RESOLUTION NO. 2025-06
Sponsored by: Administration
A RESOLUTION ADOPTING THE CITY'S CAPITAL IMPROVEMENT PLAN FOR FISCAL YEARS 2026-
2030.
WHEREAS, City Council held a Joint Work Session on December 18, 2024 where the draft Capital
Improvement Plan was reviewed and discussed; and,
WHEREAS, the Capital Improvement Plan included with this Resolution is inclusive of the comments and
discussion from the Joint Work Session; and,
WHEREAS, the Airport Commission, Harbor Commission, Planning & Zoning Commission, Parks &
Recreation Commission, Beautification Commission and Council on Aging Commission have expressed
their support of the Plan to Council; and,
WHEREAS, the Administration supports and recommends adoption of the plan; and,
WHEREAS, adoption of this plan is in the best interest of the City; and,
WHEREAS, the Capital Improvement Plan is adjusted annually to meet the ongoing needs of the City.
NOW, THEREFORE, BE IT RESOLVED BY THE COUNCIL OF THE CITY OF KENAI, ALASKA:
Section 1. Council adopts the City of Kenai Capital Improvement Plan for Fiscal Years 2026-2030.
Section 2. Council authorizes the Administration to pursue grant opportunities in support of the
Capital Improvement Plan and to submit projects through CAPSIS, the Legislative Finance Capital
Project Submission and Information System.
Section 3. That this Resolution takes effect immediately upon passage.
PASSED BY THE COUNCIL OF THE CITY OF KENAI, ALASKA, THIS 15T" DAY OF JANUARY, 2025.
o�
Brian Gabriel Sr., Mayor
ATTEST:
Michelle X. Soer, MKC, City Clerk
New Text Underlined; [DELETED TEXT BRACKETED]
K F
N A I
City of Kenai 1 210 Fidalgo Ave, Kenai, AK 99611-7794 1 907.283.75351 www.kenaixity
MEMORANDUM
TO: Mayor Gabriel and Council Members
THROUGH: Terry Eubank, City Manager
FROM: Lee Frey, Public Works Director
DATE: January 7, 2025
SUBJECT: Resolution No. 2025-06 - Capital Improvement Plan FY2026-2030
Adoption
This memo requests adoption of the Fiscal Year 2026-2030 Capital Improvement Plan. The Plan
is a collective effort with input received from staff, commissions, committees, and the community.
Projects were provided by Department Heads, brought forth for discussion at the City's various
commission and committee meetings and reviewed at the City Council's Joint Work Session on
December 18, 2024.
Modifications of note from the version presented at the Joint Work Session are to the Airport Fund.
The terminal parking lot project has been removed. The Runway 02L/20R was added to FY26
with the grant funds expected to be received this fiscal year. Lastly the Taxiway project was
phased over two years to recognize local funds needed upfront to proceed with design work.
Thank you to all the staff, Council members and Committee members that participated in the
development of this document.
1
FISCAL YEARS 2026 – 2030
CITY OF KENAI TERRY EUBANK LEE FREY
CITY HALL CITY MANAGER PUBLIC WORKS DIRECTOR
210 FIDALGO AVENUE TEUBANK@KENAI.CITY LFREY@KENAI.CITY
KENAI, AK 99611 907-283-8223 907-283-8236
2
TABLE OF CONTENTS
Page 3
INTRODUCTION
Page 5
AIRPORT FUND
Page 12
GENERAL FUND
Page 25
WATER & SEWER FUND
Page 36
SENIOR CITIZENS FUND
Page 39
CONGREGATE HOUSING FUND
Page 42
PERSONAL USE FISHERY FUND
Page TBD
APPENDIX A – CAPITAL PROJECT SCHEDULE
(INCLUDES PREVIOUSLY FUNDED PROJECTS AND FY26 PROPOSED PROJECTS)
3
INTRODUCTION
The Public Works Department develops the City of Kenai's Five-Year Capital
Improvement Plan (CIP) in coordination with other City departments,
Administration, Boards, Commissions, and the City Council for the purpose of long-
range capital improvement planning and budgeting. A capital improvement project
is typically a one-time expenditure in excess of $35,000 that has a useful life
exceeding one year or is a major project for long-range planning or development.
Projects included in the plan are generally current needs or anticipated future
needs for items nearing the end of their useful life.
The CIP is divided into six parts based on the City Fund from which the project
would be funded. These include the Airport Fund, General Fund, Water & Sewer
Fund, Senior Citizens Fund, Congregate Housing Enterprise Fund, and Personal Use
Fishery Fund. Projects are not listed in priority order for each Fund by fiscal year.
Active projects funded in prior years are not included in the plan unless additional
capital funding is needed to fund another phase of the project.
Projects identified in the CIP are included for planning purposes and to recognize a
need. Not all projects receive the necessary funding to accomplish them in a
projected year, which is why the list is updated annually. Many projects are
dependent on non-City funding sources, which the City can expect to seek but are
not guaranteed to receive. The availability of outside funds can vary with local,
state, and federal economies. The list may change significantly from year to year as
needs, priorities, local funding, and availability of outside funding changes.
4
Blank
5
AIRPORT FUND
FY2026
No
Project Name
Total Project Cost
Grant
Funding
City Funding
1 Rehabilitate RW 02L/20R - Construction $25,330,100 $25,115,000 $215,100
2 Rehabilitate TW A/B/C/D/E/K/L/M - Design $650,000 $650,000
3 Animal Control Building Roof Replacement $400,000 $400,000
Totals
$26,380,100
$25,115,000
$1,265,100
FY2027
No
Project Name
Total Project Cost
Grant
Funding
City Funding
4 Rehabilitate TW A/B/C/D/E/K/L/M -
Construction
$19,952,100 $19,314,500 $637,600
5 Float Basin TW Sierra w/Access Control &
Lighting
$10,287,000
$9,644,100
$642,900
6 Airport Apron & Willow St Extension $7,448,000 $6,982,500 $465,500
Totals
$37,687,100
$35,941,100
$1,746,000
FY2028
No
Project Name
Total Project Cost
Grant
Funding
City Funding
7 ARFF Building Roof Replacement - Design $100,000 $100,000
Totals
$100,000
$100,000
FY2029
No
Project Name
Total Project Cost
Grant
Funding
City Funding
8 ARFF Building Roof Replacement -
Construction $900,000 $500,000 $400,000
Totals
$900,000
$500,000
$400,000
6
FY2030
No
Project Name
Total Project Cost
Grant
Funding
City Funding
9 Rehabilitate TW F/J & GA Apron $25,528,900 $23,933,300 $1,595,600
10 Rehabilitate TW G/H/J & City Apron $5,910,500 $5,541,100 $369,400
Totals
$31,439,400
$29,474,400
$1,965,000
Total Project Cost
Grant
Funding
City Funding
Airport FY2026-2030 Grand Totals
$96,506,600
$91,030,500
$5,476,100
7
AIRPORT FUND PROJECTS
REHABILITATE RUNWAY 2L/20R -
CONSTRUCTION
Department: Airport
Total Project Cost: $25,330,100
Project Phased: Yes
Project Type: Infrastructure
Funding Source(s): Grant / Airport Fund
Potential Grant Identified: Federal Aviation
Administration
Operating Budget Impact: Increase
YEAR: 2026 2027 2028 2029 2030
COST: $25,330,100
Details: This project will rehabilitate Kenai Municipal Airport’s primary Runway 2L/20R to current
standards. The work will involve milling of the existing runway surface and placement of new
asphalt surfaces along the 7,855 lineal feet in length by 150 lineal feet in width runway. Project
will be bid to receive full grant funding for construction this fiscal year. The City has forward
funded the design effort to date and local funds are anticipated to meet match requirements.
REHAB TW A/B/C/D/E/K/L/M
Department: Airport
Total Project Cost: $20,602,100
Project Phased: Yes
Project Type: Infrastructure
Funding Source(s): Grant / Airport Fund
Potential Grant Identified: Federal Aviation
Administration
Operating Budget Impact: Increase
YEAR: 2026 2027 2028 2029 2030
COST: $650,000 $19,952,100
Details: This project will rehabilitate runway taxiways A, B, C, D, E, K, L, and M to current
standards. The work will involve milling the existing taxiways and placing new asphalt surfaces,
markings, and lighting. HDL Engineering continues to develop design documents in coordination
with the Runway Rehab work. These documents will be completed in advance of the 2026 grant
season as coordinated with the Federal Aviation Administration. The City has forward-funded the
design effort to date.
8
AIRPORT FUND PROJECTS
ANIMAL CONTROL BUILDING ROOF REPLACEMENT
Department: Airport
Total Project Cost: $400,000
Project Phased: No
Project Type: Infrastructure
Funding Source(s): Airport Fund
Potential Grant Identified: None
Operating Budget Impact: Increase
YEAR: 2026 2027 2028 2029 2030
COST: $400,000
Details: This project will replace the failing inverted roof membrane assembly on the Animal
Control Building with a new EPDM roof system.
FLOAT BASIN TW SIERRA W/ACCESS
CONTROL & LIGHTING
Department: Airport
Total Project Cost: $10,287,000
Project Phased: No
Project Type: Infrastructure / Technology
Funding Source(s): Grant / Airport Fund
Potential Grant Identified: Federal Aviation
Administration
Operating Budget Impact: Increase
YEAR: 2026 2027 2028 2029 2030
COST: $10,287,000
Details: The development of the Kenai Municipal Airport (ENA) Seaplane Base (SPB) is critical to
the growth of the airport. The SPB is fundamental to de-conflicting General Aviation (GA)
operations and Commercial Aircraft Operations. It allows for the continued development of GA
to the west and frees up prime commercial aviation property on the east side of the airport and
South Airpark. The project will establish the foundation for the continued growth of the SPB by
appropriately connecting the SPB to the main runway and making several plots available for
hangar, tie-down, and other GA services development.
9
AIRPORT FUND PROJECTS
EA / DESIGN / CONSTRUCTION APRON & WILLOW ST. EXTENSION
Department: Airport
Total Project Cost: $7,448,000
Project Phased: No
Project Type: Land Improvement /
Infrastructure
Funding Source(s): Grant / Airport Fund
Potential Grant Identified: Federal Aviation
Administration
Operating Budget Impact: Increase
YEAR: 2026 2027 2028 2029 2030
COST: $7,448,000
Details: This project would extend the apron taxiway 600 feet for lease lots and N. Willow St.
extension (road and utilities) and provide for lease lot development (five acres).
EA / DESIGN / CONSTRUCTION ARFF BUILDING ROOF REPLACEMENT
Department: Airport
Total Project Cost: $1,000,000
Project Phased: Yes
Project Type: Infrastructure
Funding Source(s): Grant / Airport Fund
Potential Grant Identified: Federal Aviation
Administration
Operating Budget Impact: None
YEAR: 2026 2027 2028 2029 2030
COST: $100,000 $900,000
Details: The Kenai Municipal Airport's Aircraft Rescue Fire Fighting Operations Facility at 515 N.
Willow St. finished construction in 2001. The facility's EPDM roof system, encompassing
approximately 19,637 square feet, will be reaching the end of its intended useful life. This project
will provide design documents for a complete roof replacement. Design documents will be
prepared in FY2028, and construction is scheduled to take place in FY2029.
10
AIRPORT FUND PROJECTS
REHABILITATE TW F/J & GA APRON
Department: Airport
Total Project Cost: $25,528,900
Project Phased: Yes
Project Type: Infrastructure
Funding Source(s): Grant / Airport Fund
Potential Grant Identified: Federal Aviation
Administration
Operating Budget Impact: None
YEAR: 2026 2027 2028 2029 2030
COST: $25,528,900
Details: These sections of asphalt are anticipated to need replacement by the year 2030. The
Edges and lighting of these areas are nearing the end of their useful life and are expected to be
replaced as part of this project.
REHABILITATE TAXIWAYS G/H/J AND CITY APRON
Department: Airport
Total Project Cost: $5,910,500
Project Phased: Yes
Project Type: Infrastructure
Funding Source(s): Grant / Airport Fund
Potential Grant Identified: Federal Aviation
Administration
Operating Budget Impact: None
YEAR: 2026 2027 2028 2029 2030
COST: $5,910,500
Details: These sections of asphalt are anticipated to need replacement by the year 2030. Taxiway
J and the City Apron are already in poor condition. The Edges and lighting of these areas are
nearing the end of their useful life and are expected to be replaced as part of this project.
11
Blank
12
GENERAL FUND
FY2026
No
Project Name
Total Project Cost
Grant
Funding
City Funding
1 Wildwood Drive Rehabilitation $1,480,000 $1,200,000 Note 1
2 Aliak Stormwater and Paving Repair –
Construction $600,000 See Note 2 $600,000
3 Streets Condition Assessment $100,000 $100,000
4 GIS Stormwater, Lighting, and Road Mapping
Improvements $50,000 $50,000
5 Downtown Asphalt Crack Sealing $200,000 See Note 2 $200,000
6 Road Improvements and Repairs $1,150,000 $1,000,000 $150,000
7 Parking Lot Sealcoating and Repairs $300,000 $300,000
8 Flight Services RTU Replacements $400,000 $400,000
9 Beaver Creek Pavilion Replacement $50,000 $50,000
10 Tractor Replacement $70,000 $70,000
11 City Hall Improvements – Design $75,000 $75,000
Totals
$4,475,000
$2,200,000
$1,995,000
FY2027
No
Project Name
Total Project Cost
Grant
Funding
City Funding
12 Old Town Park Reconstruction $1,635,000 $1,000,000 $635,000
13 Gymnasium Drop Curtain Addition $40,000 $40,000
14 City Hall Improvements – Construction $800,000 $640,000 $160,000
15 Gravel Road Improvements $200,000 $200,000
16 Stormwater Improvements $240,000 $240,000
17 Asphalt Roadway Improvements Phase I –
Design $150,000 $150,000
Totals
$3,065,000
$1,640,000
$1,425,000
13
FY2028
No
Project Name
Total Project Cost
Grant
Funding
City Funding
18 Asphalt Roadway Improvements Phase I –
Construction $1,500,000 $1,350,000 $150,000
19 Asphalt Roadway Improvements Phase II –
Design $150,000 See Note 3 $150,000
20 Relocation of Parks & Rec to Daubenspeck –
Design $150,000 $150,000
21 Multipurpose Facility Roof Replacement –
Design $75,000 $75,000
Totals
$1,875,000
$1,350,000
$525,000
FY2029
No
Project Name
Total Project Cost
Grant
Funding
City Funding
22 Relocation of Parks & Rec to Daubenspeck –
Construction $3,000,000 $2,400,000 $600,000
23 Multipurpose Facility Roof – Construction $850,000 $680,000 $170,000
24 Asphalt Roadway Improvements Phase II –
Construction $1,500,000 $1,350,000 $150,000
Totals
$5,350,000
$4,430,000
$920,000
FY2030
No
Project Name
Total Project Cost
Grant
Funding
City Funding
25 Multipurpose Facility Refrigeration System
Replacement $500,000 $500,000
Totals
$500,000
$0
$500,000
Total Project Cost
Grant
Funding
City Funding
General Fund FY2026-2030 Grand Totals
$15,265,000
$9,620,000
$5,365,000
Note 1: The City has completed design work for the Wildwood Drive project and has $280,000 already
appropriated to this project. No new local funds are needed.
Note 2: The City intends to seek grant funds for Citywide Roadway Improvements. If successful in
obtaining funding, these projects may be supplemented with this funding if needed.
Note 3: The City intends to seek grant funds for Asphalt Roadway Improvements. Design of the Phase II
Improvements may be supplemented with grant funds if needed.
14
GENERAL FUND PROJECTS
WILDWOOD DRIVE REHABILITATION
Department: Public Works
Total Project Cost: $1,480,000
Project Phased: No
Project Type: Infrastructure
Funding Source(s): State Grant / General Fund
Potential Grant Identified: State Grant
Operating Budget Impact: Decrease
YEAR: 2026 2027 2028 2029 2030
COST: $1,480,000 Details: This project will rehabilitate Wildwood Drive from the Kenai Spur Highway to the
entrance of the Wildwood Drive Correctional Facility. The roadway is severely deteriorated. The
State of Alaska Department of Corrections is the primary user of the roadway. Designs for the
project are 95% complete, and approximately $280,000 in local funding is available from
previous appropriations for this project. Project activity will include design completion, right of
way acquisition, and construction.
ALIAK STORM WATER & PAVING REPAIR –
CONSTRUCTION
Department: Public Works
Total Project Cost: $600,000
Project Phased: Yes
Project Type: Infrastructure
Funding Source(s): General Fund
Potential Grant Identified: None
Operating Budget Impact: Decrease
YEAR: 2026 2027 2028 2029 2030
COST: $600,000 Details: This project will address a failed stormwater line on Aliak Dr. between Candlelight Dr.
and Highbush Ln. The galvanized piping has collapsed in several locations, which causes the
occasional sinkhole to surface after significant runoff. This project will require the removal of
sections of the roadway and the replacement of existing stormwater piping with new ones or
removal of piping and installation of infiltration basins, followed by resurfacing the roadway.
15
GENERAL FUND PROJECTS
STREETS CONDITION ASSESSMENT
Department: Public Works
Total Project Cost: $100,000
Project Phased: No
Project Type: Planning
Funding Source(s): General Fund
Potential Grant Identified: None
Operating Budget Impact: No Effect
YEAR: 2026 2027 2028 2029 2030
COST: $100,000 Details: This project will assess all the asphalt roads the City of Kenai maintains. The condition
ratings collected from this assessment will be used to develop a priority list for replacing and
maintaining asphalt roadways.
GIS STORMWATER, LIGHTING, AND ROAD MAPPING IMPROVEMENTS
Department: Public Works
Total Project Cost: $50,000
Project Phased: No
Project Type: Information Technology
Funding Source(s): General Fund
Potential Grant Identified: None
Operating Budget Impact: No Effect
YEAR: 2026 2027 2028 2029 2030
COST: $50,000 Details: Funding to be used as part of a project with Water and Sewer funding to update and
import new information into our GIS system. The goal is to include underground stormwater
piping and street light wiring.
16
GENERAL FUND PROJECTS
DOWNTOWN ASPHALT CRACK SEALING
Department: Public Works
Total Project Cost: $200,000
Project Phased: No
Project Type: Infrastructure
Funding Source(s): General Fund
Potential Grant Identified: None
Operating Budget Impact: Decrease
YEAR: 2026 2027 2028 2029 2030
COST: $200,000 Details: The project will use asphalt mastic to seal the wide gaps that are unraveling between
paving joints on downtown roads. Priorities will be Willow and Main. The product is similar to
crack sealing but creates a better bond with the existing asphalt to minimize water intrusion.
ROAD IMPROVEMENTS AND REPAIRS
Department: Public Works
Total Project Cost: $1,150,000
Project Phased: Yes
Project Type: Infrastructure
Funding Source(s): State Grant / General Fund
Potential Grant Identified: State Grant
Operating Budget Impact: Decrease
YEAR: 2026 2027 2028 2029 2030
COST: $1,150,000 Details: General funding for roadway improvements to supplement active projects as needed
and repair major deficiencies. Grant funds would be used start design and construction
improvements to roads identified in the Streets Assessment. If no grant funds are obtained,
local funds will be used to cap gravel roads to improve driving surfaces and drainage.
17
GENERAL FUND PROJECTS
PARKING LOT SEAL COATING AND REPAIRS
Department: Public Works
Total Project Cost: $300,000
Project Phased: No
Project Type: Infrastructure
Funding Source(s): General Fund
Potential Grant Identified: None
Operating Budget Impact: No Effect
YEAR: 2026 2027 2028 2029 2030
COST: $300,000 Details: The project would crack seal and seal coat parking lot areas for the City of Kenai-owned
buildings, excluding the airport and utility buildings, to extend the life of the asphalt. The
project would also make minor repairs to parking lots as needed.
FLIGHT SERVICES RTU REPLACEMENTS
Department: Public Works
Total Project Cost: $400,000
Project Phased: No
Project Type: Building Improvement
Funding Source(s): General Fund
Potential Grant Identified: None
Operating Budget Impact: Decrease
YEAR: 2026 2027 2028 2029 2030
COST: $400,000 Details: This is a planned replacement project for air handling units reaching the end of their
useful life. This work will provide for the efficient and reliable function of HVAC systems at the
facility currently leased by the Federal Aviation Administration (FAA).
18
GENERAL FUND PROJECTS
BEAVER CREEK PARK REPLACEMENT PAVILION
Department: Parks and Recreation
Total Project Cost: $50,000
Project Phased: No
Project Type: Parks & Recreation
Funding Source(s): General Fund
Potential Grant Identified: None
Operating Budget Impact: No Effect
YEAR: 2026 2027 2028 2029 2030
COST: $50,000 Details: Construct a new pavilion at Beaver Creek Park located just off the Spur Highway on
Parkside Dr. This will be a wood frame structure consistent with other similar structures within
the City.
TRACTOR REPLACEMENT
Department: Parks & Recreation
Total Project Cost: $70,000
Project Phased: No
Project Type: Equipment
Funding Source(s): General Fund
Potential Grant Identified: None
Operating Budget Impact: No Effect
YEAR: 2026 2027 2028 2029 2030
COST: $70,000
Details: This project will replace aging equipment with new equipment. A tractor and various
attachments, including a wide area mower deck and snow removal components, are
anticipated. Price will also include purchase of a trailer to haul equipment around City.
Equipment is planned for year-round use.
19
GENERAL FUND PROJECTS
CITY HALL IMPROVEMENTS
Department: Public Works
Total Project Cost: $875,000
Project Phased: Yes
Project Type: Building Improvement
Funding Source(s): Grant / General Fund
Potential Grant Identified: State Capital
Project Submission and Federal Grants to be
Identified
Operating Budget Impact: Decrease
YEAR: 2026 2027 2028 2029 2030
COST: $75,000 $800,000 Details: This project will replace the 40+ year-old exterior doors, windows, exterior siding, and
mechanical ventilation systems. Remodel of interior portions of the building may also occur as
the scope is developed through the design phase.
OLD TOWN PLAYGROUND RECONSTRUCTION
Department: Parks and Recreation
Total Project Cost: $1,635,000
Project Phased: No
Project Type: Parks & Recreation
Funding Source(s): Grant / General Fund
Potential Grant Identified: State Capital Project
Submission and Federal Grants to Be Identified
Operating Budget Impact: No Effect
YEAR: 2026 2027 2028 2029 2030
COST: $1,635,000 Details: This project will replace aging equipment at the park on Peninsula Avenue, adjacent to
the Fine Arts Center in Old Town, a popular destination for visitors and locals. Located near the
Visitor’s Center and several large housing complexes, the park serves as a key recreational space
for families and children. Preliminary meetings with the Kenaitze Indian Tribe, Salamatof Native
Association, and other community members emphasized accessibility, the Native Youth Olympic
Court, art, and Kenai culture as focal points of the design and layout of the park.
20
GENERAL FUND PROJECTS
GYMNASIUM DROP CURTAIN ADDITION
Department: Parks & Recreation
Total Project Cost: $40,000
Project Phased: No
Project Type: Building Improvement
Funding Source(s): General Fund
Potential Grant Identified: None
Operating Budget Impact: No Effect
YEAR: 2026 2027 2028 2029 2030
COST: $40,000 Details: A drop curtain in the Kenai Recreation Center Gymnasium will be added to divide the
space into two usable areas.
STORMWATER IMPROVEMENTS
Department: Public Works
Total Project Cost: $240,000
Project Phased: No
Project Type: Infrastructure
Funding Source(s): General Fund
Potential Grant Identified: None
Operating Budget Impact: Decrease
YEAR: 2026 2027 2028 2029 2030
COST: $240,000 Details: This project will allow Public Works to continue addressing stormwater runoff, culvert,
and catch basin issues as they deteriorate throughout the City.
21
GENERAL FUND PROJECTS
GRAVEL ROADWAY IMPROVEMENTS
Department: Public Works
Total Project Cost: $200,000
Project Phased: No
Project Type: Infrastructure
Funding Source(s): General Fund
Potential Grant Identified: None
Operating Budget Impact: Decrease
YEAR: 2026 2027 2028 2029 2030
COST: $200,000 Details: Funding will be used to continue capping gravel roads in the City to improve the driving
surface and improve drainage.
ASPHALT ROADWAY IMPROVEMENTS
Department: Public Works
Total Project Cost: $3,300,000
Project Phased: No
Project Type: Infrastructure
Funding Source(s): State Grants / General Fund
Potential Grant Identified: None
Operating Budget Impact: Decrease
YEAR: 2026 2027 2028 2029 2030
COST: $150,000 $1,650,000 $1,500,000 Details: Projects to design and seek grant funds for asphalt roadways in the City. Priority lists to
be determined from asphalt assessments and designs to be completed to determine costs and
seek grant funds to complete projects.
22
GENERAL FUND PROJECTS
RELOCATION OF PARKS & REC TO DAUBENSPECK
Department: Parks and Recreation
Total Project Cost: $3,150,000
Project Phased: Yes
Project Type: Building
Funding Source(s): Grant / General Fund
Potential Grant Identified: None
Operating Budget Impact: Increase
YEAR: 2026 2027 2028 2029 2030
COST: $150,000 $3,000,000 Details: This project will relocate Park & Rec facilities from their current location at 332 Airport
Way to 550 Daubenspeck where the Streets, Shop, and Building Maintenance division currently
resides. A new building including garage and office space shall be provided.
MULTIPURPOSE FACILITY ROOF
Department: Public Works
Total Project Cost: $925,000
Project Phased: No
Project Type: Building Maintenance
Funding Source(s): General
Potential Grant Identified: None
Operating Budget Impact: Decrease
YEAR: 2026 2027 2028 2029 2030
COST: $75,000 $850,000 Details: The Multipurpose facility was constructed in 1999. This project will replace the roof at
the expected end of life.
23
GENERAL FUND PROJECTS
MULTIPURPOSE FACILITY REFRIGERATION SYSTEM REPLACEMENT
Department: Parks & Recreation
Total Project Cost: $500,000
Project Phased: No
Project Type: Building Maintenance
Funding Source(s): General Fund
Potential Grant Identified: None
Operating Budget Impact: Decrease
YEAR: 2026 2027 2028 2029 2030
COST: $500,000
Details: The refrigeration system for maintaining the ice rink during the winter is nearing the
end of life. Options are being reviewed for replacement in the future.
24
Blank
25
WATER & SEWER FUND
FY2026
No
Project Name
Total Project Cost
Grant
Funding
City Funding
1 Disinfectant Generation Equipment – Design $100,000 $100,000
2 GIS Mapping Improvements $100,000 $100,000
3 WTP/WWTP Fencing Improvements $200,000 Note 1 $200,000
4 Trading Bay Road Sewer Insulation $100,000 $100,000
Totals
$500,000
$0
$500,000
FY2027
No
Project Name
Total Project Cost
Grant
Funding
City Funding
5 Airport Reservoir Pump House Improvements
– Design
$200,000
$200,000
6 Disinfectant Generation Equipment –
Construction
$500,000
$400,000 $100,000
7 Water Main Line Improvements $250,000 $250,000
8 Water Meter Equipment & Software $200,000 $160,000 $40,000
9 WWTP Operations Building $2,000,000 $1,600,000 $400,000
10 Broad Street Lift Station Reconstruction $600,000 $600,000
Totals
$3,750,000
$2,160,000
$1,590,000
FY2028
No
Project Name
Total Project Cost
Grant
Funding
City Funding
11 Airport Reservoir Tank Exterior Repair –
Design $100,000 $100,000
12 Water Main Line Improvements $250,000 $250,000
13 Airport Reservoir Pump House Improvements
- Construction
$2,000,000 $1,600,000 $400,000
14 WWTP Effluent Flow Monitoring/Auto Dosing $225,000 $225,000
15 Vac Truck Replacement $600,000 $600,000
Totals
$3,175,000
$1,600,000
$1,575,000
26
FY2029
No
Project Name
Total Project Cost
Grant
Funding
City Funding
16 Florida Ave Water Main – Design $60,000 $60,000
17 Airport Reservoir Tank Exterior Repair $1,000,000 $800,000 $200,000
18 Replace WWTP Screening System $2,000,000 $1,600,000 $400,000
Totals
$3,060,000
$2,400,000
$660,000
FY2030
No
Project Name
Total Project Cost
Grant
Funding
City Funding
19 Florida Ave Water Main – Construction $250,000 $250,000
20 Water Main Line Improvements $500,000 $500,000
21 WWTP Influent Pump Station $1,000,000 $800,000 $200,000
Totals
$1,750,000
$800,000
$950,000
Total Project Cost
Grant
Funding
City Funding
Water & Sewer Fund FY2026-2030 Grand
Total
$12,235,000
$6,960,000
$5,275,000
Note 1: Grant funds may be available for all or part of this project that may reduce local funding
requirements.
27
WATER & SEWER PROJECTS
DISINFECTANT GENERATION EQUIPMENT
Department: Public Works – Water & Sewer
Total Project Cost: $600,000
Project Phased: No
Project Type: Equipment
Funding Source(s): Water & Sewer Fund / Grant
Potential Grant Identified: State Revolving Fund
Operating Budget Impact: Decrease
YEAR: 2026 2027 2028 2029 2030
COST: $100,000 $500,000
Details: This Project will allow the Public Works department to generate our own chlorine
disinfectant for use at the water and wastewater plants. This project will result in long-term
cost savings over purchasing liquid disinfectant.
GIS MAPPING IMPROVEMENTS
Department: Public Works – Water & Sewer
Total Project Cost: $100,000
Project Phased: No
Project Type: Information Technology
Funding Source(s): Water & Sewer Fund
Potential Grant Identified: None
Operating Budget Impact: No Effect
YEAR: 2026 2027 2028 2029 2030
COST: $100,000
Details: This project will update the water and sewer mapping for the utility systems. Funds to
be used with a general fund project to update street light and storm sewer mapping.
28
WATER & SEWER PROJECTS
WTP & WWTP FENCING IMPROVEMENTS
Department: Public Works – Water & Sewer
Total Project Cost: $200,000
Project Phased: No
Project Type: Infrastructure
Funding Source(s): Water & Sewer Fund /
Grant
Potential Grant Identified: SHSP
Operating Budget Impact: No Effect
YEAR: 2026 2027 2028 2029 2030
COST: $200,000
Details: This project will add fencing where needed to secure utility sites and replace damaged
fencing at the WWTP. Grant funds are being pursued for this project.
TRADING BAY ROAD SEWER INSULATION
Department: Public Works – Water & Sewer
Total Project Cost: $100,000
Project Phased: No
Project Type: Infrastructure
Funding Source(s): Water & Sewer Fund
Potential Grant Identified: None
Operating Budget Impact: Decrease
YEAR: 2026 2027 2028 2029 2030
COST: $100,000
Details: Several sewer services on Trading Bay Road have annual freezing issues due to the
shallow burial depth. The project will excavate and insulate these service lines within the ROW
to reduce the chances of freezing during winter.
29
WATER & SEWER PROJECTS
AIRPORT RESERVOIR PUMP HOUSE IMPROVEMENTS
Department: Public Works – Water & Sewer
Total Project Cost: $2,200,000
Project Phased: No
Project Type: Infrastructure
Funding Source(s): Water & Sewer Fund/Grant
Potential Grant Identified: State Revolving Fund
Operating Budget Impact: Decrease
YEAR: 2026 2027 2028 2029 2030
COST:
$200,000 $2,000,000
Details: This project will provide equipment replacements at the Airport Reservoir Pump
House. This site has a three-million-gallon storage tank that provides the majority of the City's
water during daytime hours. This work will utilize the existing building but modify pumps and
controls to increase reliability and operations with our water plant.
WATER MAIN LINE IMPROVEMENTS
Department: Public Works – Water & Sewer
Total Project Cost: $1,000,000
Project Phased: Yes
Project Type: Infrastructure
Funding Source(s): Water & Sewer Fund
Potential Grant Identified: None
Operating Budget Impact: No Effect
YEAR: 2026 2027 2028 2029 2030
COST:
$250,000 $250,000
$500,000
Details: Funds will be used to improve and modify our water distribution system. The main
areas to be targeted include the installation of fire hydrants for improved flushing and fire
coverage and the looping of mains to reduce dead ends and poor water quality.
30
WATER & SEWER PROJECTS
WATER METER EQUIPMENT AND
SOFTWARE
Department: Public Works – Water & Sewer
Total Project Cost: $200,000
Project Phased: No
Project Type: Information Technology
Funding Source(s): Water & Sewer Fund
Potential Grant Identified: None
Operating Budget Impact: Decrease
YEAR: 2026 2027 2028 2029 2030
COST:
$200,000
Details: This project will standardize a software solution for reading meters for the
department, starting with commercial facilities. This project will significantly reduce staff time
in reading meters.
WWTP OPERATIONS BUILDING RENOVATIONS - CONSTRUCTION
Department: Public Works – WWTP
Total Project Cost: $2,000,000
Project Phased: No
Project Type: Building Improvement
Funding Source(s): Water & Sewer Fund/Grant
Potential Grant Identified: State Revolving Fund
Operating Budget Impact: Decrease
YEAR: 2026 2027 2028 2029 2030
COST:
$2,000,000
Details: This project will replace the primary operations building at the Waste Water Plant,
initially constructed in 1974, with additions in 1982. The facility is on the shore of Cook Inlet
and is subject to the constant presence of salt air. As a result, much of the facility doors,
windows, siding, hardware, etc., have rusted beyond repair. Due to the extent of remodel work
and other issues relating to the size of the facility, it has been determined that a new building is
in the City's best interest. Costs will be determined through design efforts before seeking grant
funds.
31
WATER & SEWER PROJECTS
BROAD STREET LIFT STATION RECONSTRUCTION
Department: Public Works – Water & Sewer
Total Project Cost: $600,000
Project Phased: No
Project Type: Infrastructure
Funding Source(s): Water & Sewer Fund
Potential Grant Identified: None
Operating Budget Impact: Decrease
YEAR: 2026 2027 2028 2029 2030
COST:
$600,000
Details: This project will provide major improvements to the Broad Street Lift Station that are
much-needed. This project is a major collection site with all connections east of Broad St.
running through this site before proceeding to the Waste Water Plant. This project will increase
the capacity of the existing site, provide emergency backup power generation, and replace
pumps and controls with new ones.
AIRPORT RESERVOIR TANK EXTERIOR REPAIR
Department: Public Works – Water & Sewer
Total Project Cost: $1,100,000
Project Phased: Yes
Project Type: Infrastructure
Funding Source(s): Water & Sewer Fund/Grant
Potential Grant Identified: State Revolving Fund
Operating Budget Impact: No Effect
YEAR: 2026 2027 2028 2029 2030
COST:
$100,000 $1,000,000
Details: This project will address the exterior appearance of the airport reservoir tank. The
interior of the tank was coated to extend its life. This project will address the deteriorating
exterior insulation and coating.
32
WATER & SEWER PROJECTS
WASTEWATER TREATMENT PLANT EFFLUENT FLOW MONITORING / DOSING
CONTROL
Department: Public Works – WWTP
Total Project Cost: $225,000
Project Phased: No
Project Type: Process Control
Funding Source(s): Water & Sewer Fund
Potential Grant Identified: None
Operating Budget Impact: Decrease
YEAR: 2026 2027 2028 2029 2030
COST:
$225,000
Details: This project will provide equipment to provide more accurate dosing of chemicals in the
treatment of wastewater effluent, which will result in savings in sodium hypochlorite and
sodium bisulfate. Chemical feed will vary based on the flow of effluent leaving the plant.
VAC TRUCK
Department: Public Works – Water &
Sewer
Total Project Cost: $600,000
Project Phased: No
Project Type: Equipment
Funding Source(s): Water & Sewer Fund
Potential Grant Identified: None
Operating Budget Impact: No Effect
YEAR: 2026 2027 2028 2029 2030
COST:
$600,000
Details: This project will provide for the replacement of the City's existing Vac Truck. This
vehicle is an integral piece of equipment used regularly by the City. We have one, with no
backup other than contracting out the services at a significant expense to the utility. The truck
cleans and maintains wastewater lift stations and the overall sewer collection system. The truck
is also capable of jetting clogged lines.
33
WATER & SEWER PROJECTS
FLORIDA AVE WATER MAIN
Department: Public Works – Water & Sewer
Total Project Cost: $310,000
Project Phased: Yes
Project Type: Infrastructure
Funding Source(s): Water & Sewer Fund
Potential Grant Identified: None
Operating Budget Impact: No Effect
YEAR: 2026 2027 2028 2029 2030
COST:
$60,000 $250,000
Details: Extend a new 12" water main connecting Fifth St. and Florida Ave and extending to
First St. This project is intended to remedy issues with 4" water mains installed 50+ years ago
as part of the old military base. With recent new construction in the area, the 4" mains are
limited in terms of how many homes can be served. The 12” main would reduce existing
bottlenecks in capacity. The total line extension is approximately 1600lf.
REPLACE WWTP SCREENING SYSTEM
Department: Public Works – Water & Sewer
Total Project Cost: $2,000,000
Project Phased: No
Project Type: Process Technology
Funding Source(s): Water & Sewer Fund
Potential Grant Identified: State Revolving Fund
Operating Budget Impact: Decrease
YEAR: 2026 2027 2028 2029 2030
COST:
$2,000,000
Details: The screening system at the WWTP is aging, and equipment occasionally fails, causing
backup and cleaning issues. The project would replace aging equipment with new technology
and improve operations for handling higher flows with redundancy.
34
WATER & SEWER PROJECTS
WASTEWATER TREATMENT PLANT INFLUENT PUMP STATION
Department: Public Works - Water & Sewer
Total Project Cost: $1,000,000
Project Phased: No
Project Type: Infrastructure
Funding Source(s): Water & Sewer Fund/Grant
Potential Grant Identified: State Revolving Fund
Operating Budget Impact: No Effect
YEAR: 2026 2027 2028 2029 2030
COST:
$1,000,000
Details: This project will replace the existing influent station and install a new pump station to
provide surge protection storage and grit capture. This project will allow for more balanced
incoming flows into the plant and reduce staff time on recovering from surges.
35
Blank
36
SENIOR CITIZENS FUND
FY2026
No Project Name Total Project Cost
Grant
Funding City Funding
Nothing Currently Planned
Totals
FY2027
No Project Name Total Project Cost
Grant
Funding City Funding
1 Senior Center Landscaping Project Phase I $40,000 $40,000
Totals $40,000 $40,000
FY2028
No Project Name Total Project Cost
Grant
Funding City Funding
2 Senior Center Landscaping Project Phase II $35,000 $35,000
Totals $35,000 $35,000
FY2029
No Project Name Total Project Cost
Grant
Funding City Funding
Nothing Currently Planned this fiscal year
Totals
FY2030
No Project Name Total Project Cost
Grant
Funding City Funding
Nothing Currently Planned this fiscal year
Totals
No Project Name Total Project Cost
Grant
Funding City Funding
Senior Citizens Fund FY 2026-2030 Grand
Total
$75,000 $75,000
37
SENIOR CITIZENS FUND PROJECTS
SENIOR CENTER LANDSCAPING
Department: Senior Center
Total Project Cost: $75,000
Project Phased: Yes
Project Type: Land Improvement
Funding Source(s): Senior Citizens Fund
Potential Grant Identified: None
Operating Budget Impact: No Effect
YEAR: 2026 2027 2028 2029 2030
COST: $40,000 $35,000
Details: This project would landscape the south lawn of the Senior Center to level the area,
replant grass and trees, and construct walkways for easy and safe maneuvering. This would
improve lost access to the perimeter of the building, yard, and bluff areas for private rentals
and the public, including wheelchair access. The project has been pushed back until the bluff
erosion has stabilized.
38
Blank
39
CONGREGATE HOUSING FUND
FY2026
No Project Name Total Project Cost
Grant
Funding City Funding
1 Elevator Maintenance $100,000 $100,000
Totals $100,000 $100,000
FY2027
No Project Name Total Project Cost
Grant
Funding City Funding
2 Apartment Kitchen and Bathroom Remodel $100,000 $100,000
Totals $100,000 $100,000
FY2028
No Project Name Total Project Cost
Grant
Funding City Funding
3 Apartment Kitchen and Bathroom Remodel $100,000 $100,000
Totals $100,000 $100,000
FY2029
No Project Name Total Project Cost
Grant
Funding City Funding
Nothing Currently Planned
Totals
FY2030
No Project Name Total Project Cost
Grant
Funding City Funding
Nothing Currently Planned
Totals
No Project Name Total Project Cost
Grant
Funding City Funding
Congregate Housing Fund FY2026-2030
Grand Total $300,000 $300,000
40
CONGREGATE HOUSING FUND PROJECTS
ELEVATOR MAINTENANCE
Department: Senior Center
Total Project Cost: $100,000
Project Phased: No
Project Type: Building Improvement
Funding Source(s): Congregate Housing Fund
Potential Grant Identified: None
Operating Budget Impact: No Effect
YEAR: 2026 2027 2028 2029 2030
COST: $100,000
Details: These funds will supplement previously appropriated elevator maintenance funds to
complete a modernization of the elevator.
CONGREGATE HOUSING FUND PROJECTS
APARTMENT KITCHEN AND BATHROOM REMODEL
Department: Senior Center
Total Project Cost: $200,000
Project Phased: Yes
Project Type: Building Improvement
Funding Source(s): Congregate Housing Fund
Potential Grant Identified: None
Operating Budget Impact: No Effect
YEAR: 2026 2027 2028 2029 2030
COST: $100,000 $100,000
Details: This project remodels the kitchen and bathrooms in three to six apartments each year
at Vintage Pointe. The project would replace original (1993) tile flooring, cabinetry, countertops,
and fixtures in kitchens and bathrooms to bring apartments into compliance with the Americans
with Disabilities Act. This project is not eligible for low-income housing grants.
41
Blank
42
PERSONAL USE FISHERY FUND
FY2026
No Project Name Total Project Cost
Grant
Funding
City Funding
Nothing Currently Planned
Totals
FY2027
No Project Name Total Project Cost
Grant
Funding
City Funding
Nothing Currently Planned
Totals
FY2028
No Project Name Total Project Cost
Grant
Funding
City Funding
Nothing Currently Planned
Totals
FY2029
No Project Name Total Project Cost
Grant
Funding
City Funding
Nothing Currently Planned
Totals
FY2030
No Project Name Total Project Cost
Grant
Funding
City Funding
Nothing Currently Planned
Totals
Total Project Cost
Grant
Funding
City Funding
Personal Use Fishery Fund FY2026-2030
Grand Total
43
Blank
44
APPENDIX A –
CAPITAL PROJECT SCHEDULE
(INCLUDES PREVIOUSLY FUNDED PROJECTS AND FY26 PROPOSED PROJECTS)
FY26 Project Schedule
Project Cycle FY-2025-2026
J-25 F-25 M-25 A-25 M-25 J-25 J-25 A-25 S-25 O-25 N-25 D-25 J-26 F-26 M-26 A-26 M-26 J-26
Projects
Airport Fund
Airport Operations Boiler & Controls Replacement 2021
KMA Runway Rehabilitation 2021
KMA Airfield Marking, Crack Sealing, Sealcoat 2023 Design ITB
Terminal Surveillance Camera/Ops Access 2023 RFP
Airport Master Plan Phase 1 & 2 2023
Perimeter Fenceline Improvements 2025
Acquire ARFF Vehicle 2025
Rehabilitate Taxiway 2026
Animal Control Building Roof Replacement 2026 ITB
General Fund
General Government
Bluff Stabilization Project - Mulityear 2015
Cemetery Expansion Phase 1 2019
Cemetery Expansion Phase 2 2022
Public Safety
Repair Underground Water Tank 2023
Community Wildfire Protection Mitigation Phase 2/3 2024 ITB
Fire Department Flooring Replacement 2024
Emergency Services Facility Improvement 2025 RFP
Public Works
Bridge Access Pedestrian Path 2020
Wildwood Drive Rehabilitation 2021
Kenai City Hall HVAC Unit 2021
Inlet Woods Storm Drain Repairs 2021
Facility Assessments Phase 2 2023
Elevator Assessment 2024
Aliak Storm Water & Paving Repair Design 2024 RFP ITB
Public Mainwalk Replacements & ADA Ramps 2025
Street Lighting Improvements 2025 RFP ITB
Streets Assessment 2026
GIS Mapping Improvements 2026
Downtown Asphalt Crack Sealing 2026
Road Improvements and Repairs 2026
Parking Lot Sealcoating and Repairs 2026
Flight Services RTU Replacements 2026 ITB
City Hall Improvements - Design 2026
Parks, Recreation & Cultural
Softball Field Shelters/Dugouts Replacement 2023
Slash Disposal Site 2023
Municipal Park Shelter #3 Replacement 2023 ITB
Tractor Replacement 2026
Ongoing throughout CWPP projects
ConstructionDesign
Design/Construction
On Hold Pending Street Assessment
Assessment/Design
ITB
Closeout
ConstructionRFPDesign
On Hold awaiting DOT Funding
On Hold Seeking Grant Funds
On Hold to Design City Hall Improvements
On Hold to Design City Hall Improvements
Being Re-evaluated - May be incorportated in Architectural RFP
ITB
Procurement
Fu
n
d
i
n
g
F
Y
FY -2025 FY-2026
Construction Grant Closeout
Seek Funding
Construction Grant Closeout
Design Phase 1 Design Phase 2
Procurement/Ordering
Design
Construction
On Hold for Public Safety Building Assessment
Construction - Phase 2 Construction - Phase 3
On Hold for Public Safety Building Assessment
Assessment Apply for Grants/Schematic Design
Construction
Grant Dependent
RFP Design Construction
RFP Design
Construction
Design Construction
ConstructionITBDesign
ITB Construction
ITB
RFP
ITB Construction
Design Construction
Contract
Construction
RFP Design Construction
Assessment
RFP Design
45
FY26 Project Schedule
Project Cycle FY-2025-2026
J-25 F-25 M-25 A-25 M-25 J-25 J-25 A-25 S-25 O-25 N-25 D-25 J-26 F-26 M-26 A-26 M-26 J-26Fu
n
d
i
n
g
F
Y
FY -2025 FY-2026
Parks & Recreation Master Plan 2025 RFP
Tractor Replacement 2026
Beaver Creek Pavilion Replacement 2026 ITB
Water & Sewer Fund
Water & Sewer Renovations 621
Lift Station Upgrades 2021
MP 13 Lift Station
MP 14 Lift Station
Lawton Drive Lift Station
WTP Pump House Construction 2023 ITB
Cemetery Creek Culvert 2024
Broad Street Lift Station Renovation 2025
Disinfectant Generation Equipment - Design 2026 RFP
GIS Mapping Improvements 2026
WTP Fencing Improvements 2026
Trading Bay Road Sewer Insulation 2026
Waste Water Renovations 625
Digester Blower Replacement and Building 2021 ITB
Electronic Gate and Controls 2023
WWTP Fencing Improvements 2026
Senior Center Fund
Senior Center Front Door Modifications 2022
Senior Center Canopy Roof Repair 2025
Congregate Housing Fund
Vintage Kitchen/Bathroom Remodel 2023 RFP
Elevator Maintenance 2024 ITB
Vintage Point Floors 2 & 3 Hallway Carpet Replacement 2025
Exterior Door Replacements 2025 RFP
PU Fishery Fund
Personal Use Fishery Float Replacements 2023
Boat Ramp Concrete Repairs 2025
ITB Construction
Design ITB Construction
Construction
ITB
Construction
Construction
ITB Construction
Design Construction
Construction
Grant Dependent
Design Seek Grant Funding
RFP Design
Grant Dependent
Design Construction
Applying for Grant
Design ITB Construction
Procurement
On Hold - Applying for Grant
RFP Design Construction
Master Planning
Construction
Design
Construction
ITB
Design
46
MEMORANDUM
TO: Mayor Gabriel and Council Members
THROUGH: Terry Eubank, City Manager
FROM: Kathy Romain, Senior Center Director
DATE: January 7, 2025
SUBJECT: Council on Aging Commission Recommendation to City Council
On May 7, 2024 City Council approved the Council on Aging Commission 2024 Work Plan and
Objective No. 2 of the work plan was, “Discuss and Research Adding More Senior Housing for
the City of Kenai”.
During the December 12, 2024 Council on Aging Commissions regular meeting, the commission
approved a motion to, “Recommend City Council Investigate the need for Additional Senior
Housing”.
If this recommendation is supported by the City Council, you may choose to add a project to the
Fiscal Year 2026 - 2030 Capital Improvement Plan or to provide direction to the Administration
to include funding for a project in the Fiscal Year 2026 Operation Budget.
Attached:
Council on Aging Commission 2024 Work Plan - Objective No. 2
2024 – COUNCIL ON AGING ANNUAL WORK PLAN
2024 Annual Work Plan City of Kenai Council on Aging
INTRODUCTION
This area should include a brief description of the overall purpose of the commission. Note: Work plans developed by the advisory body will be submitted to the City Council for
approval; therefore, it is a good idea to align the goals and objectives with city code, policy and the City of Kenai Comprehensive Plan.
The Mission of the Council on Aging Commission is to advise the Mayor, the City Council, Senior Center Director, and City of Kenai the needs of the elderly in the area of
seniors, support the programs which enable the continued independence of senior citizens and serve as an advisory committee. Duties include advising the Senior Center
Director on matters dealing with the budgets for senior programs and programs operated at the Kenai Senior Center (KSC).
Instructions: In the space provided below, create a list of issues and goals (objectives) your commission would like to address in the upcoming year, your list should also
include plans on how to address those issues. Each objective listed should include information regarding additional staff resources and/or community volunteers needed;
funding resources, are funds available in the budget if not are you proposing council include funding in the upcoming budget cycle; and how long is it expected to obtain
the objective. Pease prioritize the objectives of your group with number one (1) being the top priority.
GOAL OR OBJECTIVE COLLABORATION FUNDING RESOURCES TIME TO COMPLETE
Objective No. 2 _______ Objective: Discuss and Research Adding More Seniors Housing for the City of Kenai Estimated Time to Complete: 2024 __________________________
Strategy: (Provide a summary of tasks which need to be done to obtain the objective.)
1. Discuss and research adding more senior housing for the City of Kenai.
a. Schedule work sessions and assign research tasks to commission members.
b. Compile finds and provide a comprehensive report to the City Council Member representing the Council on Aging Commission.
c. Have the City Council Representative report the findings and recommendations to the full Kenai City Council.
Narrative: (Describe the benefits to the residents and visitors of the City.)
There is currently a one year waiting list for housing for Vintage Pointe Manor. Research and discussions on the viability and finding sources needs to begin for planning
future senior housing.
Collaboration: (Who needs to be involved to obtain the objective?)
The Council on Aging Commission members and KSC staff. This task has been assigned to two Commission members.
Funding: (Are funds available, or is funding needed in a future budget?)
No funding required.
6