A RESOLUTION AUTHORIZING A CONTRACT AWARD AND CORRESPONDING PURCHASE
ORDER FOR PROFESSIONAL ARCHITECTURAL AND ENGINEERING SERVICES FOR THE WATER
TREATMENT PLANT PUMPHOUSE PROJECT.
WHEREAS, the City of Kenai released a formal Request for Proposals on March 9, 2020 to provide
Professional Engineering Services as a term agreement to cover Capital Projects for our Water, Sewer,
and Wastewater facilities and infrastructure; and,
WHEREAS, HDL Engineering Consultants was the successful firm provided with a formal Notice of
Award on May 15, 2020 to provide for these services; and,
WHEREAS, this Resolution will award professional architectural and engineering services work for the
Water Treatment Plant Pumphouse project as identified within the FY2024 Capital Improvement Plan;
and,
WHEREAS, the Water Treatment Plant Pumphouse Project will construct a new pumphouse including
new water distribution system pumps and appurtenances at the 420 Shotgun Dr. location to replace
outdated equipment and improve overall system resiliency as detailed within the City's FY2024 Capital
Improvement Plan; and,
WHEREAS, the State of Alaska, Department of Environmental Conservation has offered funding through
the Alaska Drinking Water Fund, as a $1,200,000, 100% forgivable loan through the State's Revolving
Fund as detailed and approved by Council through passage of Resolution 2023-56 at the September 20,
2023 meeting; and,
WHEREAS, design services will extend into the summer with the intent of releasing the project for
construction bids late summer.
NOW, THEREFORE, BE IT RESOLVED BY THE COUNCIL OF THE CITY OF KENAI, ALASKA:
Section 1. That the City Manager is authorized to execute a contract award and corresponding
purchase order to HDL Engineering Consultants in the amount of $187,461.
Section 2. That this Resolution takes effect immediately upon passage.
PASSED BY THE COUNCIL OF THE CITY OF KENAI, ALASKA, THIS 17T" DAY OF APRIL, 2024.
ATTEST:
Miche.4al�leCity Clerk
Approved by Finance:
r �
Brian Gabriel Sr., Mayor
New Text Underlined; [DELETED TEXT BRACKETED]
KFNAI
City of Kenai 1 210 Fidalgo Ave, Kenai, AK 99611-77941 907.283.75351 www.kenaixity
MEMORANDUM
TO: Mayor Gabriel and Council Members
THROUGH: Terry Eubank, City Manager
FROM: Scott Curtin, Public Works Director
DATE: April 7, 2024
SUBJECT: Resolution 2024-14
This Resolution will award professional architectural and engineering services to develop bid
ready construction documents for the Water Treatment Plant Pumphouse project. This project will
provide a new structure and water distribution pumps and associated controls, and will function
as the primary water distribution system for the City.
This project was partially designed during the water filtration plant project roughly twelve years
ago, and did not move forward at that time due to funding limitations. This project now will replace
aging equipment and address system limitations experienced during power outages.
The Public Works Department was successful in applying for and receiving funds through the
State of Alaska's DEC with a 100% forgivable loan through the Alaska Drinking Water Fund in
the amount of $1,200,000 which will cover all of the design costs and a majority of the construction
costs associated with the project.
Design work will continue into the summer, with a construction bid release anticipated for late
summer early fall. Construction may not start until spring 2025 depending on the availability of
construction materials, primarily the steel building components.
Council's approval is respectfully requested.