CITY OF KENAI
RESOLUTION NO. 2013 -53
A RESOLUTION OF THE COUNCIL OF THE CITY OF KENAI, ALASKA, AWARDING A
CONTRACT FOR THE CONSTRUCTION OF THE VEHICLE MAINTENANCE FACILITY
BASE BID AND ADDITIVE ALTERNATE NUMBER ONE TO BLAZY CONSTRUCTION,
INC. FOR AN ESTIMATED TOTAL COST OF $3,938,900.
WHEREAS, the following bids were received on May 29, 2013;
BIDDER
Base Bid
Add Alt 1
Total
Blazy Construction, Inc.
$3,833,000
$105,900
$3,938,900
Tunista Construction, LLC
$3,850,000
$89,826
$3,939,826
Engineers Estimate
$3,540,000
$100,000
$3,640,000
and,
WHEREAS, Blazy Construction Inc.'s bid is the lowest responsible bid and award to
this bidder would be in the best interest of the City; and,
WHEREAS, the recommendation from City Administration is to award the contract to
Blazy Construction Inc. for the total approximate cost of $3,938,900; and,
WHEREAS, sufficient monies are appropriated.
NOW, THEREFORE, BE IT RESOLVED BY THE COUNCIL OF THE CITY OF KENAI,
ALASKA, that the contract for the project entitled "Vehicle Maintenance Facility" be
awarded to Blazy Construction, Inc. for the approximate amount of $3,938,900.
PASSED BY THE COUNCIL OF THE CITY OF KENAI ALASKA this 3RD day of Jul
2013.
A 10� / III
40 � 40
a •. EyAwmwalm
7 A EST:
G�-� u✓
Sandra Modigh, City Clerk (�
Approved by Finance:
Contingent upon approval of Ordinance No. 2711 -2013
" "Villaye with a Past, C# with a Future
210 Fidalgo Avenue, Kenai, Alaska 99611 -7794 �a
Telephone: (907) 283 -7535, Ext. 236 / FAX: (907) 283 -3014 Illllt
1992
KE these LA K MEMORANDUM
KENAA\ SKA
TO: Rick Koch, City Manager I
FROM: Sean Wedemeyer, Public Works Director Srt'�
i.,/
DATE: June 26, 2013
SUBJECT: Resolution 2013 -53 Award of Contract for Vehicle Maintenance
Facility
Rick,
Please find attached Resolution 2013 -53 awarding the construction of the Vehicle
Maintenance Facility to Blazy Construction Inc. for the estimated total amount of
$3,938,900. This award is contingent upon approval of Ordinance No. 2711 -2013.
The project consists of constructing a new — 17,000 sq ft maintenance facility. Additive
Alternate One provides for a snowmelt system in the 10' apron outside the overhead
doors.