HomeMy WebLinkAboutResolution No. 2010-01BIDDER
Base Bid
Add Alt
#1
Add Alt
#2
Add Alt
#3
Add Alt
#4
TOTAL
BID
SOUTH CENTRAL
CONSTRUCTION
2,673,259.00
240,807.00
263,213.00
92,536.00
195,104.00
3,464,919.00
GMC
CONTRACTING
$2,559,778.29
$310,127.00
250,986.74
$132,412.27
$227,039.06
$3,480,343.36
ROGER NICKEL
CONTRACTING
$3,276,505.00
$366,365.00
$365,345.00
$122,322.00
$250,380.00
$4,380,917.00
TWIN PEAKS
CONTRUCTION
$2,700,677.00
$242,550.00
$271,252.00
$190,780.00
$304,790.00
$3,710,049.00
FOSTER
CONSTRUCTION
$2,872,959.00
$281,233.00
$330,897.00
$1.09,517.00
$232,750.00
$3,827,356.00
NORTH STAR
PAVING
CONSTRUCTION
$2,270,347.30
$234,640.00
$229,421.00
$150,211.50
$333,381.00
$3,218,000.80
CONSTRUCTION
UNLIMITED
$3,387,876.00
$367,728.00
$478,147.00
$242,700.00
$384,400.00
$4,860,851.00
he cy
KENAI, ALASKA
CITY OF KENAI
RESOLUTION NO. 2010 -01
SUBSTITUTE
Suggested by: Administration
A RESOLUTION OF THE COUNCIL OF THE CITY OF KENAI, ALASKA, APPROVING A
CONTRACT TO NORTH STAR PAVING CONSTRUCTION FOR THE PROJECT
ENTITLED BRIDGE ACCESS WATER AND SEWER 2009 FOR THE TOTAL AMOUNT
OF $3,218,000.80.
WHEREAS, the following bids were received on December 30, 2009:
and,
WHEREAS, North Star Paving Construction's bid is the lowest responsible bid and
award to this bidder would be in the best interest of the City; and,
WHEREAS, the recommendation from the City Administration is to award the contract
to North Star Paving Construction for the total cost of $3,218,000.80; and,
WHEREAS, sufficient monies are appropriated.
SUBSTITUTE
Resolution No. 2010 -01
Page 2 of 2
NOW, THEREFORE, BE IT RESOLVED BY THE COUNCIL OF THE CITY OF KENAI,
ALASKA, the contract for the project entitled Bridge Access Water and Sewer 2009 be
awarded to North Star Paving 86 Construction for the total amount of $3,218,000.80.
PASSED BY THE COUNCIL OF THE CITY OF KENAI, ALASKA, this sixth day of
January, 2010.
ATTEST:
Carol L. Freas, City Clerk
Approved by Finance:
PAT PORTER, MAYOR
the edy of
KENAI, ALASKA
I/c' /laye with a Past, Cc ty with a Future
210 Fidalgo Avenue, Kenai, Alaska 99611 -7794 d
Telephone: (907) 283 -7535, Ext. 236 FAX: (907) 283 -3014 tl II 1
1992
MEMORANDUM
DUM
TO: RiCk Koch, City Mal dye'
FROM: Kevin Lyon, Capital Projects Manager
DATE: December 31, 2009
SUBJECT: AWARD OF CONTRACT; BRIDGE ACCESS WATER AND
SEWER 2009
Rick,
Attached is the completed resolution that was submitted in blank form due to the holiday
packet schedule detailed in my previous memo dated December 30, 2009.
On December 30 bids for the project were opened and seven bids were received.
These bids have been reviewed and it has been determined that North Star Paving
Construction was the lowest bidder. The bid documents were complete and responsive
and sufficient funds are available to award all four additive alternates as listed below:
Basic Bid for the water main begins at Tern Avenue Childs Avenue and includes
crossing of Bridge Access Road with water main at Childs Avenue. The sewer main
begins at Frontage Road and ends at Childs Avenue.
Additive Alternate 1 extends the basic bid so the water main begins at Childs Avenue
and ends at Beaver Loop.
Additive Alternate 2- extends the basic bid so the sewer begins at Childs Avenue and
ends at Beaver Loop.
Additive Alternate 3 extends the basic bid so the sewer main crosses Bridge Access
Road at Childs Avenue.
Additive Alternate 4 extends the additive alternate one and two so the water and sewer
main cross Bridge Access Road at Beaver Loop Road.
The attached completed Resolution 2010 -01 recommends award of the contract to North
Star Paving and Construction for the total cost of $3,218,000.80.