A RESOLUTION OF THE COUNCIL OF THE CITY OF KENAI, ALASKA, APPROVING A
CONTRACT TO WINCE CORTHELL BRYSON CONSULTING ENGINEERS FOR
ENGINEERING DESIGN FOR FLOAT PLANE BASIN DEVELOPMENT PROJECT,
PHASE 1 FOR THE TOTAL AMOUNT OF $146,000.00.
WHEREAS, the contract will provide professional design and engineering services
through construction documents and bidding phase for construction of Kenai Float
Plane Basin Development Project, Phase 1; and,
WHEREAS, the project will consist of design to realign the Fourth Avenue Access Road
into the Float Plane Basin parking area and the City water tank and other
improvements; and,
WHEREAS, Wince Corthell -Bryson Consulting Engineers previously provided
engineering and construction inspection services for the Kenai Municipal Airport
Taxiways F,G, 8s H Lighting, Grading Drainage Project; and,
WHEREAS, the recommendation from City Administration is to award the contract to
Wince Corthell-Bryson Consulting Engineers for the total cost of $146,000.00; and,
WHEREAS, award to Wince Corthell- Bryson Consulting Engineers would be in the
best interest of the City; and,
WHEREAS, sufficient monies are appropriated.
NOW, THEREFORE, BE IT RESOLVED BY THE COUNCIL OF THE CITY OF KENAI,
ALASKA, the contract for Kenai Float Plane Basin Development Project for the total
amount of $146,000.00.
PASSED BY THE COUNCIL OF THE CITY OF KENAI, ALASKA, this first day of
September, 2010.
ATTEST:
Carol L. Freas, City Clerk
Approved by Finance: 7
PAT PORTER, MAYOR
Contingent upon approval of Ordinance 2510 -2010
the aty o f
KENA� SKA
TO: Rick Koch, City Manager
FROM: Wayne Ogle, Public Works Director
DATE: August 25, 2010
Rick,
Village with a Past, Cc wcth a Future
210 Fidalgo Avenue, Kenai, Alaska 99611 -7794
Telephone: (907) 283 -7535, Ext. 236 FAX: (907) 283 -3014 1 1111!
MEMORANDUM
SUBJECT: MEMO IN SUPPORT OF A RESOLUTION AWARDING A
CONTRACT FOR DESIGN SERVICES; PHASE 1, FLOAT
PLANE BASIN DEVELOPMENT PROJECT
This resolution awards funds to Wince Corthell- Bryson Consulting Engineers for
the development of construction documents and bidding phase for the Kenai
Municipal Airport Float Plane Basin Development Project, Phase 1. The total
amount for this engineering is not to exceed $146,000.
The project will consist of realigning the 4 Avenue Access Road into the Float
Plane Basin parking area and the City water tank. There will also be construction
of approximately 1,200 linear feet of paved taxiway "S" from runway 1L to the
realigned access road and construction of approximately 1,600 linear feet of
paved taxiway "T". There will also be grading to improve drainage of
approximately 350,000 square feet of lease lot area, installing security fencing
and gates, painting taxiway markings, installing taxiway lights and signage and
providing for the installation of natural gas and power utilities. Provisions for the
future installation of water, sewer and telecommunications utilities are also to be
provided. Bid documents are expected to ready by April 1, 2011 with construction
during summer 2011.
Ordinance No. 2510 -2010 increased the estimated revenues and appropriations
in the Airport Improvement Capital Project Fund to complete design work for
Phase 1 of the Kenai Municipal Airport Float Plane Basin Development Project.
There are sufficient funds for this project.