HomeMy WebLinkAboutResolution No. 2004-28Suggested by: Administration
CITY OF KENAI
RESOLUTION NO. 2004-28
A RESOLUTION OF THE COUNCIL OF THE CITY OF KENAI, ALASKA, AWARDING
THE BID TO HANSEN PAINTING INC. FOR VINTAGE POINTE MANOR AND SENIOR
CENTER EXTERIOR STRIPPING AND PAINTING- 2004 FOR THE TOTAL AMOUNT OF
$165,000.
WHEREAS, the following bid was received on May 26, 2004:
BIDDER
Hansen Painting Inc.
BASIC BID
Vintage Pointe
Manor
$148,500
ADDITITVE
ALTERNATE
Senior Center
$16,500
TOTAL
$165,000
WHEREAS, Hansen Painting Inc.'s bid was the only bid received; and,
WHEREAS, Hansen Painting Inc.'s bid meets the bid specifications; and,
WHEREAS, the recommendation from the City Administration is to award the bid to
Hansen Painting Inc.; and,
WHEREAS, the Council of the City of Kenai has determined that Hansen Painting
Inc.'s bid is a responsible bid and award to this bidder would be in the best interest of
the City; and,
WHEREAS, sufficient monies are appropriated.
NOW, THEREFORE, BE IT RESOLVED BY THE COUNCIL OF THE CITY OF KENAI,
ALASKA, that the bid for Vintage Pointe Manor and Senior Center Exterior Stripping
and Painting - 2004 be awarded to Hansen Painting Inc. for the total amount of
$165,000.
PASSED BY THE COUNCIL OF THE CITY OF KENAI, ALASKA this second day of June
2004.
ATTEST:
Carol L. Freas, City Clerk
Approved by Finance: ..
CITY OF KENAI
210 FIDALGO AVE., SUITE 200 KENAI, ALASKA 99611-7794
TELEPHONE 907-283-7535
FAX 907-283-3014 ~
1992
M E MORAN DU M
To:
Through'
From'
Linda Snow, City Manager
Jack LaShot, Public Works Manager(~
Robert Springer, Building Official
Date: 5-27-04
Re:
Stripping and Repainting Senior Center
In the recent stripping and repainting bid project for the Vintage Pointe Manor we
included an additive alternate for stripping and repainting of the Senior Center.
This memo is to provide you with information on this project.
The five-year building maintenance schedule indicated the Senior Center building
be repainted in 2006, but since Vintage Pointe is going to be done this year we
included the Senior Center in this project as an additive alternate to the base bid.
The main reason to include the Senior Center now, is that the two buildings finish
would not match if they were not done as one project. By doing both buildings
now the cost to do the Senior Center is thought to be less than if we wait to do
the same project later.
With an administrative transfer we will have enough money left in this year's
budget to do the Senior Center now. I recommend it be done with the Vintage
Pointe project.