HomeMy WebLinkAbout2004-02-05 Parks & Recreation Packet SPECIAL MEETING
KENAI PARKS/~ RECREATION COMMISSION
FEBRUARY 5, 2004
CITY HALL COUNCIL CHAMBERS
7:00 P.M.
AGENDA
ITEM 1:
ITEM 2:
ITEM 3:
ITEM 4:
CALL TO ORDER/~ ROLL CALL
AGENDA APPROVAL
OLD BUSINESS
Discussion-- Multipurpose Facility
1. Reviewin§, Prioritizin§ Su§§ested Needs/Updates to Facility with
Recommendation.
2. Summer USe Schedule
ADJOURNMENT
KENAI MULTI-PURPOSE FACILITY
Possible Upgrades For AWG 2006
January 28, 2004
OPTION #1 - Portable Bleachers & Elevated Platform
This option is the most inexpensive route that could possibly be undertaken and
yet accommodate the 2006 Arctic Winter Games. Bleacher space would
accommodate 300 to 400' people and be slightly elevated in order to increase
rink visibility.
No significant impact on operational costs would be realized other than routine
cleaning and maintenance.
Cost Est.
Portable Bleachers
Spectator Netting
Elevated Area (wood)
Total $39,500
$30,000
3,000
6,500
KENAI MULTI-PURPOSE FACILITY
Possible Upgrades For AWG 2006
January 28, 2004
OPTION #2 - Radiant Heat, Security Cameras (and Option #1)
This option not only accommodates the spectator space needed for the 2006
Arctic Winter Games, but also satisfies a very important aspect for the AWG
National Committee, i.e., comfort of athletes, via radiant heat above the player's
boxes. Radiant heat could also be added to the spectator area along with a
temporary wind-screen.
Security cameras could also be installed to deter vandalism at the facility.
Although this has not been a huge problem, cameras may help deter future
problems and perhaps add an element of safoty.
Although more discussion and exploration is warranted with regard to satisfying
the ventilation issue (condensation, dripping, etc.), there is a good chance that
simply removing more exterior panels (both high and Iow) may drastically
improve the situation, however, will not eliminate the problem altogether.
Spraying the interior beams with a recommended material may also help.
Kodiak's outdoor rink relies exclusively on passive ventilation (all four sides open
down Iow and up high coupled with a roof vent). To date they have only
experienced very minor problems with condensation. However, they have only
been in operation since early December, thus, it may be too early to draw any
solid conclusions. Certain exterior panels could be removed this season
(pending budget constraints) and ventilation monitored throughout this spring and
fall.
No significant operational costs would be realized, except for occasional
maintenance of the radiant heat & security cameras. The security camera
recorder is mostly self-sufficient except staff time to review tapes when needed.
Routine maintenance and materials for heaters and camera equipment is
estimated at $2,000 annually.
Cost Estimates:
Option #1 $39,500
Radiant Heat 40,000
Security Cameras 10,000
TOTAL $89,,500
KENAI MULTI-PURPOSE FACILITY
Possible Upgrades For AWG 2006
January 28, 2004
OPTION #3 - Temporary Spectator/Lobby Area (and Option #2)
This option provides all the amenities of option #2, plus a temporary, semi-
enclosed spectator area. Construction could comprise of removable wood
panels that could be erected on an as needed basis. This would primarily allow
for comfort of spectators by providing a sheltered area. Project could be done
less expensively if only frame construction was used in conjunction with tarps.
The disadvantage of this type of temporary construction, if designed for repeated
use, is the staff time required for set-up and lack of storage while not in use.
Based on the premises of a temporary use, a sprinkler system would not be
required.
Operational costs would increase slightly for repair and maintenance work,
including periodic replacement of tarps. Personnel costs to install and remove
panels on an as needed basis would be the largest cost. Presently, there is no
protected area to store this type of set-up.
item Cost Estimate
Option No. 2 $89,500
Temporary Construction
15,000
TOTAL COST $104,000
KENAI MULTI:PURPOSE FACILITY
Possible Upgrades For AWG 2006
January 28, 2004
OPTION #4- Permanent Lobby/Spectator Area (ends of facility open for 24hr.
access)
The permanent area, based on current design drawings as submitted by Architects
Alaska/Klauder & Company Architects, Inc., is approximately 8,000 sq. ff. The option
provides the greatest degree of comfort for both players and spectators since the area
would be a heated environment. The addition not only enhances the architectural
appearance of the facility, but also provides a functional area for the 2006 AWG and
beyond.
The 8,000 sq. ft. may be excessive and could possibly be scaled back to around 4,000 sq.
ft., in which case the warming shacks could be placed under the bleacher area. A
substantial cost savings would probably be realized going this route instead. The
concessions and skate rental counter space could be moved against the walls or even
moved to a different location altogether (newly constructed area along the south east end
of building). The bleachers would be elevated and permanently installed during the
construction phase.
Access to the rink would remain open 24 hours via the ends of the facility. The lobby
and spectator area would subsequently be locked and secured during after-hour use.
Condensation on the dasher board glass directly facing the bleachers would be controlled
via radiant heat and passive ventilation would be used to help control rink condensation.
(a dehumidification system would only operate effectively if the facility were entirely
enclosed).
The disadvantage of this option is naturally the associated costs, both construction and
operations. If the City were to continue contracting out ice maintenance services, an
additional $1,000 to $2,000 per month could be realized primarily due to extra staffing
and janitorial. Additional utility costs would be realized at approximately $1,000 per
month.
Cost Estimates:
Perm. Const. $1,600,000
Sprinkler System 80,000
Radiant Heat 40,000
Security Cameras 10,000
TOTAL $1,730,000
KENAI MULTI-PURPOSE FACILITY
Possible Upgrades For AWG 2006
January 28, 2004
OPTION #5 - Permanent Lobby/Spectator Area and Fully Enclosed
This option includes a fully enclosed facility and is obviously the most expensive
option. Controlled access (for fee collection purposes), reliable ice, increased
control over ice maintenance costs and condensation problems are some of the
advantages of a fully enclosed facility, however, not without a price. A
permanent enclosure would require not only a dehumidification system, but also
some form of mechanical ventilation for the entire rink area, thus increasing utility
costs as well.
Aside from additional utility costs, a fully enclosed facility could eliminate after-
hour use of the facility and severely limit summer use unless staffed. Personnel
and maintenance costs throughout the winter would increase whereby higher ice
fees would be warranted. However, a facility of this nature would also open up
programming opportunities for the community, e.g., tournaments, Learn to Skate
Programs, etc.
More time and analysis would need to be given to staffing requirements and
maintenance expenses based on this type of operation and whether or not the
ice maintenance is treated separately or performed in-house. Cost estimates on
staffing and maintenance could be developed as needed.
Items Cost Estimates
Permament Construction $2,000,000
Mechanical Ventilation 150,000
Sprinkler System
Dehumidifier
Radiant Heat (player's box)
Security Cameras
80,000
70,000
15,000
10,000
TOTAL COST $2,325,000