RENAI COMMUNITY CENTER
PROPOSED BIDDING PROCEDURES
In view of the limited funds available, the following procedure is
recommended should bidding be proposed this year.
1. BIDDING ALTERNATES:
Base Bid 2,835,000 2,835,000
This consists of the building 100
completed, furnished with water and
sewer connected.
Does not include site work e. g.
parking lots, connecting roads,
landscaping.
ADDITIVE ALTERNATES
West Road to Site 110,000
West Site work 500,000
East Site Work 600.000
1,210,000 1,210.060
TOTAL 4,045,000
All the above figures include a 10~ bidding contingency
2. BIDDING TTME:
We recommend bidding the project sometime in August, immediately
after the HEA project bids. Since the HEA project is the same
construction type i. e. steel frame, dryvit exterior, same roofing
system and since HEA's project is more than twice the size of the
Community Center Project we feel the possibility exists for the
costs for Contractors and Subcontractors General Requirements e. g.
mobilization, etc. to be shared, thus reducing the Sid Price.
Hence the Bid Date for the Communtty Center should be
approximately one week after that of the FIFA project.