete Repairs 2025 130 280
RFP Design Construction
Reallocating Grant Funds ITB Construction
Design Applying for Grants
Contract Construction
ITB Construction
Design Construction
Closeout
Construction
Closeout
Closeout
Grant Application ITB Construction
Design Construction
Design Construction
RFP
ITB Construction
RFP Design Construction
Construction Grant Closeout
Design
Design
ITB
Construction Closeout
Design
Construction
Closeout
Closeout
Contract Construction
ITB Equipment on Order
Applying for Grants
RFP Design
Design ITB Construction
Contract
Design ITB Construction
Applying for Grants
Alan Robillard Page 2 1/11/2024
Page 56